Model essay on summary and reflection report of electric shock emergency drill (6 selected articles) (1) 1. Hazard source
Electrical leakage of switch box, distribution box, generator, line and pumping unit.
Storage location: job site
Second, the possibility of accidents.
There are many possibilities for personal electric shock at the construction site. For example, the operators are not skilled in operation, have poor safety awareness, the circuit switch is installed on the zero line, the cable connector is not wrapped or improperly wrapped, and the cable line is aged and mopped (especially when there is water in the well site) and placed on the operation equipment, derrick, pumping unit, tubing, etc. All these may lead to electric shock accidents.
Third, the accident state:
An electric shock accident is likely to lead to the death of the electrocuted person.
Fourth, the emergency command system
1, command telephone
2, the rescue team list and division of labor
Group length:
Responsibilities: Be fully responsible for accident command, handling and communication.
Deputy team leader:
Responsibilities: Assist the team leader to command and handle accidents. Team member: Responsibilities: On-site emergency rescue.
Verb (abbreviation of verb) emergency measures for accidents
When personal electric shock occurs in the construction well site, personnel should be organized to rescue immediately.
1, that is, cut off the power supply. If you can't cut off the power supply, you can't directly pull the body of the electrocuted person by hand. You must connect the power cord with a dry wooden stick or insulator, or stand on a dry wooden board or wear insulating rubber shoes, and then pull the person who got an electric shock with one hand to be rescued from the power supply (and send someone to call to report at the same time).
2, after getting an electric shock, did not lose consciousness, the wounded should be carried to a warm and ventilated place to rest.
3, coma after electric shock and has lost consciousness, but still breathing the wounded, should also be carried to a warm and ventilated place to rest. If it is found that the wounded have difficulty breathing or gradually weaken, mouth-to-mouth resuscitation or chest compression in supine position must be carried out.
4. After getting an electric shock, if the breathing and pulse are very weak or stop, but still can't be considered dead, mouth-to-mouth resuscitation and chest compressions should be implemented immediately for rescue until the medical staff give first aid.
Precautionary measures of intransitive verbs
1. The team members on the construction site are equipped with communication tools.
2. Each class is equipped with a test pen. Before using electrical appliances and starting the pumping unit, the electricity must be checked with a test pen, and insulating gloves must be worn when opening the switch. Insulating gloves are not allowed to be used for other purposes.
3, strengthen the training of post personnel, improve their technical level and practical operation ability.
4, formulate and improve the management system, clear job responsibilities, team leaders and cadres should always check and supervise the implementation of the system.
5, team, team should be in accordance with the provisions, safety inspection of power lines, found bare, aging, mopping the floor, etc. Rectification should be made in time before use.
6, all employees should strengthen the training of first aid methods, so that employees can adopt effective rescue measures for the injured.
Seven, the nearest hospital
XXXX
Eight, evacuation location:
outside
IX. Help ensure
1, communication guarantee:
2, safety protection:
Insulating gloves 1 pair
Insulating rod 1 first aid kit 1.
Fire extinguishers: 35kg2, 8kg4 (fire extinguishers are checked once a month), fire buckets, 2 fire shovels, 2 beds of asbestos quilts: 2.
Model essay on summary and reflection report of electric shock emergency drill (6 selected articles) (2) 1. Responsible for the scene, its task is to understand and master the accident situation, organize on-site rescue command.
Two, responsible for liaison, its task is to arrange on-site rescue in time according to the command of the headquarters, and keep in touch with the local construction administrative departments and labor departments.
Three, responsible for maintaining the order of the scene, do a good job of the parties, the surrounding people's inquiry records.
Four, responsible for properly handling the aftermath, according to the functions of centralized responsible for maintaining communication with local authorities.
Verb (abbreviation of verb) Emergency measures for electric shock accident 1. On-site personnel should decisively disconnect from the power supply, cut off the power supply (close the circuit) as soon as possible, or use the insulation materials and other equipment obtained on site to separate the electric shock personnel from the charged body. 2, the injured immediately out of danger, organize personnel to rescue. 5. If it is found that the electrocuted person stops breathing or breathing, the injured person will lie on his back on a flat or flat surface and breathe immediately or press the extracorporeal heart at the same time. Call 120 immediately to get in touch with the local emergency center (the hospital is nearby and sent directly to the hospital). The location and severity of the accident should specify the contact telephone number of the department in detail and send someone to meet at the intersection. 4. Report the accident to the emergency rescue leading group of the affiliated project management department and the project management department of the group for support.
