Pmc job responsibilities 1 Pmc are usually divided into two positions: PC and MC.
PC (Product Control): namely, production planning, production control and production control. Taiwan-funded Japanese-funded enterprises are commonly known as production management, and state-owned enterprises are commonly known as production scheduling. The main functions are to make enterprise resource planning (MRPII, including the demand planning of materials, human resources and machinery and equipment), review the delivery date, set the master production plan, close the work order, solve production anomalies, and control the inventory of finished products and semi-finished products. The key and difficult point of production management is to make master production plan and solve abnormal production.
MC (Material Control): that is, material planning and material control, commonly known as material control/material management, and Taiwan-funded and Japanese-funded enterprises are also called materials. The main function is to make material plan, picking plan, feeding plan and inventory plan according to production plan, and implement and control related plans. The key and difficult point of material control is the implementation of feeding plan and proper inventory.
It can be seen that PMC is the command center of modern enterprise production and operation, and all activities and even resource preparation of enterprises revolve around PMC (such as whether it is necessary to purchase machines to expand production capacity, whether it is necessary to recruit new employees, whether it is necessary to work overtime, and the demand, allocation, arrival and inventory level of materials, etc.). ).
Pmc job responsibilities 2 1, according to the daily production plan of the workshop, arrange the material plan, supply the production line materials in time to ensure balanced production;
2. Track and supervise the implementation scenarios of the production plan, analyze the production capacity and load, adjust the plan in time, and implement it after being approved by the superior leaders;
3. Participate in the production coordination meeting and weekly meeting, truthfully report the implementation of the production plan and put forward effective suggestions;
4, according to the daily production records submitted by the workshop, update the summary production report and equipment operation records;
5. Responsible for monitoring and tracking material progress and material loss; Inventory control, waste prevention, control and treatment;
6. Coordinate the work progress and cohesion of all departments, and put forward the adjustment of time and work of each working procedure in the workshop;
7, product quality, quantity and timeliness statistical analysis report, report to the leadership within the prescribed time limit.
Pmc job responsibilities 3 1. Arrangement and scheduling of production plan, tracking and control of production materials, and delivery arrangement of finished products.
2. Arrangement and scheduling of material demand plan and improvement of inventory turnover rate.
3. Standing materials and non-material plans and material changes.
4. Supervise the implementation of production plan and material demand plan, coordinate production, and ensure the smooth progress of production.
5. Statistics and analysis of production scenarios, such as production capacity, qualified rate, standard working hours and equipment failure rate.
6. Cooperate with the development of the company, reduce the cost for the company and strictly implement JIT.
Pmc job responsibilities 4 1. The main responsibilities of the production manager are:
1, formulate and distribute feasible and effective production plans and production schedules to reduce downtime;
2. Analyze and count the capacity load of each machining center;
3. Track the production process and coordinate the production progress;
4, statistical production data of each processing center, for each department to query.
5. Hold a production meeting to coordinate and arrange the production processes of various departments;
Second, the main responsibilities of the material manager are:
1, statistics and grasp the material situation, and provide it to other departments in the factory at any time.
2. Prepare the material budget, prepare the material demand table for procurement, and provide it to the purchasing department to arrange material procurement.
3. Regularly summarize material changes, make logistics plans and control material inventory;
4. Analyze the products according to the plate-making samples and operation standard books, and formulate the standards for the use of materials;
5. Make statistics on material consumption and loss on a regular basis, make cost evaluation, and have the right to take reasonable measures against waste in production.
Pmc job responsibilities 5 1. Review, prepare and audit annual, quarterly and monthly production plans according to the company's sales forecast and sales orders;
2, according to the production plan, make material demand plan;
3. Supervise the procurement process and track the arrival of materials;
4, supervise the daily warehouse safety inventory and material inventory cycle;
5. Effectively control the procurement cost;
6. Track the implementation of the production plan and assist in handling abnormal production situations;
7, temporary tasks assigned by the superior
Pmc job responsibilities 6 1. Be responsible for making and maintaining the annual master production plan, and provide the basic basis for the company's production and operation.
