Second-level constructor's examination questions style
Among the second-level constructor examination subjects, the first subject "Construction Management of Building Engineering" and the second subject "Regulations and Related Knowledge of Building Engineering" are objective questions, that is, they are all multiple-choice questions, and the answers are subject to the answer sheet filled out; Subject 3 "Professional Engineering Management and Practice" includes objective questions (multiple choice questions 40 points) and subjective questions (case analysis 80 points, written answers on the test paper).

Here is a set of 20 1 1 year secondary constructor's "Construction Management" test paper. Try to do it!

Go to the battlefield tomorrow, and I wish you good grades in the exam!

1. Multiple choice questions (70 questions in total, each with 1 point, and only 1 option in each question best meets the meaning of the question)

1.A unit plans to build a new audio-visual education center. After the design bidding, Design Institute B will undertake the design task of this project. Among the following objectives, the one that does not belong to the project management objective of Design Institute B is ().

A. Project investment objectives

B. Design progress target

C. Construction quality objectives

D. Design cost objectives

2. A general contracting management mode of building engineering construction, in which the secondary decoration project is contracted out by the construction unit to the secondary unit. In the construction, unit B shall directly accept the operation instruction of ().

A. structural unit

B. Design unit

C. Construction general contracting management enterprise

D. Construction contracting enterprises

3, the use of project structure diagram to decompose the construction project, the decomposition of project structure should be combined with the deployment of the whole construction project, and combined with () to be adopted.

A. Organizational structure

B. Engineering procedures

C. Functional structure

D. Contract structure

4. The organization chart in the construction management of the construction project reflects ().

A. Logical relationship between components in the project management team

B. Organizational relationship between components in the project

C. Organizational relationship among departments in the project management team

D. Logical relationship between components in the project

5. According to Code for Valuation with Bill of Quantities of Construction Projects (GB50500-2008), the comprehensive unit price of partial projects provided by the bidder does not include ().

A. expenses

B. Profit

C. Management fees

D. Direct engineering cost

6. Prepare the construction management task division table, which involves the following matters: ① determine the work tasks of the work department or individual; ② Project management task decomposition; (3) Prepare the task division table. The correct programming step is ().

A.①②③

B.②①③

C.③②①

D.②③①

7, about workflow and workflow diagram, the correct is ()

A. The owner and project participants are consistent in the broadcast workflow task.

B. The task of workflow organization is to prepare the organization chart.

C. Workflow diagram can be used to describe workflow organization.

D. The logical relationship between workshops is represented by bidirectional arrow lines in the work flow chart.

68. According to the Construction Contract of Construction Project (Presentation of Foreign Exchange Text) (GF-99-020 1), if the impact of interference events on the construction project lasts for a long time, the contractor shall submit it within a reasonable time interval according to the requirements of the supervision engineer ().

A. Notice of intention to claim

B. Basis of interlocutory claims

C. Interlocutory claim report

D. List of claims

69, project professional and technical director to organize relevant personnel to acceptance of pile foundation engineering, should be signed by () acceptance opinions and acceptance conclusion, and sign and seal.

A. Builders of construction enterprises

B. Professional supervision engineer

C. project professional and technical person in charge

D. Personnel of the construction unit participating in the acceptance.

70, about the management of construction documents, the correct is ().

A. The engineering subcontracting enterprise shall file the engineering documents formed by the unit and hand them over to the construction unit in time.

B. For a construction project composed of multiple unit projects, the project documents shall be filed as a construction project.

The construction enterprise shall hand over the relevant project files to the construction unit before the project is completed and accepted.

Engineering documents can be written in pure blue ink.

Second, multiple-choice questions (a total of 25 questions, 2 points for each question, 2 or more options for each question meet the meaning of the question, at least 1 wrong item, wrong choice, this question does not score; Choose one less item, and add 0.5 points for each item)

7 1, the following project management work, belongs to the contractor's project management tasks are ().

A. Construction quality control

B. Construction cost control

C. Construction progress control

D. Personnel management of subcontractors

E. Building safety management

72, about the division of construction management functions, the correct ().

A. The functions of the management function division table are completely consistent with the job description.

Different management functions can be undertaken by different functional departments.

C each participant in the project should prepare their own division of management functions.

The division of management functions can be used for enterprise management and project management.

E. The division of management functions only reflects the tasks of the project manager and project technical director.

73, division (disciplines) the main contents of the engineering construction organization design are ().

A. Overview of construction projects

B. Selection of construction methods

C. Selection of construction machinery

D. Labor demand plan

E. Safety construction measures

74, according to the "construction project management standard" (GB/T50326-2006), the construction enterprise project manager in the process of project construction management, should have the authority ().

A. participate in project bidding, tendering and contract signing.

B. Developing internal compensation system

C. participate in the establishment of the project management department

D. select the establishment unit.

E. Selecting subcontractors

75, the following construction enterprises control measures for the use of construction machinery, the correct one is ().

A. Try to reduce the machine idleness caused by improper arrangement.

B. Strengthen on-site scheduling of machinery to avoid slowdown.

C. Try to choose newly developed new mechanical equipment.

D. Strengthen the maintenance of machinery

E. coordinate and cooperate with the crew and auxiliary production personnel on board.

76, building engineering construction quality does not meet the requirements, the correct treatment method is ().

A the inspection lot of reworked or replaced appliances and equipment shall be re-accepted.

B inspection lots that meet the design requirements after being tested and identified by qualified testing units shall be accepted.

C inspection lots that fail to meet the design requirements after inspection and appraisal by qualified inspection units, but can meet the structural safety and use functions after accounting and approval by the original design unit, can be accepted.

D. The repaired or reinforced subdivisional and divisional works can still meet the requirements of safe use despite the changes in overall dimensions, and can be accepted according to the technical treatment plan and negotiation documents.

E. After repair or reinforcement, sub-projects that still cannot meet the requirements for safe use should be used at a lower safety level after identification.

95, about the construction safety management tasks, the correct ()

A. Construction scheme design is the main content of construction safety management scheme.

B. The construction team shall have part-time security officers.

C. Management and control of construction safety mainly focus on manpower, material resources and environment in construction activities.

D. Creating a safe and civilized demonstration site is one of the main contents of implementing the construction safety management objectives.

E. All construction projects shall formulate individual safety technical schemes and measures.