Six, maintain order at the scene, closely protect the scene of the accident. Fourth, first-aid supplies: standing medicines: disinfection supplies, first-aid supplies (bandages, sterile dressings) and various commonly used small splints, stretchers, hemostatic bags and oxygen bags.
Seven. Communication contact hospital rescue center: 120 Fei Jing: 1 10 fire alarm: 1 19 on-site duty phone: relevant person in charge phone: project leader: mobile phone: security officer: mobile phone: technical leader: mobile phone:
Eight. Precautions 1. Never pull the electrocuted person by hand when the electrocuted person is not powered off. 2. When an accident happens, we should organize personnel to do all-out rescue, call 120 emergency number according to the situation, and immediately notify the relevant person in charge. 3, pay attention to protect the scene of the accident, easy to investigate and analyze the cause of the accident. 4, cardiopulmonary resuscitation rescue measures should adhere to the continuous (including on the way to the hospital) can't give up.
Model essay on summary and reflection report of electric shock emergency drill (6 selected articles) (3) This plan is specially formulated to strengthen the company's safety management, standardize production site management and operation behavior, effectively prevent and reduce losses caused by accidents, and rescue accidents in time.
First, emergency preparedness.
1. Organization and responsibilities
1. 1 emergency rescue leading group
Team leader: Deputy General Manager
Deputy leader: safety supervisor and production manager.
Team members: workshop director and monitor.
Duty phone: xxxx
1.2 The leading group consists of emergency rescue group (team leader: workshop supervisor 1), communication liaison group (team leader: human resources manager), evacuation guidance group (team leader: workshop director), safety alert group (team leader: security team leader) and logistics support group (team leader: purchasing manager, logistics manager and electromechanical section chief), with members from
The accident emergency rescue leading group is responsible for the emergency treatment of electric shock accidents at the production site.
2. Training and exercises
2. 1 The production department is responsible for hosting and organizing the workshop to conduct a simulation drill once a year according to the requirements of "emergency" of electric shock accidents.
2.2 Each team member should cooperate to complete the drill according to their respective responsibilities.
After the drill, the team leader will organize to evaluate the effectiveness of the Emergency Response and adjust or update the requirements of the Emergency Response when necessary.
2.3 Records of drills, evaluations and updates shall be kept.
2.4 The safety supervisor and deputy supervisor are responsible for training relevant personnel once a year.
2.5 The safety committee is responsible for checking the establishment of emergency plan and rescue system.
3. Preparation, maintenance and maintenance of emergency materials
3. 1 emergency materials preparation: simple stretcher, medicines for falls and bandages.
3.2 All kinds of emergency materials should be prepared, and daily management should be strengthened.
Second, the emergency response
1. Remove the power supply for symptomatic rescue. When an electric shock accident occurs, first disconnect the electric shock victim from the power supply. The key to quick first aid is "quick".
2. For low-voltage electric shock accidents, the following methods can be used to get the electric shock person out of the power supply.
2. 1 If there is a power switch or plug near the electric shock site, you can immediately pull down the power switch or unplug the power plug to cut off the power supply.
2.2 Electrical pliers with insulated handle, axe with dry wood handle and shovel with dry wood handle can be used to cut off the power cord. Insulators such as dry boards can also be inserted under the electric shock to isolate the power supply.
2.3 When the electric wire is placed on the electrocuted person or pressed under him, dry clothes, gloves, ropes, boards, sticks and other insulators can also be used as tools to pull, lift or open the electric wire, so that the electrocuted person can be separated from the power supply. Never pull the electric shock directly.
3. For high-voltage electric shock accidents, the following methods can be used to make the electric shock person out of the power supply:
3. 1 immediately notify the relevant departments of the power outage.
3.2 Wear insulating gloves and shoes, and turn on the switch in turn with insulating tools of corresponding voltage levels.
