First, smt patch preparation process:

1, ejector pin: the technician holds the finished ejector pin plate and puts it in the corresponding position in the machine. After the PCB board is completely positioned, put the ejector pin into the ejector pin position marked by the white paint pen, check whether there is a gap between the ejector pin and the PCB board, and then start production.

2. Check the air pressure of the machine: check whether the air supply is normal (0.4-0.6kmpa) before pasting. If the air pressure is abnormal, solve it in time and don't turn it on.

3. Boot: Turn the main switch to turn on the main power of the machine until the machine starts normally.

4. Start the mounter program: open the MARK5 program on the desktop and enter the machine working interface.

5. Preheating: Select "Preheating" in the main menu "Application", and the general preheating time is 10 minute. Repair can only be carried out after preheating is completed.

Second, choose SMT patch program:

1, select the file opening option under "File", find the file corresponding to PCB and open it.

2. Enter "pcb editing" mode, select "Step", move the camera to the random patch component, and observe whether the component coordinates are offset from those in the program. If there is any deviation, please adjust the program. If there is no deviation, you can enter the "production" mode.

3. After entering the production mode, click Finish --" PCB download. Click "Start" when finished, and then press the green start button on the fuselage, and the machine will automatically paste normally.

Third, smt patch quality supervision:

The first piece of smt paste should be confirmed by quality inspection, and mass production can only be carried out after the board surface is confirmed to be free of defects such as parts, wrong parts and deviations. When the first piece is found to be wrong, the machine should be adjusted in time and the wrong piece should be corrected manually. Then adjust the position of smt mounter components to the best copy state.

Four. Precautions for patch:

1, when an alarm occurs in the process of pasting, the operator should check the fault in time and solve it in time.

2. When replacing materials, be careful not to install the wrong materials.

3. After 3.smt mounting is completed, exit the program and close the mounter. Feida, which needs to be removed, is put on the special shelf of Feida. Finally, do a good job of cleaning.

4. When making φ5 monochrome 64×32 PCB, it is necessary to install thimbles at the bottom of PCB to prevent PCB from sinking due to gravity.