According to the report of South China Daily, with the upgrading of Guiguang Railway to a dedicated passenger line, the freight exchange between most parts of northwest China and Sichuan, Chongqing, Guizhou and the Pearl River Delta will be undertaken by Liu Zhao Railway, which has new requirements for railway capacity and design standards. Does this mean that the pre-feasibility study scheme designed by China Railway Consulting Company is different from that designed by China Railway Second Hospital? In this regard, the person in charge of Liuzhou Railway Waterway Construction Office expressed his approval.
It is understood that in order to promote the planning and project construction of Liu Zhao Railway as soon as possible, Liuzhou City began to entrust China Railway Second Hospital to carry out the research on Liu Zhao Railway Scheme in February last year. At the same time, after struggle, the project can be re-incorporated into the national medium-and long-term railway network planning according to procedures. The planned Liu Zhao railway project will be organized by the Ministry of Railways, and China Railway Engineering Design Consulting Group Co., Ltd. will win the bid to undertake the tasks of pre-feasibility study report and exploration design scheme preparation.
The Liu Zhao Railway Pre-feasibility Study Report compiled by China Railway Consulting Co., Ltd. started from Jinde Station of Liuzhou Hub, and suggested that it should cross Dayao Mountain by a long tunnel in the shortest air distance near Baizhang Township of Xiangzhou County, and then enter Guangdong eastward through Guiping, Pingnan County and Wuzhou City, with the end point in Zhaoqing City. The total length of the railway line is 4 10 km, which is a first-class double-track electrified railway of China Railway, with a speed target of 200 km/h.. "It is possible for Liu Zhao Railway to build another double line parallel to nanning-guangzhou railway, but it will not share the track with nanning-guangzhou railway." The person in charge said that due to the passenger transport function of the former Guiguang Railway, the connection scheme of Pingnan-Nanguang Line designed by the former China Railway Second Hospital could not adapt to the development of the new situation. Therefore, Liu Zhao Railway does not rule out the possibility of building along the north bank of Xijiang River after entering Guangdong, and passing through Fengkai and Deqing counties to Zhaoqing.
According to reports, it was agreed by the Railway Engineering Construction Office of the Autonomous Region and China Railway Consulting Co., Ltd. that the pre-feasibility study report of Liu Zhao Railway will be submitted before 25th of this month, and then submitted to the Ministry of Railways and the National Development and Reform Commission for approval. Yao Chufeng, deputy general manager of China Railway Consulting Group Company and chief engineer in charge of railways, Wang Guolian, deputy chief engineer of this project, and chief engineers of various disciplines arrived in Liuzhou on June 16 this month to conduct survey and research on the direction along the railway.
China Railway Engineering Corporation completed the pre-feasibility study of Liuzhao Railway.
Pre-feasibility study on Liuzhou-Zhaoqing railway project of Ministry of Railways.
Research basis: Notice of the Development Planning Department of the Ministry of Railways on the announcement of the survey and design work arrangement of Changji-Ganke Special 18 project.
Research scope: Liuzhou-Zhaoqing section (including railway hub and both ends). The total length of the main line is about 4 14.560km.
1) From Jinde Station (inclusive) to Zhaoqing East Station (inclusive), the length of the main line is about 4 14.560 km, of which the descending bus from Jinde 10.3 km and the descending bus from Zhaoqing East are 6.249km;;
2) The lead-in line length of contact line at Jinde Station is 9.909 km, and the downlink line length is 9 158km, totaling 19.067 km:
3) Liuzhou Hub, Wuzhou Region and Zhaoqing Region (Guangzhou Hub) related projects.
Research year: recent 2020, long-term 2030.
Summary of recommended scheme: The route leads from Jinde Station of Liunan Passenger Dedicated Line to the southeast, passes through Liuyi Expressway, Guiliu Expressway and G209 National Road in turn, passes through the north side of Chuanshan Town to the south side of Xiangzhou County, crosses Liujiang River, and then establishes Xiangzhou Station;
After that, the line passes through Huangmiao Township Tunnel, and Jinxiu Station is set on the south side of Zhangda Township: after leaving the station, the line passes through Dayao Mountain with Yawangshan Tunnel, and then drives southeast after setting Dapeng Station in Dapeng, and sets Pingnan Station in Anhuai Town along the mountains on the north side of Wangsi Township and Guancheng Town;
After that, the line set up Mengjiang Station in Qincun, crossed Mengjiang River, passed through Mengcun and Renhe, and introduced to Wuzhou Station of the existing Luozhan Line. After leaving the station, turn east over Gui Jiang Bridge on Luozhan Line, and then pass through Gui Jiang.
