1 The total cost of civil installation project is less than 2 million yuan, and the total cost from 3 ‰ to 5 ‰ is not less than 2,500 yuan. The reinforcement shall be calculated separately.
The total cost of the civil installation project below 23 million yuan is 2.5‰~4‰, and the steel bar extraction is counted separately.
3. The total cost of civil installation project is less than 5 million yuan, and the total cost is 2.5 ‰ ~ 4 ‰, which shall be calculated separately.
4. The total cost of civil installation project is 5-20 million yuan, and the total cost is 2.5 ‰-4 ‰, which shall be calculated separately.
The total cost of the civil installation project below 55,000 yuan is 2.5‰~4‰, and the reinforcement is calculated separately.
6. The total cost of civil installation project is more than 50 million yuan, and the total cost is 2‰~4‰, and the steel bar is calculated separately.
7 decoration project budget total cost of 3‰~5‰ is not less than 3000 yuan.
8. The total budget cost of the garden construction project is 3‰~5‰ and not less than 3,000 yuan, and the reinforcement is counted separately.
9. The total cost of greening project budget is 3%~4‰, not less than 3,000 yuan.
The estimated total cost of 10 project is 2‰~4‰, and not less than 3,000 yuan.
1 1 The total budgeted cost of lightning protection project for electrical installation is 2.5%~3‰, and not less than 3,000 yuan.
12 the total budget for fire water supply and drainage, heating and ventilation is 2.5‰~3‰, not less than 3,000 yuan.
Second, the whole project cost service: 2%~5% of the total investment in construction and installation.
Third, the project settlement service:
1. The total settlement price of basic service fee is less than100000 yuan, and the total cost is 2‰~4‰ and not less than 3000 yuan. The total settlement price100000 yuan, and the total cost 1‰~3‰.
2. 8%~20% of the settlement audit incentive fee shall be agreed upon by both parties according to the increase or decrease.
3. 3‰~ 1% of the total cost of decoration project settlement shall not be less than 3,000 yuan.
4. The total cost of fire water supply and drainage and HVAC settlement is 3‰~6‰, and not less than 654.38+10,000 yuan.
5. The total settlement cost of lightning protection project for electrical installation is 3‰~6‰, and not less than 654.38+10,000 yuan.
4. Calculation of reinforcement quantity (reinforcement drawing): more than 500 tons, 5~8 yuan/ton, not less than 2,500 yuan, which will be calculated separately after checking (the above charging standards are for reference only).
Project investment budget
Project budget is a plan for the income and expenditure of the project in a certain period in the future. It can evaluate the investment of the project and reflect the economic effect of the project through monetary form. It is the basis for strengthening enterprise management, conducting economic accounting, assessing project cost and making construction plans. It is also the main basis for bidding quotation and determining the project cost.