1. 1 presided over the review of customer orders or sales of "2+4" marketing content, and worked out the master production plan for 1-3 months;
1.2 Review the master production plan every week to ensure the' dynamic consistency' between the master production plan and the market state;
1.3 according to the master production plan, analyze the balance between production capacity and market demand, and put forward the labor demand and equipment demand plan;
2. Responsible for organizing production planners, making monthly, weekly and daily production plans according to the master production plan, issuing production task instructions, and supervising and summarizing the implementation of production plans;
3. According to the production capacity and process load, be responsible for analyzing the delivery date of new orders in cooperation with the production department and feeding back to the sales department in time;
4. Analyze the production data, summarize the efficiency and loss level, and put forward rectification management suggestions;
5. According to the production plan, organize the material planner to make the material plan and delivery plan, supervise the implementation of the material plan and delivery plan, and ensure the smooth progress of production activities;
6. Supervise the inventory quantity of raw materials, embryo socks and finished products, and coordinate sales, procurement and other functional departments to control inventory in a regular way to reduce resource occupation;
Pmc job responsibilities 7 1. Make the staff of this department fully understand the business philosophy of the company and the company's iso9000 series quality policy, and earnestly implement it.
2. Design the post responsibilities and corresponding relations of the staff in subordinate departments, and guide, coordinate, supervise and assess whether subordinates actively carry out their work in accordance with regulations and procedures.
3. Prepare the department's management system, quality documents, operating procedures and other document systems, and participate in the formulation of relevant procedures and materials.
4. Sales order review and capacity load dynamic balance analysis.
5. When the production capacity is limited, the planning, control and time cost analysis of outsourcing (outsourcing).
6. Arrangement, organization and implementation of production plan.
7. Arrangement, organization and implementation of 7.mrp.
8. Prepare the safety stock plan and prepare the file system.
9. Handle and solve production anomalies in time.
10. Train, communicate and coordinate the personnel of this department.
1 1. Manage the resources and property of the department to ensure that the working environment conforms to "5s".
12. Report to the manager or vice president in charge of production, and represent the production manager in his absence.
Pmc job responsibilities 8 1, responsible for the daily management of warehouse and PMC;
2. Be responsible for preparing the program documents, workflow and related form design related to the department;
3. Be responsible for preparing the monthly work plan and monthly work summary of the department;
4. Be responsible for making the scheduling plan and updating it weekly;
5. Be responsible for reviewing the material demand plan and controlling the arrival time and quantity of materials in combination with the production scheduling plan;
6. Be responsible for tracking the progress of materials, and issue a material shortage report to relevant departments for tracking every day;
7. Be responsible for the examination and approval of warehouse receipts and warehouse receipts, and supervise whether warehouse receipts and warehouse receipts are executed as planned;
8, responsible for each order, statistics of the actual material consumption of each order report to the finance department;
9, responsible for organizing the monthly physical inventory work;
10, list the "material list" and "scrap list" according to the monthly inventory results, and make corresponding treatment according to the examination and approval opinions;
1 1, responsible for the supervision of supplier returns;
12, responsible for warehouse operation safety, fire safety and anti-theft management;
13, responsible for the rational layout of the warehouse site and the implementation of "5S" management and assessment;
14, responsible for the training and assessment of department personnel;
Responsible for completing other tasks assigned by superiors.
Pmc job responsibilities 9 pmc merchandiser
1, order review and production order preparation.
2. Establish customer information and be responsible for communication and coordination with customers.
3. Establish monthly transportation statistics.
4. Shipping and delivery arrangements.
5. Track materials and production progress.
6. The implementation and control of material plan.
7. Production scheduling.
8. Follow up guest complaints.
9. Balance supply and demand.
Pmc procurement
1. Establish supplier evaluation data and price records.
2. Processing, inquiry, price comparison, negotiation and ordering.
3. Delivery schedule control and overdue tracking.
4. Treatment of abnormal feed quality and quantity.
5. Assist in arranging and auditing accounts payable.
6. Supplier evaluation report.
Pmc clerk
1, attendance and overtime application of department personnel.
2. Distribution, sorting and classified storage of departmental documents.
3. Prepare documents (such as internal copy, meeting minutes, etc. ).
4. Receipt, distribution and circulation of documents.
5, warehouse monthly report finishing.
6. Procurement and storage of office supplies required by department personnel.
7. Complete the work assigned by the superior.
Pmc statistician
1, statistics of production efficiency and working hours loss of each department every day.
2. Statistics of the production progress of plastic department and assembly department.
3, statistics monthly production material loss and the cost rate of poor incoming materials.
4. Weekly summary of warehousing, shipment and assembly of finished products, and weekly production details of assembly line, processing and packaging.
5, statistics in and out of raw materials.
6, employee assessment statistics.
7. Classification and classified storage of reports and documents.
8. Obey and complete the arrangement of the superior.
Pmc warehouse supervisor
1. Plan the storage area of the warehouse.
2. Responsible for the arrangement of warehouse management.
3. Responsible for the monthly inventory data.
4. Responsible for the daily income and expenditure accounts.
5. Keep the accounts, materials and cards consistent.
Pmc finished product warehouse management
1. The finished products should be inspected when they are sent to the warehouse.
2. Finished products are delivered from the warehouse.
3. Finished product warehousing and accounting treatment.
4, finished product location planning, sorting and safety maintenance.
