Step 1: The construction unit shall, within 7 days from the date of obtaining the construction permit, file the fire protection design with the fire department of the public security organ for the renovation project of the training institution that needs fire protection design.
Step 2: After the fire protection design is put on record, determine the spot check object through the preset spot check procedure in the fire protection design filing and acceptance system. The construction project that is not shown in the drawing should keep the printed "record voucher" for future reference. The pumped construction unit shall, within 5 days from the date of receiving the Record Certificate, provide relevant materials in accordance with the requirements of fire protection design review and acceptance, submit materials to the fire control institutions of public security organs, and conduct spot checks on fire protection design.
Step 3: The fire department of the public security organ shall, within the specified time limit, conduct drawing review and on-site inspection on the materials submitted by the selected construction unit in accordance with the national fire technical standards and norms, and the inspection results shall be published in the fire protection design and completion acceptance filing and acceptance system. If the inspection is unqualified, the Notice of Unqualified Record Inspection of Fire Protection Design of Construction Project shall be made according to law to inform the existing problems and order them to make corrections. Those who pass the inspection and pass the audit shall obtain the Public Security Fire Protection "Filing Inspection Opinion".