Current location - Education and Training Encyclopedia - University rankings - Model of construction organization design scheme for university gymnasium project?
Model of construction organization design scheme for university gymnasium project?
What is the specific content of the construction organization design scheme of the university gymnasium project model? Zhong Da Consulting will answer your questions below.

The first section engineering characteristics

1. This project was built to welcome the convening, and the tight construction period is its biggest feature.

Second, the roof structure of the gymnasium project is a six-fulcrum four-leaf spatial steel reticulated shell, which adopts welded hollow spherical joints and seamless steel tube members, which is difficult to construct.

3. The gymnasium project is equipped with 500× 1500 large inclined beams.

Fourth, this project has many arcs, irregular structure, complicated high-rise changes, and it is difficult to measure and set out.

Five, the project site is fully functional, the construction team is specialized, and the construction team is highly mobile.

Section II Project Overview

Gymnasium is a modern sports facility built on campus to welcome the National University Games. It is a key project and one of the key projects in development planning. It can not only meet the requirements of the National University Games and daily physical education in schools, but also take into account the development of mass physical fitness activities for teachers and students in schools.

Its grand multi-functional building scale; The novel and unique architectural modeling, ready to go, symbolizes the steady progress trend of 2 1 1 project, and also reflects the vigorous spirit of college students and athletes. This is a landmark building.

I. General situation of architecture

The construction site of this project is 280×224 meters, and the layout of "integrated venues" is adopted. The main axis of the gymnasium is perpendicular to Jiusan Highway and symmetrically arranged left and right. Campus roads are planned at the north and south ends, and distribution squares are planned at the west side. The square can park motor vehicles and non-motor vehicles, as well as tennis courts and a lot of green spaces. The memorial statue of Zhu De is set in the central green space, which not only beautifies the campus, but also highlights the main entrance of the gymnasium and increases the cultural atmosphere of the campus.

1, Introduction of Gymnasium Building:

The total construction area of the gymnasium is square meters, with two floors above ground and one underground, and the building height is meters.

The basement of the gymnasium is 3.6m high, and it is equipped with auxiliary buildings such as wind and rain playground, indoor track and field training ground, gym, training hall, office and warehouse. Among them, the space size of the storm playground is 48.3×34.3×5.5m (length× width× beam bottom height).

The ground floor of the gymnasium is 4.2m high, and it is equipped with a recording hall, a lounge for athletes and referees, a VIP lounge and corresponding auxiliary rooms, as well as an electric classroom, a computer room, a library, a teaching and research section, an office, a conference room, a power distribution room and a fire control duty room.

There is a main stadium on the second floor of the gymnasium, with a plane size of 48.3× 34.5m and a clear height of1.3m. There are 450 movable seats in the stadium, which can meet different competition requirements. There is a mezzanine space in the east and west grandstands, which is convenient for the audience to rest halfway. There are canteens and men's and women's toilets in the audience lounge.