Remarks on decoration content, quantity, unit price and price
I. Residential areas
Covering paint-free doorways 5 linear meters 50 250 paint-free doorways and doorways, styrofoam, leveling, labor costs.
5.3 m2 150 795 melamine partition, hardware, steam sprayed door panel for upper cabinet door.
2.7 m2 320 864 titanium-magnesium alloy sliding door, painted glass, slideway.
Ceiling modeling 1.4 m2 220 308 wooden keel, gypsum board, auxiliary materials, modeling stained glass, glass nails and labor costs.
Floor tile laying, skirting board 3.5 m2 42 147 cement, sand, caulking agent, foot board laying, labor costs.
Subtotal 2364
Two. sitting room
Shovel the wall, scrape putty, brush latex paint 62 m2 35 2 170 shovel the wall, Wanrong 303 putty, Dulux Haolang full-effect latex paint, labor costs.
Floor tile laying, skirting board 27 m2 42 1 134 cement, sand, caulking agent, foot board laying, labor costs.
TV wall 1 900 900 crystal artificial stone table top, embedded hardware, large core board, glass, colored latex paint, labor cost.
Living room ceiling 8 linear meters 58 464 wooden keel, gypsum board, accessories, hardware, labor costs
Top corner line 12m 8 96 gypsum top corner line, glue, labor cost.
7 linear meter 1 10 770 paint entrance, entrance line, styrofoam, leveling and labor costs.
6 sets of 80,480 polycrystalline glass with glass corner protector, advertisement nail, labor cost.
Subtotal 60 14
Three. Living room balcony
Floor tile 7 m2 38 266 Cement, sand, joint sealant and labor costs
Brick wall 22 m2 38 836 cement, sand, caulking agent, labor costs
Tile corner line 6 10 60 Tile corner line, labor cost.
Air-conditioning lower cabinet 3.3 m2 200 660 melamine partition, hardware, large core board door panel, paint, labor costs.
Balcony cabinet (one-sided facade) 5m220 1 100 melamine partition, hardware, large core board door panel, painting and labor costs.
Plastic steel ceiling 7 m2 95 665 plastic steel plate, wooden keel, plastic steel corner line, auxiliary materials and labor costs.
Subtotal 3587
Four. bedroom
Hit the door, widen and lower the door 1 item 120 120 hit the door, wooden keel, accessories, labor costs.
Paint doors 1 set of paint doors11801180 paint doors and paint doors, labor costs, (excluding door locks, hinges and door suction)
Site leveling 15 m2 18 270 cement, sand and labor costs
Shovel the wall, scrape putty, brush latex paint 58㎡35 2030 shovel the wall, Wanrong 303 putty, have fun with Haolang full-effect latex paint, and there are labor costs.
Top corner line 17m 8 136 gypsum top corner line, glue and labor costs.
Paint the window 4.5 linear meters 1 10 495, paint the doorway, doorway line, styrofoam, adjust the window and level it, and labor costs.
Window sill artificial stone 1.8 linear meter 140 252 crystal artificial stone, the width of artificial stone extends out of the window 10 cm, and the width is less than 300 cm.
1 item household roof seal 60 wooden keel 60 gypsum board fittings labor cost
Subtotal 4543
Verb (abbreviation for verb) study room
Smash doorways, widen doorways 1 item 120 120 wooden keels, fittings and labor costs.
Paint doors 1 set of paint doors11801180 paint doors and paint doors, labor costs, (excluding door locks, hinges and door suction)
Site leveling 10 m2 18 180 cement, sand and labor costs
Shovel wall, scrape putty, brush latex paint 43 m2 35 1505 shovel wall, Wanrong 303 putty, Dulux Haolang full-effect latex paint, labor cost.
Top corner line 13m 8 104 gypsum top corner line, glue and labor costs.
Paint the window 1 1.7 linear meter101287, paint the doorway, doorway line, styrofoam, adjust the window, elevation and labor costs.
Window sill artificial stone (3 pieces) 3. 1 linear meter 140 434 crystal artificial stone, which is 10 cm wider than the window and less than 300 cm wider.
