Current location - Education and Training Encyclopedia - Graduation thesis - Bohai Bay Pollution Discharge Regulations
Bohai Bay Pollution Discharge Regulations
Discharge Standard for Oily Sewage in Offshore Oil Development Industry (GB49 14-85)

This standard is formulated to implement the Law of the People's Republic of China on the Protection of Marine Environment and prevent the environmental pollution caused by oily sewage from offshore oil development.

This standard is applicable to all enterprises, institutions, operators and individuals engaged in offshore oil development in all sea areas under the jurisdiction of People's Republic of China (PRC).

1 classification of standards

Oily sewage from offshore oil development industry refers to the oil production process sewage discharged from fixed sewage outlets after being treated on the oil production platform.

The discharge standard of oily sewage in offshore oil development industry is divided into two levels.

Grade I: It is suitable for Liaodong Bay, Bohai Bay, Laizhou Bay and Beibu Gulf, special marine protected areas designated by the state, and coastal scenic spots within equidistant shore 10 nautical mile.

Grade II: Applicable to the sea areas beyond the scope of application of Grade I standard.

2 standard value

The maximum allowable concentration of oily sewage discharge standard for offshore oil development industry shall comply with the provisions in Table 1. Mg/l

Allowable value of monthly average at project level

Oil grade 30 45

Secondary petroleum 50 75

Oil production process sewage should be reinjected into the formation to reduce sewage discharge.

Oily sewage from offshore oil development industry located in intertidal zone shall be subject to GB 3550-83 Discharge Standard of Water Pollutants for Oil Development Industry.

3 implementation and monitoring of standards

3. 1 From the date of implementation of this standard, the oil production platform that has started construction will immediately implement this standard. The existing oil production platforms shall implement Class II standard values from the date of implementation of this standard, and one year later, they shall be implemented according to the provisions of this standard.

3.2 For the oil production platform, monitoring sampling points should be set in the process sewage outfalls, and the environmental monitoring institutions of offshore oil enterprises are responsible for daily monitoring.

3.3 The monitoring and analysis methods of this standard shall be implemented with reference to Analysis Methods of Oily Sewage in Offshore Oil Development Industry.

Additional notes:

This standard was put forward by the Ministry of Urban and Rural Construction and Environmental Protection of People's Republic of China (PRC).

This standard was drafted by the writing group of Discharge Standard for Oily Sewage in Offshore Oil Development Industry.

This standard is entrusted to the State Oceanic Administration and the Ministry of Petroleum Industry for interpretation.

Comprehensive wastewater discharge standard

/view/ 12962 10.htm,

Liaoning has greatly raised sewage discharge standards.

/HPS/85/200807 1 1/ 105754557 . html

Tianjin local standard

DB 12/356—2008

Comprehensive wastewater discharge standard

1 range

This standard specifies the definition, technical content and monitoring provisions of comprehensive wastewater discharge standard.

This standard is applicable to the management of water pollutant discharge of sewage units, construction projects and environmental impact assessment of construction projects within the jurisdiction of Tianjin.

Design, completion and acceptance of environmental protection facilities and emission management after commissioning.

2 normative reference documents

The clauses contained in the following documents become the clauses of this standard by reference in this standard. For dated reference documents, all subsequent documents

The revised table (excluding errata) and the revised version of this standard are not applicable. However, all parties who have reached an agreement based on this standard are encouraged to study this standard.

Investigate whether the latest versions of these files can be used. For undated reference documents, the latest edition is applicable to this standard.

GB 3097- 1997 seawater quality standard

GB 3838-2002 Environmental Quality Standard for Surface Water

Water quality. Determination of ammonium. Distillation and titration.

Water quality. Determination of ammonium. Nessler's reagent colorimetry.

Water quality-Determination of five-day biochemical oxygen demand (BOD5)-Dilution and inoculation method

GB 8978- 1996 integrated wastewater discharge standard

Gb/t11893-1989 determination of total phosphorus in water-ammonium molybdate spectrophotometric method

Gb/t11901-1989 gravimetric method for determination of suspended solids in water.

Gb/t11914-1989 determination of chemical oxygen demand in water-dichromate method.

