Current location - Education and Training Encyclopedia - Educational institution - Housing construction agreement
Housing construction agreement
In the era of continuous progress, men, women and children may need to use agreements, and the signing of agreements is the best specification of rights and obligations between two parties or several parties. How was the general agreement drafted? The following are five housing construction agreements that I have carefully compiled. Welcome everyone to refer to it, I hope I can help you.

House Building Agreement 1 Party A:

Party B:

Party A's house under construction has two floors, one floor is about square meters, and the other floor is about square meters, which is contracted by Party B. Based on the principles of equality, mutual benefit, honesty and credit, both parties, through consultation, sign this contract to ensure the safety, high quality, high efficiency and low consumption of the project, so as to abide by it jointly:

First, the contracting method.

Take the way of contracting without contracted materials.

Party A shall provide materials needed for the building, including: red bricks, river sand, stones, lime, cement, steel, water pipes, sewer pipes, nails, wires, water and electricity, etc.

Party B shall provide labor services, construction technology, construction tools and all production and living appliances.

Second, the construction project

Party B shall carry out the construction according to the design drawings or the requirements put forward by Party A. The buildings of Party A's main building project include walls, beams, columns, stairs, floors, formwork installation, formwork removal, steel bars, cast-in-place concrete and concrete cushion for the ground and front steps; Paint the interior decoration, paste the front exterior wall tiles, brush cement mortar along the rear exterior wall, paste the bathroom floor and wall tiles, and install porcelain pots, sewer pipes and downspouts; The top layer shall be polished with cement slurry, and at the same time, it shall be well treated for seepage prevention and impermeability.

Third, the contract price

RMB in words per square meter: RMB (), and the construction area is calculated according to each external wall. The construction scope includes all the walls that need cement mortar plastering.

Four. mode of payment

After signing the contract, the tools will enter the site and the personnel will be in place, and 30% will be paid in advance. Pay 50% for the first floor brick and rammed ground, 8000 yuan for the second floor and roof, 90% for the completion of the project, and reserve 10% as quality guarantee. If there is no quality problem within one year after completion, the balance payment shall be paid.

Verb (abbreviation for verb) The responsibility of both parties.

Party A is responsible for the timely supply of water and electricity and the timely entry of raw materials. Party B must ensure the quality and progress of the project at lunch every day, carry out the construction according to the design drawings and Party A's requirements, save materials, take good care of them and not lose them.

Six, quality requirements

Party B shall organize the construction according to the national housing quality standards and requirements. If it does not meet the requirements, Party B shall be responsible for rework. The rework fee shall be borne by Party B or deducted by Party A from Party B's project payment.

Seven, pay attention to safety

Labor protection measures, construction protection measures in place, safe construction. If Party B's construction personnel suffer work-related injuries due to their own reasons or Party B's inadequate safety protection measures, or others are injured due to construction, Party B shall be responsible for everything, and Party A shall not bear any responsibilities and expenses. Civilized construction, pay attention to professional ethics, pay attention to cleanliness.

Eight, the time limit for a project requirements

The main project duration is 75 (calendar days). Since the date of signing this contract, Party B must complete the main project ahead of schedule, which will be postponed due to the weather. Party B shall not delay the completion time of Party A's building for various reasons. If Party B needs materials, Party B shall submit the plan to Party A in advance for timely preparation.

Nine, the later maintenance

The maintenance expenses arising from Party B's quality problems shall be borne by Party B, and the relevant compensation and responsibilities arising therefrom shall be borne by Party B..

X. others

Other matters not covered shall be settled by both parties through consultation, and shall be implemented in strict accordance with national and local standards.

This contract is made in duplicate, one for each party, and shall come into effect as of the date of signature.

Signature (seal) of Party A:

Signature (seal) of Party B:

Chapter II of House Building Agreement Party A's Representative: XXX

Representative of Party B: XXX

In response to the government's call for renovation of dilapidated houses, Party A and Party B have made reasonable planning and renovation of the original guild hall of Wang Zhu Group and the scattered old houses. After many consultations, both parties agree to sign the following agreement:

I. Basic information of original conditions: Party A has 8 sets of old houses and Party B has 7 sets of old houses.

Second, in order to rationally adjust the two sides in the spirit of brotherhood, the original scattered former residence was divided into two centers for reconstruction. The first floor of the public hall is jointly built by both parties, and the distribution position is on the left, which shall be borne by Party A (bounded by the public hall). The right side shall be borne by Party B (bounded by the lobby). The front yard is owned by both parties.

