2. Before the business line is rebuilt, the construction unit shall conduct a detailed investigation on the working environment and conditions of the job site according to the track design documents, and formulate a safe construction plan.
Three, the construction unit shall, according to the approved construction plan, 72 hours before the formal construction, should put forward the construction plan, construction site and scope of influence to the equipment management unit. After receiving the construction request, the equipment management unit should check the influence scope of the construction plan and plan, and send someone to supervise the construction safety.
Four, before the construction, the equipment management unit should actively assist the design and construction units to check the existing equipment, and provide the accurate location of underground pipelines, wires, cables and other hidden facilities. When the accurate location cannot be provided, the design unit and the construction and equipment management unit will jointly explore and verify, plan the protection scope, sign a safety agreement, and clarify the safety responsibilities of all parties.
5. During the construction period, the construction unit shall take reliable protective measures for the existing equipment in the construction area that affects the construction operation.
Six, the reconstruction of the business line should be submitted for approval in accordance with the provisions of the construction plan, please point, protection, operation, acceptance, opening and transfer.