Subtotal 48 10
Intransitive verb toilet
Floor tile laying 4.2 m2 38 159.6 cement, sand, caulking agent and labor costs
Brick wall 22 m2 38 836 cement, sand, caulking agent, labor costs
Plastic steel ceiling 4.2 m2 95 399 plastic steel plate, wooden keel, plastic steel corner line, auxiliary materials and labor costs.
Tile corner line 4 10 40 Tile corner line, labor cost.
Water basin cabinet 1.4 linear meter 800 1 120 crystal artificial stone table, melamine cabinet, UV cabinet door, aluminum-plastic plate (excluding hinged handle slide rail)
Paint doors, doors 1 set 1280 1280 paint doors, doors, digging holes, glass, labor costs (excluding locks, hinges and floor absorption).
Bathroom glass tray 6 40 240 8 thick-edged glass tray, stainless steel bracket.
Toilet waterproofing 1 260 Item 260 Waterproof mortar, oil drainage and labor costs
Subtotal 4334.6
7. Bedroom entrance
Ceiling modeling 2.4 m2 130 3 12 wooden keel, gypsum board, accessories and labor costs.
Modeling of suspended ceiling outside toilet1.7m2130221wooden keel, gypsum board, fittings and labor costs.
Paint the window 4.5 linear meters 1 10 495 paint the doorway, doorway line, styrofoam and labor costs.
Window sill artificial stone 1.55 linear meter 140 2 17 crystal artificial stone, which is wider than the window 10 cm and less than 300 cm.
Floor tile laying, skirting board 3.2 m2 42 134.4 cement, sand, caulking agent, foot board laying and labor costs.
Shovel the wall, scrape putty, brush latex paint 2 1㎡35 735 shovel the wall, Wanrong 303 putty, Dulux Haolang full-effect latex paint, labor costs.
Subtotal 2 1 14.4
Eight. restaurant
Floor tile laying, skirting board 6 m2 42 252 cement, sand, caulking agent, foot board laying, labor costs.
Restaurant background, ceiling modeling, 5 m2 150 750 wooden keel, gypsum board, accessories and labor costs.
Top corner line 8.5 meters 8.68 gypsum top corner line 1 circle, glue, labor costs
Shovel wall, scrape putty, brush latex paint19m2 35 665 shovel wall, Wanrong 303 putty, Dulux Haolang full-effect latex paint, labor costs.
Paint the door 6.5 linear meters 1 10 7 15, paint the door, the door line, styrofoam, adjust the window, level, and labor costs.
Subtotal 2450
Nine. kitchen
Floor tile laying 6 m2 38 228 cement, sand, caulking agent and labor costs.
Wall tile 2 1 m2 38 798 cement, sand, caulking agent, labor costs
Hanging cabinet 2.85 linear meter 1 100 3 135 crystal artificial stone table top, UV panel, melamine partition, (excluding hinged handle and slideway)
Basement cabinets 1. 1 linear meter 800 880 crystal artificial stone countertops, UV panels, melamine partitions, (excluding hinged handles and slideways)
Including gas meter cabinet 1 item 180 180 wooden keel, steel wire mesh and mortar board.
Plastic steel ceiling 6m295 plastic steel plate, wooden keel, plastic steel corner line, auxiliary materials and labor costs.
Total 579 1
All of them
Shovel wall skin 2 m2 150 300 shovel second-hand house wall skin, labor cost.
Scraping putty and brushing latex paint 35m3150 52.5 million Rong 303 Samsung putty, Dolores Haolang universal latex paint cost.
Floor tile 6 square meters 38 228
Eleven. main material
Floor tile 800 * 80010280816062 m2.
Wall turn 450*300 490 pieces 5.8 2842 wall brick 65 square meters.
30 pieces of glass skirting board 8.5 255 black polycrystalline glass skirting board
50 bathroom tiles 4.5 225 bathroom tiles 4.2 square meters
Composite floor 26 m2 85 22 10 including skirting board installation.
Subtotal 13692
present
Free decoration and cleaning, removal of stainless steel railings, chiseling and repairing of five-window walls, extension of heating in two bedrooms, and installation of lamps and sanitary ware.
Total 49928