Project Description: The project covers an area of 94,855.28 square meters (about 142.28 mu), including 84,485.72 square meters for schools and 10369.56 square meters for municipal roads, with a total construction area of 59,500 square meters. Including: building 1 primary school complex, 1 primary school dormitory/canteen, 1 middle school complex, 1 middle school dormitory, 1 middle school canteen, 1 lecture hall, 1 stormy playground,/kloc.
Power supply and distribution, drainage, fire fighting and other supporting facilities.
Project construction fund: 308 million yuan, to be solved by financial funds.
Project construction period: July 2020 to August 20265438 +0.
Total project duration: 460 days, including 20 days of investigation; Design period: 35 days; Duration: 405 days.
Project location: north of Xingdong New District and Shengbei Street, east of Zhenxing Third Road, south of Elite Middle School and west of Xinhe Road in Xingtai East Station.