GB 18466-2005 Discharge Standard for Water Pollutants in Medical Institutions

GB 189 18-2002 Pollutant Discharge Standard for Urban Sewage Treatment Plants

HJ/T 86-2002 Determination of Biochemical Oxygen Demand in Water Quality Rapid Determination by Microbial Sensor

Methods for monitoring and analysis of water and wastewater (fourth edition) Determination of chemical oxygen demand of water quality (China Environmental Science Press, 2002)

Fast closed catalytic digestion method (including spectrophotometry)

Reply of the State Council on Tianjin Urban Master Plan (Guo Han [2006] No.62)

Tianjin Urban Master Plan (2005 -2020)

Interpretation of on-site inspection and monitoring methods of pollutant discharge announced by the Ministry of Environmental ProtectionNo. 16 of the State Environmental Protection Administration in 2007

3 definition

The following definitions apply to this standard.

3. 1 wastewater

Refers to the water discharged in the process of production, work and life.

3.2 Urban Municipal Sewage Treatment Plant Urban Sewage Treatment Plant Drainage

Refers to the service object located in the central city of Binhai New Area 1 1 in the Tianjin Urban Master Plan (2005 -2020).

GB 189 18 Drainage of Urban Sewage Treatment Plants in New Urban Areas.

3.3 Urban Sewage Treatment Plant Urban Sewage Treatment Plant Drainage

Refers to the drainage of urban sewage treatment plants defined in GB 189 18, except "drainage of urban sewage treatment plants" defined in this standard.

3.4 Rural sewage treatment plant drainage

Refers to the drainage of sewage treatment plants that only receive rural domestic sewage.

3.5 Industrial Park Sewage Treatment Plant Industrial Park Sewage Treatment Plant Drainage

Refers to the drainage of sewage treatment plants in various industrial parks, development zones and livestock and poultry breeding communities that mainly receive and treat production sewage.

DB 12/ 356—2008

2

3.6 Medical tissue wastewater generated by medical institutions

Refers to the sewage of medical institutions defined in GB 18466.

3.7 Other wastewater

Refers to the sewage other than the sewage from sewage treatment plants and medical institutions listed in 3.2 to 3.5 of this standard.

3.8 displacement

Refers to the discharge of water directly used for process production in the production process. Excluding indirect cooling water, factory boiler and power station drainage.

4 technical content

4. 1 Standard Classification and Limits

4. 1. 1 urban sewage treatment plant drainage

4. 1. 1. 1 The drainage of newly-built and expanded urban sewage treatment plants shall meet the first-class standard A in GB 189 18.

4. 1. 1.2 The completed urban sewage treatment plant was reformed, and the drainage met the first-class standard B of GB 189 18 "Discharge Standard of Water Pollutants".

Quasi. "

4. 1. 1.3 The drainage of the completed urban sewage treatment plant should reach the Water Pollutant Discharge Standard I in GB 189 18 before 2010/2.

Class b standard. "

4. 1.2 Drainage of urban sewage treatment plant

4. 1.2. 1 The drainage of newly-built (including reconstruction and expansion) urban sewage treatment plants shall meet the Class I B standard of GB 189 18 "Discharge Standard of Water Pollutants".

Quasi. "

4. 1.2.2 The drainage of the completed urban sewage treatment plant should reach the Water Pollutant Discharge Standard I in GB 189 18 before 2010/2.

Class b standard. "

4. 1.3 Drainage of rural sewage treatment plants

4. 1.3. 1 The drainage of newly-built (including reconstruction and expansion) rural sewage treatment plants shall meet the second-class standard in GB 189 18.

4. 1.3.2 The drainage of the completed rural sewage treatment plant should reach the Water Pollutant Discharge Standard II in GB 189 18 before 2010/2.

Level standard ".

4. 1.4 Drainage of sewage treatment plant in industrial park

4. 1.4. 1 The drainage of sewage treatment plants in newly-built (including reconstruction and expansion) industrial parks shall meet the first-class standard of GB 189 18 Discharge Standard for Water Pollutants.

B standard ".

4. 1.4.2 The drainage of the sewage treatment plant in the completed industrial park should reach the Discharge Standard of Water Pollutants in GB 189 18 before 2010/2.