The above third and second floors shall be borne by Party A (Party B shall not bear any expenses).

Four. This agreement is made in duplicate, one for each party.

5. This agreement shall come into effect as of the date of signing, and both parties shall abide by it without going back on their word.

6. Use the old house and the old plan.

Party a: XXX

Party b: XXX

20XX x month XX day

Article 3 of the House Building Agreement Party A: Group 4 Xinzhuang, Luomu Village, Bianyang Town (hereinafter referred to as Party A)

Party B: Bianyang Town (hereinafter referred to as Party B)

In order to do a good job in the safety management of building construction, Party A will live here in the future, and the whole family will be healthy and happy, and the children will flourish. Therefore, in order to prevent all safety accidents, both parties signed this agreement through consultation.

Article 1: This project is a private building construction.

Article 2: Party A's safety responsibility: Before entering the site for construction, Party A shall verbally explain the safety matters to Party B's representative, and its content is to clearly explain to Party B the safety precautions related to construction, namely bricklaying, erection, hoisting, floor beating and all overhead construction.

Article 3: Party B's Safety Responsibility

(1) The representative of Party B is the person in charge of safety, who is responsible for the daily safety management of construction projects, strictly abides by the on-site safety rules and regulations, and is responsible for supervising the safe construction operations.

(2) Before the start of construction, safety education must be given to the subordinate personnel, such as building precautions, etc. Personnel without safety education shall not be arranged to enter the construction site.

(3) Any personnel of Party B shall not fight or drink at the construction site. It is forbidden to go to work after drinking.

(4) Party B shall be responsible for all safety responsibilities of the building. If there is a production safety accident in the building, Party B shall bear all accident responsibilities and economic responsibilities.

Article 4: Party A and Party B shall strictly abide by the terms of this contract, perform their respective duties and do a good job in housing construction.

Article 5: This Agreement shall come into effect after being signed by both parties, in duplicate, with each party holding one copy.

Party A:

Party B:

Verifier:

date month year

Article 4 of the House Building Agreement: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Party B: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

In accordance with the Contract Law of People's Republic of China (PRC), the Construction Law of People's Republic of China (PRC) and relevant national regulations, in order to ensure the smooth progress of Party A's housing construction and clarify the rights and obligations of both parties during the construction of the construction project, Party A and Party B sign this contract on the principle of "responsibility, right and benefit" through consultation.

1. Project overview

The project is located in a five-story brick-concrete building with raft foundation. The first and second floors are cast-in-place slabs, and the rest are precast slabs, structural columns, ring beams and shingle roofs.

Two: the way of contracting

Party A signs a contract with Party B on the basis of no materials.

Three. Scope of project contracting

According to the construction drawing provided by Party A, Party B shall be responsible for all construction machinery (wooden molds, nails, iron wires, scaffolding, etc. ), from foundation earthwork to bricklayer, carpenter, steel worker, etc. Internal completion. The facade of the external wall is plastered with external wall bricks, and other walls are made of water conservancy mortar. Five floors, tiled floor, bathroom, kitchen, stairs and steps.

Four. Contract price and payment method

1: Price: 140 yuan/m2 (building area). The construction area shall be calculated according to the calculation method stipulated by the state, and the increase or decrease of engineering quantity shall be settled by both parties through consultation according to the market situation.

2: Pay RMB 5,000 only after the foundation is completed; Pay RMB 4,000 only after the completion of each main cover plate, RMB XX only after the completion of internal and external painting, and pay the balance without quality problems in one lump sum before the Spring Festival (if there are quality problems, compensate the material cost).

Five: Time limit for a project and safety responsibilities

The construction period is from June 28th to October 28th, 20xx 10. For each day of delay, Party A will impose a fine of 200 yuan/day, which will be deducted from the project payment. ..

1 During construction: Party B is responsible for all safety matters of this project, and is responsible for safety management during construction according to the requirements of the project, and all personnel and property losses caused by Party B and its employees shall be borne by Party B; If a third party causes harm to Party B and its employees, the third party shall be responsible for it, which has nothing to do with Party A. ..

2. During the construction period, Party B shall not engage in anything unrelated to the construction, and professional construction personnel shall hold relevant certificates; The aerial work part can only be constructed after practical installation measures are taken. Appropriate monitoring personnel must be arranged on the ground, and fire prevention should be paid attention to in welding operation.

