1. The developer Yida Group withdrew its capital, which led to the break of the project capital chain.
2. The developer and the government failed to reach an agreement on the division of school districts, which further affected the sales strategy and plan of the project.
3. The delivery standard of fine decoration has not been determined, which leads to the delay of decoration project.
Therefore, the delivery time of Wang Dazhi Town has been delayed again and again, and there is still no exact date.