Quasi-first-class standard B standard ".

4. 1.5 Sewage from medical institutions

4. 1.5. 1 Sewage discharged from medical institutions in the water collection system of sewage treatment plants listed in this standard (medical treatment of infectious diseases and tuberculosis)

Except institutions), the total phosphorus shall meet the relevant requirements of this standard 4. 1.6. 1, and other projects shall meet the relevant requirements of GB 18466.

4.1.5.24.1.5.1The chemical oxygen demand, biochemical oxygen demand,

Suspended solids, ammonia nitrogen and total phosphorus shall meet the relevant requirements of 4. 1.6.3 and 4. 1.6.4 of this standard, and other items shall meet the relevant requirements of GB 18466.

4. 1.6 Other sewage

This standard is divided into three grades according to different discharge directions and different functions of sewage.

4. 1.6. 1 The sewage discharged into the water collection system of each sewage treatment plant listed in this standard is subject to Grade III standard, and the limit values are shown in Table 1.

Table 1 Maximum allowable pollutant discharge concentration unit: mg/L (unless otherwise specified)

Serial number pollutant or project name primary standard secondary standard tertiary standard

1 suspended solids (SS)

2 Five-day BOD 10 20 300

3 chemical oxygen demand 50 60 500

4 ammonia nitrogen (calculated as nitrogen) 5 8 35

5 Total phosphorus 0.5 1.0 3.0

DB 12/ 356—2008

three

4. 1.6.2 The sewage not discharged or discharged into the water collection system by the sewage treatment plants listed in this standard shall be discharged according to the effluent of the drainage system.

The function of water body shall meet the requirements of 4. 1.6.3 and 4. 1.6.4 of this standard respectively.

4. 1.6.3 The sewage receiving water bodies of the drainage system are Class IV water bodies in GB3838 and Class II and III sea sewage in GB3097.

See table 1 for standards and limits.

4. 1.6.4 The receiving water bodies of the effluent from the drainage system are Class V water bodies in GB3838 and Class IV sea sewage in GB3097, and the secondary standards are implemented.

See table 1 for values.

4.2 Other terms and conditions

4.2. 1 Items not listed in this standard shall meet the corresponding requirements of GB8978; If there are industry standards, they shall conform to the relevant industry standards.

Rules.

4.2.2 The maximum allowable discharge of some industries shall comply with the relevant provisions of this standard, and the discharge limits are shown in Table 2. Strictly speaking, it is not listed in this standard.

Table 5 in GB8978 or relevant industry standards and relevant provisions on cleaner production shall be implemented.

Table 2 Maximum allowable displacement of some industries

Maximum allowable displacement of industrial projects

1. Steelmaking

A. converter wastewater quantity, m3/t steel ≤0.7

B continuous casting wastewater, m3/t steel ≤0.5.

C. Electric furnace waste water quantity, m3/t steel ≤ 1.2.

2. Hot rolling

Waste water quantity of plate/belt, m3/t product ≤2.0.

Steel pipe wastewater, m3/t product ≤2.0.

Iron and steel wastewater, m3/t product ≤ 1.5.

Wire rod wastewater, m3/t product ≤ 1.2.

3. Sintering

Sintering, m3/t product ≤0.005.

Particles, m3/t product ≤0.002

4. Cold rolling

Strip wastewater, m3/t product ≤ 1.5.

5. Ironmaking

steel

industry

steel complex

Waste water quantity, m3/t product ≤ 1.5.

The amount of industrial wastewater produced by processing tons of crude oil in the oil refining industry is t water /t crude oil ≤ 1.0.