3.3 Open the wire of the person who gets an electric shock with a high-voltage insulating rod.
4. If the person who gets an electric shock gets an electric shock when working at high altitude, when disconnecting the power supply, it is necessary to prevent the person who gets an electric shock from falling and causing secondary injuries.
4. 1 If the electric shock victim is not seriously injured, conscious, but a little flustered, numb limbs, or general weakness, or the electric shock victim was once in a coma, but has recovered, he should rest quietly, don't move around, and take him to the hospital under close observation.
4.2 If the electric shock victim is seriously injured and unconscious, but his heart is beating and his breathing is still there, he should be carried to a place with fresh air, unbuttoned, let the electric shock victim lie on his back, and put soft clothes under his body to make his head slightly lower than his shoulders, so as not to hinder his breathing. If the weather is cold, he should pay attention to keep warm and send it to the hospital quickly. If it is found that the person who gets an electric shock has difficulty breathing and convulsions, he should prepare for rescue immediately after his heart stops beating or breathing stops.
4.3 If the electric shock victim is seriously injured, and his breathing stops or his heart stops beating or both, mouth-to-mouth resuscitation and chest compressions should be carried out immediately and sent to the hospital. On the way to the hospital, you shouldn't stop the rescue. Many people who were electrocuted died on their way to the hospital.
4.4 People will suffer from nerve paralysis, respiratory interruption, cardiac arrest and coma after getting an electric shock, which is usually suspended animation and must not be lightly regarded as "dead".
4.5 For those who get an electric shock, especially those who fall from high altitude, special attention should be paid to handling. Many people who get an electric shock, in addition to electric injuries, also have falls and injuries. Improper handling, such as a broken rib plunged into the heart, may lead to death.
4.6 For those who have been electrocuted by suspended animation, they should be rescued quickly and permanently. Many people who got an electric shock were rescued after four hours or more. Only after the doctor diagnosed the death did the rescue stop.
5. Artificial respiration is a first-aid method applied after the person who gets an electric shock stops breathing. Among all kinds of artificial respiration methods, mouth-to-mouth breathing is the best.
5. 1 Before artificial respiration, collars, tops, etc. Food, broken teeth, blood clots, mucus, etc. that hinder breathing on the person who gets an electric shock should be quickly untied. Take out the thing that hinders breathing in your mouth, so as not to block the respiratory tract and make the electrocuted person lie on his back, and make his head fully buckled (you can hold the electrocuted person's neck with one hand), and his nostrils should be upward to facilitate breathing.
5.2 Ambulancemen put their hands over the nostrils of the person who got an electric shock, and after taking a deep breath, blow inward near the mouth of the person who got an electric shock for about 2 seconds. The size of blowing varies according to the person who gets an electric shock, and it is advisable to slightly bulge the chest of the person who gets an electric shock every time he exhales.
5.3 After blowing, leave the mouth of the electrocuted person immediately, relax the nose of the electrocuted person, and let the air exhale for about 3 seconds. Then repeat the blowing action. Blow evenly, about 12 times per minute. After the electrocuted person has started breathing freely, you should also carefully observe whether breathing stops again. If it stops again, artificial respiration should be continued. At this point, artificial respiration should conform to the weak free breathing law of the electric shock.
5.4 If you can't make the person who gets an electric shock open his mouth, you can use mouth-to-mouth artificial respiration, that is, bite your mouth tightly and blow close to your nostrils.
6. Chest compressions are the first-aid methods for people who get an electric shock after their hearts stop beating.
6. 1 When doing chest extrusion, make the person who gets an electric shock lie on his back in a relatively solid place, and the posture is the same as mouth-to-mouth artificial respiration. The rescuer kneels on one side or both sides of the waist of the electrocuted person, with his hands folded, and the palm root placed above the heart socket and one-third to one-half below the sternum. Press the palm root downward (backward direction) to force the blood out of the heart. Adults should squeeze 3 ~ 5 cm, once a second, too fast and the effect is not good, and it is appropriate to squeeze 60 times a minute. After squeezing, the palm root is quickly and completely relaxed, so that the chest of the electric shock person can recover automatically and the blood can fill the heart. You don't have to leave your chest completely when you relax.