Entering Guangdong to Dawan, crossing Hejiang, marching along the north bank of Xijiang River, passing through Fengkai, Deqing, Yuecheng and Lubu in turn, passing through Beiling Mountain by tunnel, passing through the existing Sanmao Line in parallel, passing through Sanmao Railway after the completion of Nanguang Line, passing through Guiguang Railway under construction, and introducing into Zhaoqing East Station.
The length of the line from Liuzhou to Zhaoqing is 4 14.56km, in which the length of the line in Guangxi is 262.238 km and that in Guangdong is 152.322km. Expansion coefficient 1. 12, 9 new stations, 3 reconstructed stations, large and medium-sized bridge 163, 69.09 km, tunnel1/seat, 140.956 km, main line. It is suggested that the whole line and double track be built at one time.
Suggestions on main technical standards:
Railway grade: National Railway Class I..
Number of main lines: double lines
Design driving speed: 160km/h
Minimum curve radius in plane: generally 2000m, difficult1600m,
Maximum slope: 6‰
Traction type: electric power
Type of locomotive: passenger car SS9, EMU; Cargo plane HXD3
Traction mass: 4,000 tons
Effective length of arrival and departure line: 850 meters
Blocking mode: automatic blocking
Overview of station support: There are 1 2 stations in the near future and long term (including two existing stations in Jinde and Wuzhou and1station under construction in Zhaoqing East), including 7 intermediate stations and 5 off-road stations. The maximum distance between stations (from Jinde to Xiangzhou) is 55.204 kilometers, and the minimum distance (from Yuecheng to Landport) is 28.700 kilometers, with an average of 37.624 kilometers.
Transportation organization mode: this line mainly undertakes the transportation of goods in the north and northwest of Southwest China and the Pearl River Delta region, taking into account the short-distance passenger flow of surrounding cities and counties and towns along the line. Combined with the study of construction scheme, it is suggested that the transportation organization mode of this line should be the same line for passengers and goods, with goods as the main part and customers as the main part.
Main Bridges and Tunnels:
1) Liujiang extra-large bridge (center mileage AK54+039.00), span arrangement is (3 1 32m simply supported T-beam)+(5.48m simply supported box girder)+(73.2+120+228+12) The price is 73.
2) Yawangshan Tunnel, which crosses Dayaoshan Mountains (entrance mileage AK90+ 160, exit mileage AK 104+830), is a single-hole double-line tunnel with longitudinal slopes of 4.093 and -4.5 respectively.
3) Mawuling Tunnel (entrance mileage AK39 1+3 10, exit mileage AK405+390), with a total length of 14.08 km, is a single-hole double-line tunnel, and the longitudinal slopes in the tunnel are herringbone slopes with slopes of 5.0 and 1.3 respectively.
Investment estimation: The estimated total investment of the project is 3038778 million yuan, and the technical and economic indicators are 733010.3 million yuan/trunk line kilometer, of which the static investment is 2740365438+700 million yuan, and the technical and economic indicators are 6665438+0.065438 yuan/trunk line kilometer; The locomotive purchase cost is 65.438+0.34 billion yuan.
The pre-feasibility study was completed from June 5, 2008 to February 2009.
Liu Zhao Railway Project Proposal passed the evaluation, which provided strong support for the next project of the National Development and Reform Commission.
The evaluation meeting of the proposal for the new Liuzhou-Zhaoqing railway project was held in Liuzhou on the 24th and 25th. On behalf of Liuzhou, Zhang Yonggang, vice mayor of Liuzhou, expressed the wish of Liuzhou people to start construction of Liu Zhao Railway as soon as possible. Li, director of the Basic Industries Department of the National Development and Reform Commission, listened to the opinions of all parties on the spot. According to the opinions of the expert group, the evaluation opinions of Liu Zhao railway project proposal will provide strong support for the next project of the National Development and Reform Commission.
Entrusted by the National Development and Reform Commission, China Railway Second Hospital Engineering Group Co., Ltd. conducted a site survey of the newly-built Liuzhou-Zhaoqing railway project in Zhaoqing, Liuzhou and Wuzhou, Guangdong Province from April 23 to 25, and listened to the introduction of the design unit and the opinions of the National Development and Reform Commission, the Ministry of Railways, Guangxi Zhuang Autonomous Region, Guangdong, Nanning Railway Bureau, Guangzhou Railway Bureau and local governments along the route. Based on the principle of "independence, justice, science and reliability", it is necessary and reliable to build this project.