1. Oily sewage

Single displacement, kg/ton of raw materials ≤40

2. Sulfur-containing sewage

atmospheric and vacuum distillation unit

Single displacement, kg/ton of raw materials ≤35

1. Oily sewage

Slag content ratio

Single replacement, kg/ton of raw materials

≤ 160 ≤ 160 ≤200

2. Sulfur-containing sewage

Slag content ratio

& lt35% 35%-70% ≥70%

petroleum

petroleum refining industry

catalytic cracking unit

Single replacement, kg/ton of raw materials

≤ 120 ≤ 120 ≤ 120

DB 12/ 356—2008

four

Table 2 (continued)

Maximum allowable displacement of industrial projects

Ammonia steaming section

Output of waste water from ammonia distillation (t/t clean coal) ≤0.50.

coke

industry

Coking industry

The amount of wastewater (t/t coke) in front of phenol-cyanogen wastewater treatment station is ≤ 1.5.

automobile

app; application

Output of automobile painting wastewater (m3/m2) ≤0. 1.

fire coal

power plant

The recovery rate of industrial wastewater from coal-fired power plants is ≥90%.

petroleum

meat processing industry

Single discharge of industrial wastewater from petroleum processing industry (ton of water/ton of crude oil) is 0.5- 1.0.

4.2.3 Units under construction (including renovation and expansion) (excluding all kinds of sewage treatment plants listed in this standard) and water pollution from the date of promulgation of this standard.

The discharge of dyes must meet this standard; Units that have been built (including reconstruction and expansion) on the date of promulgation of this standard (excluding all types listed in this standard)

Sewage treatment plant), the discharge of water pollutants is 20 10- 1, and this standard shall be implemented; To the date of promulgation, the standard is still under construction (including changes,

Expansion) units (excluding all kinds of sewage treatment plants listed in this standard), the time for discharging water pollutants shall be subject to the approval date of the environmental protection completion acceptance report.

This standard shall be implemented one year after the date of promulgation. The construction time of the construction (including renovation and expansion) unit shall be subject to the approval date of the environmental impact report (form).

Division; The completion time of the construction (including reconstruction and expansion) unit shall be subject to the approval date of the environmental protection completion acceptance report.

4.2.4 The meaning of "receiving water body"

4.2.4. 1 If the sewage is directly discharged into the water body listed in the water environment function zoning, the water body shall be regarded as the receiving water body of sewage.

4.2.4.2 sewage is discharged into the water body that is not included in the water environmental function zoning, but this water body is connected with other water bodies that are included in the water environmental function zoning.

Or there is communication, the water body that has been first input into the water environment functional zoning is the receiving water body. Not included in the water environment function zoning.

In the water body, and the water body is not connected or communicated with other water bodies listed in the water environment functional zoning, it is forbidden to build new sewage outlets in this area.

Existing sewage outlets should be closed before June 65438+1 October12009.

4.2.5 The sewage receiving water body is the sewage control area (meaning that the domestic and production wastewater is relatively concentrated, and the receiving wastewater has little impact on the water environment).

In the waters with great adverse effects, according to the actual situation of Tianjin, namely, two artificially excavated sewage channels in the north and south), the sewage discharge shall be carried out in accordance with GB 189 18.

In the first-class standard B standard of water pollutant discharge standard.

5 monitoring

5. 1 sampling point

The relevant provisions of clause 5. 1 in GB 8978- 1996 shall be implemented.

5.2 sampling frequency

Clause 5.2 in GB 8978- 1996 and announcementNo. 16 of the State Environmental Protection Administration in 2007 "On-site inspection by environmental protection departments" shall be implemented.

Explain the relevant provisions of pollution monitoring methods in the investigation.

5.3 displacement

The relevant provisions of clause 5.3 in GB 8978- 1996 shall be implemented.

5.4 statistics

The relevant provisions of clause 5.4 in GB 8978- 1996 shall be implemented.

5.5 Analysis method

The analysis method can refer to the methods listed in Table 3.

DB 12/ 356—2008

five

Table 3 Analysis Methods

Standard Notes on Determination Method of Serial Number Items

1 suspended solids gravimetric method GB/T 1 190 1

Dilution inoculation method GB/T 7488

2 biochemical oxygen demand (BOD5)

Rapid determination method of microbial sensor HJ/T86-2002

Dichromate method GB/T 1 19 14

3 chemical oxygen demand

Fast closed catalytic digestion method (including spectrophotometry)

Monitoring and analysis methods of water and wastewater (fourth edition)

China Environmental Science Press (2002)

Distillation and titration GB/T 7478

4 ammonia nitrogen (in N)

Nessler's reagent colorimetry GB/T 7479

5 total ammonium phosphomolybdate spectrophotometry GB/T 1 1893

Note: The latest edition is applicable to this standard.