6.2 It should be pointed out that heart beating and breathing are not related. The heart has stopped beating and breathing is about to stop. Breathing has stopped and the heart won't last long. Once breathing and heartbeat stop, mouth-to-mouth resuscitation and chest compressions should be performed at the same time. If there is only one person on the scene to rescue, the two methods will be carried out alternately. You can squeeze it four times and then blow it once, and the speed of blowing and squeezing should be increased to avoid reducing the rescue effect.
Three. Post-accident treatment
1. Find out the cause of the accident and the responsible person.
2. Write a report to the site in written form, including the time and place of the accident, the names of the casualties, gender, age, type of work, degree of injury and injured parts.
3. Formulate effective preventive measures to prevent such accidents from happening again.
4. Organize all personnel to carry out accident education.
5. Announce the accident results and the handling opinions of the person in charge to all personnel.
Fourth, the end of the plan.
1. After the completion of this plan, the person in charge who originally released the startup plan will announce the end of the plan and report to the General Manager.
2. Evaluate the implementation of the plan within 7 days after the end of the plan.
The moderator of the evaluation meeting shall determine according to the accident level and management authority, and the evaluation report shall be submitted to the general manager. The general accident review meeting shall be presided over by the safety specialist, and the major and extraordinarily serious accident review meeting shall be presided over by the personnel designated by the company.
3. The evaluation of the scheme is to judge whether it is inconsistent, not to discriminate against objective factors. The assessment focuses on:
3. 1 Whether the planned time limit has been implemented.
3.2 Whether the units and departments involved in the implementation of the plan carry out their work according to the requirements of the plan, whether there are omissions or faults, and who is responsible.
3.3 Whether the managers and leaders involved in the implementation of the plan organize the work according to the provisions of the plan, whether there are omissions and faults, and who is responsible.
3.4 Whether and how to modify the emergency plan.
The evaluation department shall be responsible for the authenticity and conformity of the evaluation report. For the departments and personnel who are at fault in the implementation of the plan, the safety Committee should clearly criticize the responsible person and punish those who are serious and at fault. After the Security Committee puts forward the handling opinions, it will report to the personnel cadres for approval step by step according to the jurisdiction.
Model essay on summary and reflection report of electric shock emergency drill (6 selected articles) (4) According to the basic requirements of "safe installation, complete disassembly, correct use and timely maintenance" for safe electricity use, the operation requirements for preventing electric shock injury are as follows:
1, it is forbidden for non-electricians to disassemble and connect electrical lines, plugs, sockets, electrical equipment, lamps, etc.
2. Before using electrical equipment, you must check whether the lines, plugs, sockets and leakage protection devices are in good condition.
3, electrical wiring or mechanical failure, should find an electrician to deal with, the electrician shall not repair or troubleshooting. When inspecting and repairing the distribution box and switch box, the corresponding power switch at the next higher level must be cut off, and a power outage sign board should be hung. Live working is prohibited.
4. When using hand-held motors such as vibrators for wet operation, electricians should turn on the power supply and install leakage protectors. Before work, operators must wear insulating shoes and gloves.
5, relocation or mobile electrical equipment must first cut off the power supply.
6. When handling metal objects such as steel bars and steel pipes, it is forbidden to touch wires.
7. It is forbidden to hang dry items on the wires.
8. It is forbidden to use the illuminator for baking and heating, and it is forbidden to use high-power electrical appliances such as electric furnaces without authorization.
9. Stop transmission when working near overhead transmission lines. When there is no power failure, isolation measures should be taken to keep a safe distance and prevent touching.
10, the wire must be overhead, and it is not allowed to drag on the ground and the construction surface at will. If it is necessary to cross the ground and the construction face, it should be protected by crossing the road, and materials, vehicles and personnel are not allowed to crush the wires.
Summary and reflection report on the model essay of electric shock emergency drill (selected 6 articles) (Chapter 5) Electric shock accident is a common accident in highway bridge construction. It is also the main type of personal injury and death accidents in enterprises. Judging from the final injury degree of the electric shock victim, if the electric shock victim is rescued in time and in the right way, it is very likely to be rescued. The purpose of preparing the emergency plan for electric shock accident is to try our best to rescue the injured from the death line and reduce the casualties of the accident to a minimum.