According to the assessment, the construction of Liu Zhao Railway is the need to strengthen the economic ties between southwest China, Guangxi and the Pearl River Delta region, to implement the strategy of developing the western region, to promote regional economic cooperation in the Pan-Pearl River Delta region, and to promote the coordinated and sustainable development of regional economy. It is the need to build a "five vertical and five horizontal" comprehensive transportation network in China, improve the structure of regional railway network, and form a railway corridor from southwest, Guangxi to the Pearl River Delta region; It is the need to consolidate national unity, drive poverty-stricken mountainous areas out of poverty, develop tourism resources, improve the comprehensive transportation system along the line, and promote rapid social and economic development; It is the need of developing circular economy and building a resource-saving and environment-friendly society in this area. It is the need to strengthen regional national defense construction. Therefore, it is necessary to build Liu Zhao Railway.
Liu Zhao Railway is located in the economic zones of eastern Guangxi and western Guangdong, with dense population and high level of economic and industrial development. The railway starts from Liuzhou, the largest industrial base in Guangxi, the southwest transportation hub and the second largest central city in Guangxi, and passes through Laibin City, Guigang City and Wuzhou City in the southeast to Zhaoqing City in Guangdong Province. The total design length of the line is 4 14.560km, including 262.238 km in Guangxi. Its function is located in the trunk railway with freight as the main line and passenger and freight as the same line.
Due to the efforts of Liuzhou Municipal Party Committee and Municipal Government, Liu Zhao Railway was re-listed in the National Medium-and Long-term Railway Network Planning (adjusted in 2008) in 2008. This project is a newly-built railway project in the Medium and Long-term Railway Network Planning (adjusted in 2008), which belongs to the project of improving the railway network layout. Through this evaluation, the proposal of Liu Zhao Railway Project will be revised and improved according to the opinions of experts, and submitted to the National Development and Reform Commission for approval in the near future together with the evaluation report.
China Railway Engineering Corporation completed the feasibility study of Liuzhao Railway.
Feasibility Study on Newly-built Liuzhao Railway The newly-built Liu Zhao Railway is located in Guangxi Zhuang Autonomous Region and Guangdong Province, with passenger and freight lines in common.
The line leads from Jinde Station of Liuzhou Hub, passes through Xiangzhou, Jinxiu, Guiping, Pingnan, tengxian and Wuzhou in the southeast, and passes through Fengkai and Deqing to Zhaoqing East Station. The line connects Guizhou-Guangxi, Gui Xiang-Liujiao lines and Liunan intercity railway under construction in the west, intersects the southern section of Luozhan Railway in the middle and connects Guiguang, Nanguang and Sanmao Railways in the east. It is an important channel for goods exchange between the northwest and southwest regions and the "Pearl River Delta" region of Guangdong, and also a passenger channel between Liuzhou, Hechi and the "Pearl River Delta" region.
The total length of the main line is 400.633 kilometers, including 7.603 kilometers for the right line in Jinde and 6.2 kilometers for the right line in Zhaoqing. The base length of the main line of the whole line is 146258 km, accounting for 36.5% of the line length; The length of the main bridge is 75.728km, accounting for18.9% of the line length; Main tunnel 134, 178.647 km, accounting for 44.6% of the line length; Track laying of main line is 8 16439 km; Track laying of the station line is 5320 1 km, without broken track bed 12078 km; The production room is 55,900 square meters.
In the near and long term, there will be a total of stations 1 1 (including Jinde Station, Wuzhou Station and Zhaoqing East Station under construction), including 5 new intermediate stations, 3 new off-road stations, 2 existing stations and 1 station under construction: L prospective reserved stations.
Main Bridges and Tunnels:
1. Xiangzhou Liujiang Bridge with a total length of 2115.6m..
2. Yawangshan Tunnel, with a total length of .987km and a maximum buried depth of about 500m. 3. ivory mountain Tunnel, with total length of 12.570km and maximum buried depth of about 799m.
China Railway Design Consulting and China Railway Tunnel Institute jointly designed, and China Railway Design Consulting No.1 Bureau is the overall design unit of the project. The feasibility study report (draft) was completed on March 20 10. Liuzhou Municipal Party Committee Secretary led a team to visit the leaders of the National Development and Reform Commission and the Ministry of Railways in Beijing.
Report and exchange the development of Liuzhou railway construction.
