1. The Project Department shall make unified arrangements for temporary electricity utilization on site, and determine the replacement of required leakage protector, failed leakage protection and aging cable according to the actual situation on site.
2. The Project Department manages the temporary electricity consumption on the construction site in a unified way, and implements the system of examination and approval for electricity consumption of the construction team of the Project Department. It is forbidden to connect privately.
3, the preparation of temporary electricity construction organization design, site maintenance electrician should strictly implement the "JGJ46-2005" and "JGJ59-99 standard" three-phase five-wire system, completes the equipment shell protection and zero grounding, adhere to the electrician inspection and maintenance work, and fill in the records carefully.
4. Configure according to "three-level control and two-level protection". The last switch box ensures "one machine leaks", and the switch box should have rain-proof and dust-proof facilities.
5. Correct selection of the location of the power distribution room is of great significance to the rational layout, safe operation and improvement of power supply quality of the power supply and distribution system on the construction site. The distribution room should be as close as possible to the load center, so as to reduce the length of the distribution line and the cross section of the conductor, and try to avoid places where dust, humidity and high temperature vibrate, so as to prevent the erosion of the conductive parts and insulating parts of the distribution device by dust, humidity and high temperature and the influence of vibration on the operation of the distribution device. The distribution room should not be located directly below the place where water is easy to accumulate.
6, equipment grounding, zero and leakage protection device, electrician should be installed according to the specification requirements, and the implementation of regular monitoring and telemetry inspection.
7. When working under or on one side of the erection line, warning signs should be hung to ensure that the safe working distance stipulated by the state cannot meet the requirements, and protective fences and fences must be set up.
8, the project department belongs to the construction group electrician must organize regular training, after passing the exam, to show certificates.
9. "Three-phase five-wire system" must be adopted for power supply on the construction site. TN-S zero protection system must be adopted for direct grounding power supply of neutral point of special transformer. When the construction site and external power supply lines share the same power supply system, electrical equipment should be protected by zero connection or protective grounding as required, but some equipment should not be protected by zero connection and the other part should be protected by grounding.
10, all kinds of electrical equipment should be equipped with special switches and bolts, bolts should have special protective grounding and contacts. It is forbidden to connect the conductive contact to the ground contact by mistake.
1 1. Overhead power supply lines must be laid with insulated wires, special poles supported by insulators, cement poles, wooden poles or along the wall. Tension insulators must be installed for pole cables. It is forbidden to erect power supply lines on trees and scaffolding.
12. Overhead lines on the construction site shall be installed outside the slewing radius of the boom. If this requirement cannot be met, protective frames must be erected or other measures must be taken.
13, it is forbidden to use unqualified safety devices and moldy wires. The power cable of all mobile electrical equipment should be disconnected from the whole site, and the external insulation layer should be free from mechanical damage.
14. The horizontal safe distance between power overhead lines and buildings or temporary facilities under construction shall at least keep the values listed in the table below. If it is difficult to keep the above-mentioned safe distance according to the actual situation, technical measures should be taken for protection, and construction can only be carried out with the consent of the relevant power departments.
15, switch box must strictly implement the system of "one machine, one box, one brake and one leakage switch", and it is forbidden to directly control two or more electrical equipment including sockets with the same switch. It is forbidden to store anything in the switch box, and the door should be locked, with rain-proof and moisture-proof measures.
16. When removing lines at the construction site, the power supply must be cut off first, and it is forbidden to leave wires that may be charged.
65438+
General requirements for electricians:
1. Operators must be electricians who have received professional safety technical knowledge training and assessment, obtained operation certificates for special types of work and held relevant certificates. (within the validity period).
2. Operators must undergo entrance safety education and training, and can only work at their posts after passing the examination.
3. The electrician must be operated by one person and supervised by one person. Operators must wear insulated shoes, and hang power outage maintenance signs after power outage inspection before operation;
4. When entering the construction site, you must wear a qualified safety helmet, fasten your chin strap and lock your belt buckle. When working high above the ground, you must fasten the qualified safety belt, which should be hung firmly, hung high and used low.
5. Enter the construction site, don't smoke, don't drink and operate, don't chase and play, don't take off their posts, don't operate mechanical and electrical equipment that has nothing to do with them, and strictly abide by various safety operation procedures and labor disciplines.
6. When entering the job site, first check and be familiar with the working environment. If unsafe factors and hidden dangers are found, they must be reported to the relevant departments in time, and the construction work can be carried out only after the rectification is confirmed. In the process of construction, the hidden dangers endangering personal safety should be stopped immediately, and the relevant departments should be required to deal with them in time.
7. Study hard professional safety technical knowledge, love their jobs, develop good professional ethics, establish the idea of serving the front line of production, and ensure the safe use of electricity.
8. Strictly implement the relevant regulations and standards for safe electricity use, obey the safety management, do not operate illegally, refuse to direct illegally, and stop others from operating illegally in time.
9. Live working is prohibited. When switch operation and maintenance are needed, it must be approved by relevant departments of the project department. Organizational measures and technical measures for safe electricity use shall be implemented during operation, and electrical equipment, facilities and lines shall not be dismantled by themselves. In strict accordance with the standards, construction organization design and disclosure requirements.
10. Conduct routine patrol inspection of on-site electrical equipment, facilities and lines twice a day. If any problem is found, it should be repaired and monitored without power in time, and reported to the relevant leaders for handling. All equipment, facilities and lines should be protected in place. Equipment and facilities should be kept clean and effective.