Schedule of bored pile project: the main workload of this project is bored pile 140 cubic meters, deep mixing pile for foundation pit reinforcement 1452 cubic meters, root pile of 700.5m, earthwork excavation 10570 cubic meters, and slope support construction of 79 cubic meters; The 24-hour working system is adopted, and the planned construction period is 90 days. After the contract is signed, we will immediately organize personnel to conduct regular survey and pay-off.