On the morning of May 30th, Chen Gang, secretary of Liuzhou Municipal Party Committee, called on Xu Xianping, member of the leading group and deputy director of the National Development and Reform Commission, Lu Dongfu, member of the leading group and deputy director of the Ministry of Railways, and leaders of relevant departments in Beijing to report and exchange information on the development of Liuzhou Railway.
On behalf of the Liuzhou Municipal Party Committee, the Municipal Government and the people of Liuzhou, Secretary Chen Gang thanked the National Development and Reform Commission and the Ministry of Railways for their long-term strong support and help to Liuzhou's railway construction and development, introduced Liuzhou's economic and social development, railway construction and development, and the "Twelfth Five-Year Plan" development goals, and fully expressed the strong desire of Liuzhou people to build and develop railways, especially the construction of Liu Zhao Railway. Chen Gang emphatically introduced the requirements and suggestions for the newly-built Liuzhao Railway Project to start construction as soon as possible. Xu Xianping, deputy director, and Lu Dongfu, deputy director, were all moved by the sincerity of Liuzhou people and their desire to speed up railway development. They said that they would seriously consider the actual situation in Liuzhou, fully support the railway construction in Liu Zhao, and strive to create conditions for Liuzhou's social and economic development. Liu, member of the Standing Committee of the Municipal Party Committee and Secretary General, and Vice Mayor accompanied the meeting.
On August 2nd, 20 1 1 year, the mid-year working conference of railway construction system in the whole region was held in Nanning. The meeting mainly conveyed and implemented the spirit of the mid-year work conference in the whole region, summarized the railway construction work in our region in the first half of the year, analyzed the current situation, and studied and deployed the work in the second half of the year. Li Hongqing, executive deputy director of the Railway Construction Office of the Autonomous Region, made an important speech at the meeting. He asked the railway construction system in the whole region to seriously study, profoundly understand and fully implement the spirit of the mid-year work conference in the whole region, earnestly implement the spirit of the instructions of the leaders of the autonomous region on railway construction in our region in various specific work, and firmly promote the railway construction and development in our region. In his speech, Li Hongqing, executive deputy director, first conveyed the spirit of the important speeches made by Guo Shengkun, secretary of the Party Committee of the autonomous region, and Ma Biao, chairman of the autonomous region government, at the mid-year working conference of the whole region, and comprehensively summarized the railway construction work in our region in the first half of the year. In the first half of the year, the total investment of railway construction projects in the whole region was1651200 million yuan, up 25% year-on-year, and the investment grew steadily and rapidly. Continued construction projects were accelerated in an orderly manner. By the end of June, the subgrade works of nanning-guangzhou railway (Guangxi Section), Liuning Intercity Railway and Gui Xiang Railway were basically completed, and the post-station works of Qin Nan Railway were fully rolled out, and other projects were promoted in an orderly manner; New progress has been made in the preliminary work. Six projects, including Nanning-Pingxiang Railway, Hechi-Nanning Railway, Hepu-Zhanjiang Railway and Nanning-Baise Section of Nankun Railway, have been approved by the state, and project proposals, such as Huangtong-Baise Railway and Liuzhou-Zhaoqing Railway, have been submitted to the National Development and Reform Commission for approval. New breakthroughs have been made in financing, and the local matching funds for railway construction in our region rank first in the country; New achievements have been made in foreign cooperation, and all work has been actively and steadily promoted; The characteristics and highlights of the work of railway offices, project owners and construction units in various cities are outstanding, and remarkable achievements have been made, which has maintained the good development momentum of railway construction in our region. In the 12th Five-Year Plan for the Western Development approved by the State Council, the railway construction from Liuzhou to Zhaoqing is listed as a strategic key project.
It is understood that a few days ago on February 2 1, the State Council officially approved the Twelfth Five-Year Plan for the Development of the Western Region organized by the Development and Reform Commission. The plan puts forward the "Twelfth Five-Year Plan" for the development of the western region from seven aspects: comprehensive economy, infrastructure, ecological environment, characteristic industries, public services, people's life and reform and opening up. Among the planned key railway construction projects, the railway construction from Liuzhou to Zhaoqing is regarded as "key railway project".
