As the first batch of pilot projects for the renovation and upgrading of pedestrian streets in China, Beijing Road started to upgrade the municipal environment last year. Today, the agent construction project management center of Yuexiu District, Guangzhou, once again conducted public bidding for the renovation and upgrading project of Beijing Road Pedestrian Street.
This project involves the same road section as the first phase reconstruction, but the reconstruction scope is different. This project includes the northern section of Beijing Road (only 50m east of this reconstruction), the middle section of Beijing Road (excluding the height of building reconstruction below 7.5m), Xihu Road (excluding 40m south of Beijing intersection) and Yushan Road (building facade within 40-110m east of Beijing Road, excluding ground pavement).
The construction scope of this renovation project is around Beijing Road Pedestrian Street, and it is within the enclosed area consisting of Guangwei Road, Everbright Road, Zhongshan Road, Education Road, Fang Shu Street, Danan Road, Wen Ming Road, Fu Xue West Street, Zhongshan Road and Beijing Road, with an area of about 30 hectares. The project transformation involves building facade, landscape greening, pavement of road squares (including riding downstairs), sign guidance system, water supply and drainage improvement, electrical lighting improvement, traffic relief and so on. The total investment of the project is about1570,000 yuan.
The tender announcement shows that the renovation and upgrading of the building facade includes the renovation of the arcade and the renovation of general streets and lanes, including billboards, windows, pillars of the arcade and the ceiling of the corridor. Among them, the street length of arcade building reconstruction is 1000m, and the street length of general street building reconstruction is 51194 m.
At the same time, the surrounding landscape will be afforested, including 3,000 sets of three-dimensional hanging flowers, 20 groups of afforested landscapes, 190 tree pond, Big Buddha Temple Cultural Square, etc.
In terms of municipal road upgrading, the project will upgrade the pedestrian pavement by 5 165 square meters, transform the antique road pavement area by 29,443 square meters, and upgrade the motor vehicle pavement by 6,850 square meters. And set up 60 groups of urban street sketches, 5 groups of public art sketches, 75 trash cans and 66 sets of leisure seats along the street.
In order to improve the effect of night tour in Beijing Road business district, the project will also upgrade the street lighting, including upgrading the electric lighting along the street by 6 194 meters and installing 20 intelligent light poles. In order to further solve the drainage problem in the area, the project will also transform the water supply and drainage in the area, including building 2407 meters of rainwater pipe network and dredging 34 10 meters of sewage pipe network.
In view of the numerous historical buildings in Beijing Road area, this renovation project will set up 100 sets of historical and cultural signs and two sets of Buddhist theme signs for the convenience of tourists. In addition, the project will also transform 4,200 square meters of animation space to ease the surrounding traffic.
Renovation list:
1. Renovation and upgrading of building facade
(1) Renovation of Qilou Street. The contents include billboard renovation, window renovation, arcade column renovation, arcade ceiling renovation, window renovation, wall renovation, ceiling railing renovation and so on.
Reconstruction scope: 50 meters north of Beijing Road, 270 meters between Zhongshan Road and Xihu Road in the middle of Beijing Road, 2 10 meters north of Zhongshan Fifth Road (Guangda Road-Changxing Street) and 100 meters south of Wen Ming Road (Lido Hotel).
(2) general street reconstruction. The contents include billboard renovation, window renovation, window renovation and facade improvement.
Scope of renovation: both sides of Yushan Road, Huifu East Road (including Huixin East Street), Xihu Road (excluding 40 meters north of the first phase of+100 meters), Lee Seung-Hyun, Fu Xue West Street, Yuexiu Shuyuan Street, Libai Lane, Ming Sheng Square, Ma Xiao Station, Malaysia Station and Longzang Street.
(3) Roof renovation.
Scope of renovation: located at the top of the middle section of Beijing Road.
(4) vertical advertising signs.
Reconstruction scope: North section of Beijing Road, both sides of Zhongshan Road to Xihu Road in the middle section of Beijing Road, north of Zhongshan Fifth Road (Guangda Road-Changxing Street), north of Wen Ming Road and south of Wen Ming Road (Lido Hotel). Both sides of Yushan Road, Huifu East Road, Xihu Road (excluding 40 meters north of the first phase of the Great Buddha Temple+100 meters), Lee Seung-Hyun, Fu Xue West Street, Yuexiu Shuyuan Street, Libai Lane, Ming Sheng Square, Ma Xiao Station, Malaysia Station and Longzang Street.
(5) Reconstruction of drainage riser.
Reconstruction scope: North section of Beijing Road, both sides of Zhongshan Road to Xihu Road in the middle section of Beijing Road, north of Zhongshan Fifth Road (Guangda Road-Changxing Street), north of Wen Ming Road and south of Wen Ming Road (Lido Hotel). Both sides of Yushan Road, Huifu East Road, Xihu Road (excluding 40 meters north of the first phase of the Great Buddha Temple+100 meters), Lee Seung-Hyun, Fu Xue West Street, Yuexiu Shuyuan Street, Libai Lane, Ming Sheng Square, Ma Xiao Station, Malaysia Station and Longzang Street.