I. Scope of application of the plan
This emergency plan is applicable to all employees involved in the production of this project. When there is an electric shock accident in the workplace, they should be responsible for the emergency rescue of others. In case of electric shock accident in other places, undertake the obligation of emergency rescue for foreigners.
Second, simulate the exercise situation
Suppose that the electric shock accident occurred in the residence of the project department in this contract section, and the staff of a project department accidentally touched the exposed wires, resulting in electric shock and falling to the ground, which is very important.
Third, the time of the exercise.
The exercise time is scheduled for July 9th at 20XX. 10: 00 am.
Iv. Planning organization and responsibilities:
1, organize emergency drills for electric shock accidents (commander in chief)
Commander in chief: xxx
Main responsibilities:
First, be fully responsible for on-site emergency work;
B, decided to start the emergency plan;
C, command emergency work.
Deputy commander: xx, xxx
Main responsibilities:
First, organize emergency work;
B, coordinate the unified scheduling of all departments;
C, responsible for investigation, monitoring and the determination of the first aid plan.
2, each group of personnel:
Accident investigation team: xx
Medical rescue group: xx
Alarm contact group: xx
Logistics Support Group: xx
Field operation group: xx
Responsibilities of each group:
(1) Accident investigation team: protect the site and investigate the accident.
(2) Medical rescue team: The main task is to rush to the scene of the accident in time to rescue the electric shock personnel, and decide to give first aid at the scene or the nearest hospital according to the injury to ensure the safety of personnel.
(3) Alert Liaison Group: The main task is to upload and issue leadership instructions, divert traffic routes, and send people to meet at intersections.
(4) Logistics Support Group: The main task is to obey the instructions of the commanding leader, arrange the dispatch of rescue vehicles and timely supply of emergency funds.
(5) On-site operation group: conduct on-site emergency rescue, understand the cause of the accident, and report the on-site situation to the project manager at the first time.
Verb (abbreviation for verb) practice program:
1, 10:00, the staff of a project department accidentally stepped on the exposed wire, resulting in electric shock. Zhang Wei, a colleague passing by, immediately found a dry wooden stick to pull the wire away from the injured and called for help. Li Enmin, the foreman, rushed to the scene immediately after hearing the cry for help, and immediately reported to the project manager after a preliminary understanding of the situation and injury. Immediately after receiving the call, xxx started the emergency plan and rushed to the scene.
2. 10:03xxx arrived at the scene of the accident, knew the situation, immediately called the electrician to disconnect the master brake, and to prevent the damage from expanding, informed the surrounding onlookers to evacuate the scene.
3. 10:05, the medical rescue team arrived at the scene and immediately inspected the injured. When the injured person is found to be seriously injured, "mouth-to-mouth artificial respiration" and "chest compression" should be taken immediately to give first aid to the electric shock personnel.
4. 10:07, the alert liaison team arrived at the scene and immediately set up warning lines and warning signs at the main intersections to ensure the smooth rescue passage.
5. 10:09, the accident investigation team arrived at the scene, and the accident investigation team protected and obtained evidence at the scene of the accident and directed the rescue;
6. 10: 10 The injuries of the injured were initially controlled, and xxx sent a warning liaison team to the intersection to meet the emergency ambulance.
7. 10: 15 the logistics support team led the emergency ambulance to the scene to take the injured to the hospital. Xxx sent xx to the hospital to contact the family members to do a good job of appeasement, leaving the accident investigation team to see if there are other hidden dangers at the scene. The alert personnel should do a good job of site protection and wait for the accident investigation.
8. After the rescue, xxx reports the accident to the resident office, the director's office and the headquarters.
Sixth, the end.
Xx announced the end of the drill.
Seven. comment
The leaders of the General Director's Office, the headquarters and the quality supervision station gave instructions and comments on the shortcomings and missing links in the exercise.
Eight. abstract
Through this drill, all our construction workers will be more clear about the rescue procedures of the emergency rescue plan. In order to deal with emergencies, the orderly implementation of emergency plans was ensured, time was gained for rescue, and the purpose of drills was achieved.
Model essay on summary and reflection report of electric shock emergency drill (selected 6 articles) (6 articles) This plan is specially formulated in order to improve the emergency rescue ability of the project department, effectively deal with unexpected accidents, establish and improve a scientific, effective and well-functioning emergency rescue system, test the actual combat effect of emergency departments, and organize emergency rescue drills of electric shock accidents in the project department.