In 2008, Liu Zhao Railway was listed in the National Medium-and Long-term Railway Network Planning (Adjusted in 2008). According to the contents of Nanning Railway Bureau's Medium and Long-term Railway Network Planning in February, 20 10, the main line of Liuzhao Railway is 400 kilometers long, with an estimated investment of 3 18 billion yuan and a construction period of 4 years. The project proposal was submitted to the National Development and Reform Commission on June 20 10, and the feasibility study was completed and submitted to the Ministry of Railways. In the feasibility study report, its function is positioned as a railway trunk line with passenger and freight lines, and there are three design schemes. One of the recommended schemes is that the railway starts from Liuzhou, passes through Laibin, Guigang and Wuzhou in the southeast, and then reaches Zhaoqing in Guangdong. The total design length of the line is 4 14km, including 262km in Guangxi.
"It has always been the hope of Wuzhou people to strive for the early start of Liu Zhao Railway. This time, Liu Zhao Railway was selected into the "Twelfth Five-Year Plan" for the development of the western region, which shows the importance of this railway. " Guo, director of Wuzhou Railway Construction Office, said that Liu Zhao Railway is an important railway to build a "Feng"-shaped railway hub in our city, which will make Wuzhou a new railway hub from Guangxi to the Pearl River Delta in addition to Nanning and Liuzhou railway hubs, and also help to build a domestic regional comprehensive transportation hub city.
It is reported that Liu Zhao Railway is located in the economic zones of eastern Guangxi and western Guangdong, with dense population and high level of economic and industrial development. The construction of Liu Zhao Railway is the need to strengthen the economic ties between Southwest China, Guangxi and the Pearl River Delta region, to implement the strategy of developing the western region, to promote regional economic cooperation in the Pan-Pearl River Delta region, and to promote the coordinated and sustainable development of regional economy. It is the construction of China's "five vertical and five horizontal" comprehensive transportation network, which is conducive to improving the railway layout in Guangxi and Southwest China and enhancing the safety, mobility and flexibility of the road network. The intersection of Liu Zhao Railway, nanning-guangzhou railway Railway and Luozhan Railway in Wuzhou will become another major passage for the northwest, southwest and central plains regions of China to enter Guangdong, Hong Kong and Macao, which will ease the transportation pressure of Beijing-Guangzhou Railway, Li Zhan Railway and guangzhou-maoming railway, improve the railway transportation efficiency and make the railway layout in southwest China more reasonable and perfect. In late September, the autumn was crisp, and the Liuzhou-Wuzhou section of Liu Zhao Railway was officially approved by the National Development and Reform Commission. Liuwu Railway (Liu Wu Section of Liu Zhao Railway) has been approved by Liunan Railway Co., Ltd. (hereinafter referred to as "Liunan Railway Company"), and the project construction funds have been implemented. Liunan Railway Company, as a bidder, has conducted public bidding for the railway geological survey and supervision project on the construction website.
According to the introduction of China Railway Construction Engineering Network, the newly-built Liuzhou-Wuzhou Railway (Liu Wu section of Liu Zhao Railway) leads from Jinde Station of Gui Xiang Line of Liuzhou Hub, passes through Liujiang County of Liuzhou City, Xiangzhou County of Laibin City, Jinxiu Yao Autonomous County, Guiping City of Guigang City, Pingnan County, tengxian City and Cangwu District of Wuzhou City, and finally reaches Wuzhou South Station of nanning-guangzhou railway. The west end of the project is connected with the lines of Guizhou-Guangxi, Hunan-Guangxi and Liujiao and the inter-city railway of Liunan under construction, and the east end is connected with the railways of nanning-guangzhou railway and Luozhan. It is a part of Liu Zhao Railway, which extends to Guangzhou through Wuzhou, connecting Guiguang and Sanmao Railway. It is an important channel for goods exchange between the northwest and southwest regions and the "Pearl River Delta" region of Guangdong, and also a passenger channel between Liuzhou, Hechi and the "Pearl River Delta" region. It is understood that the newly-built Liuzhou-Wuzhou Railway has stations such as Jinde, Maping, Xiangzhou, Dazhao, Dapeng, Pingnan, Mengjiang, Shuangfeng, Wuzhou South and Wuzhou. The baseline length of the main line of the whole line is 96.965 kilometers, accounting for 40.62% of the total length of the line; There are 1 14 extra large, large and medium bridges on the main line, accounting for 20.40% of the length of the line; The length of the main tunnel is 93.059 kilometers, and the tunnel accounts for 38.98% of the length of the main line. The total investment of the project is 654.38+09.6 billion yuan, of which capital accounts for 50% and the rest is domestic bank loans. The newly-built Liuzhou-Wuzhou railway was designed by China Railway Engineering Design Consulting Group Co., Ltd., with a planned total construction period of 48 months.