2. Landscape greening transformation: three-dimensional hanging flowers, combined flowerpot platform, street tree plant decoration, greening group landscape, tree pool transformation.
Reconstruction scope: It is distributed in Xihu Road, Huifu East Road, Lee Seung-Hyun, Huixin West Street, Longcang Street, Wen Ming Road, the arcade column in the north section of Beijing Road and the roof of the middle section of Beijing Road.
3. Renovation of water supply and drainage: Renovation of manhole covers and decorative manhole covers, adding rainwater pipe networks, dredging sewage pipes and replacing outdoor fire hydrants.
Conversion range:
(1) Drain cover plate: mainly located in Xihu Road Square and Ming Sheng Square.
(2) Newly built rainwater pipes: Yushan Road, Huifu East Road, Xihu Road, Lee Seung-Hyun, Fu Xue West Street, Yuexiu College Street, Libai Lane and Ming Sheng Square.
(3) Dredge sewage pipes: Yushan Road, Huifu East Road, Xihu Road, Lee Seung-Hyun, Fu Xue West Street, Yuexiu Shuyuan Street, Libai Lane, Ming Sheng Square, Wen Ming Road, Ma Xiao Station and Malaysia Station.
(4) Decorative manhole cover: in the sections of Yushan Road, Huifu East Road, Xihu Road, Lee Seung-Hyun, Fu Xue West Street, Yuexiu Shuyuan Street, Libai Lane, Ming Sheng Square, Wen Ming Road, Ma Xiao Station, Malaysia Station and Longzang Street.
(5) Outdoor fire hydrant replacement: it is distributed in Yushan Road, Huifu East Road, Xihu Road, Lee Seung-Hyun, Fu Xue West Street, Yuexiu College Street, Libai Lane, Ming Sheng Square, Wen Ming Road, Ma Xiao Station, Dama Station and Longzang Street.
4. Municipal road upgrading: pedestrian pavement upgrading, antique pavement upgrading, motor vehicle pavement upgrading, granite kerb and granite slab stone.
Scope of renovation: West Lake Road, alleys around West Lake Road, arcade pavement in the middle section of Beijing Road, Lee Seung-Hyun, Fu Xue West Street, Yuexiu Shuyuan Street, Libai Lane, Ming Sheng Square, Wen Ming Road, Ma Xiao Station, Malaysia Station, Longcang Street and Huixin West Street (including back streets and alleys such as Huixin East Street).
5. Electric lighting: lighting improvement. ?
Reconstruction scope: North section of Beijing Road, both sides of Zhongshan Road to Xihu Road in the middle section of Beijing Road, north of Zhongshan Fifth Road (Guangda Road-Changxing Street), north of Wen Ming Road and south of Wen Ming Road (Lido Hotel). Both sides of Yushan Road, Huifu East Road, Xihu Road (excluding 40 meters north of the first phase of the Great Buddha Temple+100 meters), Lee Seung-Hyun, Fu Xue West Street, Yuexiu Shuyuan Street, Libai Lane, Ming Sheng Square, Ma Xiao Station, Malaysia Station and Longzang Street.
6. Identification system: historical and cultural identification and guiding identification.
Reconstruction scope: North section of Beijing Road, both sides of Zhongshan Road to Xihu Road in the middle section of Beijing Road, north of Zhongshan Fifth Road (Guangda Road-Changxing Street), north of Wen Ming Road and south of Wen Ming Road (Lido Hotel). Both sides of Yushan Road, Huifu East Road, Xihu Road (excluding 40 meters north of the first phase of the Great Buddha Temple+100 meters), Lee Seung-Hyun, Fu Xue West Street, Yuexiu Shuyuan Street, Libai Lane, Ming Sheng Square, Ma Xiao Station, Malaysia Station and Longzang Street.
7. Traffic relief.
Reconstruction scope: North section of Beijing Road, Zhongshan Road to Xihu Road in the middle section of Beijing Road, north of Zhongshan Fifth Road (Guangda Road-Changxing Street), north of Wen Ming Road, south of Wen Ming Road (Lido Hotel), Yushan Road, Huifu East Road, Xihu Road, Lee Seung-Hyun, Fu Xue West Street, Yuexiu College Street, Libai Lane, Ming Sheng Square, Ma Xiao Station, Malaysia Station and Longzang Street.
Project progress, the whole construction period of this project is 9 months, that is, the preliminary work will start on June 5438+ 10, 2020, and it will be completed, accepted and put into use at the end of September 2020. In order to ensure the timely completion of the project, the project schedule is relatively compact. In the actual implementation process, all the work can be carried out in parallel, and attention should be paid to the connection between interrelated work, and each working procedure should be interspersed as much as possible to save time to the greatest extent.
Project construction progress:
Preliminary work:? 2020 1 to March 2020;
Civil engineering:? April 2020 to September 30, 2020; Key construction period requirements: the main streets of Beijing Road, including Yushan Road, Xihu Road and Huifu East Road, will be completed before June 30, 2020. It was fully completed on September 30, 2020.
Completion acceptance:? September 2020.