5. Bring information about finished goods inventory.
6. Inventory report of expired goods.
7. Conduct an inventory and accounting review at the end of each month.
Warehouse management of Pmc hardware, electronics and packaging materials
1. Receiving incoming materials and returning unqualified products.
2. Control the batch number of materials and report the remaining materials.
3. Location planning, arrangement and safety maintenance.
4. Delay the inventory display of materials and valuable waste products.
5. Bring dynamic information of inventory.
6, monthly inventory key inventory and accounting check.
7. Obey the arrangement of superiors, be responsible for warehouse work, and guide subordinates to standardize operations.
Pmc plastic warehouse management
1. incoming plastic parts and fuel injection parts are recycled, and unqualified products are returned.
2. The warehouse prepares, distributes and delivers materials to the workshop according to the production instructions.
3. The documents of the day are logged into the account card on the same day and distributed.
4. Partition, classify and place the rubber parts in the warehouse, and prevent dust.
5. Inventory report of expired goods.
6, monthly inventory key inventory and accounting check.
7. Regularly review the accounts and keep the accounts, materials and cards consistent.
8, check the warehouse before coming off work every day, and do a good job of safety maintenance.
9. Obey the arrangement of superiors, be responsible for warehouse work, and guide subordinates to standardize operations.
Pmc warehouse porter
1, responsible for material handling.
2. Responsible for the delivery and handling of finished products.
3. Assist in warehouse planning and management.
Pmc Responsibilities: 10 1, leading order review, material demand planning and warehouse inventory control.
2. Forecast the company's production development trend, evaluate the production potential load, and submit the production potential design scheme to the vice president of production.
3. Make overall arrangements for the overall affairs of the department, establish departmental management procedures and standards, and supervise the completion of departmental tasks.
4. Review and modify the work specifications and management system of PMC department.
Supervise production management, material control, warehouse and finished product delivery according to job responsibilities. The information includes the arrangement and adjustment of PC production plan, communication with sales department, production progress and follow-up; Establish MC material demand plan, communicate with purchasing department on material ordering, material progress tracking, material receiving and replenishment control; Receive, keep and distribute warehouse materials and products, improve accounts, computer data and other affairs; Arrange and track the shipment, transportation and return of finished products.
6. Be responsible for information communication and coordination with other relevant departments, track the processing progress of new molds for production, cooperate with the technical department to arrange new materials and new molds, and track related progress and results.
7. Check and evaluate the progress and performance of subordinates. Information includes setting subordinates' work goals and progress, tracking and conducting regular work performance evaluation.
8. Solve abnormal matters that are difficult for subordinates to handle, coordinate and promote cooperation and communication among various groups, and play a team role.
9. Plan and design the development plan of PMC department and establish a perfect scheme.
10. Cultivate and improve the quality and work potential of subordinates, make them have good management and coordination potential, improve the overall level of PMC department, and cultivate human resources for the company's development.
1 1. Issue documents and receipts from PMC departments at all levels.
Pmc job responsibilities 1 1 1. Analyze and sort out production orders, arrange appropriate production plans according to production capacity and material allocation, and distribute them to production workshops and relevant departments.
2. Supervise the material progress.
3. Change and deployment of orders; Adjustment of abnormal production scenes; Track the production progress.
4. Information collection, collation and feedback.
5. Track the shipment arrangement of finished product shipment.
6. Statistics workshop existing manpower and equipment, evaluate the production capacity load.
7. According to the order review of the company's business department, all orders are sorted and merged according to the priority principle (delivery date and customer grade).
8. According to the standard working hours of various types of products provided by the technical department, calculate the consumption time of orders, and classify and summarize the consumption time of orders delivered by stages within one week and every month. The subdivided orders are classified according to product operation characteristics and customers, and sorted according to delivery time, which is convenient for unified arrangement of operation plan.
9. Compare the order consumption time in this period with the normal operation time of the production department. If the order consumption time is longer than the operation time, it is necessary to increase working hours or increase personnel, equipment and external processing to meet the order completion; Unable to complete the order, notify the sales department to communicate with the customer to delay the delivery. If the order consumption time is less than the normal working time, measure the delivery order after one week and arrange the production in advance to achieve the balance between the order consumption time and the normal working time. Weekly orders are compiled into weekly production plans, which are reviewed by department heads and distributed to relevant departments one week in advance. Similarly, establish a monthly plan and make a material demand plan accordingly.