1. The guiding ideology and purpose of the drill is to implement the policy of "safety first, prevention first and comprehensive treatment", establish and improve the emergency management system of the project department, form an emergency system with unified leadership, timely response, scientific decision-making and orderly disposal, and comprehensively improve the ability of the project department to deal with emergencies and risks. By setting up emergency drills for accidents, the feasibility and operability of the emergency rescue plan of our project department are tested, the actual ability of emergency rescue and disaster relief is improved, the overall level of emergency rescue work of our company is continuously improved, and the life and property safety of employees in the project department is effectively guaranteed.
Second, the exercise time, place and participating units
(1) The drill time is scheduled for June 29th, 20XX.
(2) The drill site is the construction site of Fangjiashan Project Department.
(3) Units and personnel participating in the exercise
1. Project department leaders: general manager, quality assurance manager, HSE department manager, and managers of various construction teams.
2, safety personnel, team members, ambulance drivers, nurses.
Three. Accident setting Accident setting: At 9: 30am on June 29th, 20XX, employee XXX was cutting, and the third-level distribution box was electrified due to insulation aging of power cord. At that time, another employee XXX got an electric shock when he opened the door of the distribution box, and the employee was in a coma after getting an electric shock. The situation is very critical. Employees who are engaged in cutting operations should take immediate measures to give first aid and report to the HSE Department.
IV. Exercise Procedures and Division of Tasks
(1) Personnel arrangement
1, Chief Commander: Project General Manager, Deputy Chief Commander: Quality Assurance Manager
2. Team members: other leaders of the management department, managers of various departments, and heads of construction teams/factories of various disciplines.
3. Participants: safety officials, team members, ambulance drivers, nurses, ambulance personnel and general office personnel.
4. Recording and photographing: HSE management office staff and comprehensive office staff.
(2) Exercise: Electric shock rescue
(3), preliminary preparation:
1, building safety knowledge and common sense of electric shock prevention window publicity; (HSE Department and General Office are responsible)
2. Inspect the temporary electricity facilities on site; (The electrician class of the engineering department is responsible)
3. The site layout of the field exercise. (HSE Department and each construction team are responsible)
(4) Specific arrangements for electric shock rescue:
1, assemble the participants of the exercise;
2. Clean up the site and prepare tools;
3. Listen to the opinions of safety management personnel.
4. Start practicing. When employee XXX was cutting, the third-level distribution box was electrified due to the aging insulation of the power cord, which caused another employee XXX to get an electric shock when opening the door of the distribution box. After the accident, all participating units should carry out rescue according to the following procedures and assigned tasks.
1) At 9: 30, the employee got an electric shock. After discovering the accident, the cutting personnel immediately went to the gate to pull down the switch, and quickly carried out on-site first aid, and telephoned HSE department personnel and superior leaders. After receiving the report; the HSE department shall immediately organize personnel for rescue and report of the superior.
2) At 9: 38, the rescue vehicles and ambulance personnel of HSE Department arrived at the scene for first aid treatment;
3) At 9: 40, the project general manager or quality assurance manager rushed to the scene of the accident after receiving the report, and simulated and informed the county safety production supervision and management bureau and the competent department of the county construction bureau;
4) At 9: 45, carry the electric shock personnel to the ambulance and send them to the hospital for examination and treatment.
5. Main exercises:
1) The on-site construction team switches the switch while reporting;
2) Rescue by cardiopulmonary resuscitation and other methods at the scene;
3) Send the wounded to the hospital for examination and treatment;
6. End of the exercise (announced);
7. Clean up the scene.
Five, exercise command and rescue operation organization system and responsibilities
According to the Emergency Preparedness and Response Control Procedure, the organizational system and responsibilities of emergency rescue command and rescue operation for major accidents are as follows:
Commander-in-Chief: the general manager of the project, responsible for overall command.
Deputy Chief Commander (on-site command): Quality assurance manager, responsible for the command of the construction site.
(1) medical rescue team: responsible for the safe evacuation of field personnel, transporting the injured to the hospital for treatment, and guarding the accident area.
(2) Information Liaison Group: responsible for the communication and external contact at the scene of the accident.