During the construction process, Party B shall not transfer any rights and obligations under this contract to a third party, especially not subcontract or subcontract, otherwise Party A has the right to terminate the contract, and Party B will unconditionally compensate and will not settle accounts.

Both parties shall abide by their respective responsibilities in the above contract. This contract is made in duplicate and shall come into effect as of the date of signature.

Party A: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Party B: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date: _ _ _ _ _ _ _ _ _ _ _ _ _

Further reading: legal knowledge of construction organization design and construction period

(1) The contractor shall provide the construction organization design, schedule and confirmation time.

The construction organization design and schedule confirmed by the owner and the supervisor are the basis for the claim for time limit for a project change and the technical support for the cost change. In the process of contract performance, especially decoration engineering and electromechanical installation engineering, the contractor shall provide detailed special construction scheme, which shall be approved by the employer and the supervisor. For example, if the tile mosaic scheme changes, the loss rate of tiles will be different, the construction difficulty will increase, and the cost will increase. When it happens, the contractor shall calculate the cost claim and time limit claim according to the approved special construction plan and schedule.

(2) Commencement and postponement of commencement

If the commencement date agreed in the agreement cannot be started due to the reasons of the Employer, the Engineer shall notify the Contractor in writing to postpone the commencement date. The Employer shall compensate the Contractor for the losses caused by the delayed commencement, and the construction period shall be postponed accordingly.

(3) Suspension of construction

In case of shutdown caused by the Employer, the Employer shall bear the additional contract price and compensate the Contractor for the losses caused thereby, and the construction period shall be postponed accordingly;

(4) Time delay

If the construction period is delayed due to the following reasons, the construction period will be postponed accordingly after being confirmed by the engineer:

The Employer fails to provide drawings and commencement conditions as agreed in the Special Terms and Conditions;

The employer fails to pay the advance payment and progress payment of the project on the agreed date, which makes the construction unable to proceed normally;

The engineer failed to provide the required instructions, approvals, etc. According to the contract, the construction can not be carried out normally;

Design change and increase of engineering quantity;

Within one week, water, electricity and gas stoppage caused by reasons other than the contractor have accumulated for more than 8 hours;

Force majeure;

Other circumstances in which the construction period is postponed as agreed by both parties can be implemented according to the general terms or otherwise agreed.

If the construction period is delayed due to the employer's reasons, the construction period will be postponed accordingly after being confirmed by the engineer. However, the Contractor shall report the delayed construction period to the Engineer in writing within 14 days after the construction period is delayed. The engineer shall confirm the report within 14 days after receiving it. If the engineer fails to confirm the report within the time limit, he will be regarded as agreeing to extend the construction period. On this basis, the contractor calculates the delay cost of the construction period.

(5) Completion

If the Employer needs to complete the project ahead of schedule, both parties shall negotiate and sign an early completion agreement, which is an integral part of the contract documents. The agreement on early completion shall include the measures taken by the contractor to ensure the quality and safety of the project, the conditions provided by the employer for early completion and the additional contract price required for early completion.

Part V of House Construction Agreement: Party A (hereinafter referred to as the person in charge): Party B (hereinafter referred to as the contractor): In accordance with the Economic Contract Law of the People's Republic of China, the Construction Law of People's Republic of China (PRC) and other relevant laws and administrative regulations, the two parties abide by the principles of equality, voluntariness, fairness, honesty and credibility, and reach the following agreement on Party B's contract for the house construction of Party A through consultation. ..

I. Overview of the Project

Project name: house construction project (hereinafter referred to as contract project)

Project location:

Second, the scope of project contracting

Scope of contract: construction, completion, defect repair and warranty during the warranty period of this contract project. This building project includes: foundation pit excavation and cleaning, foundation and wall masonry, concrete pouring, etc. , in line with the specifications and Party A's requirements.

Third, the contract method and contract price

1. The contract price is the price other than the material cost for completing the contract project.

Full cost. Confirmed by both parties, it is RMB Yuan (in words:

2. The contract price includes all the explicit and implicit responsibilities stipulated in the contract, as well as the requirements for the work.

All relevant items and articles required for proper construction, testing, inspection, maintenance, maintenance, completion and defect repair (excluding the cost of materials used in this project).

3. The contract price includes labor, manufacturing, transportation, installation, testing, debugging, testing, maintenance, management, profits, taxes and all risks, responsibilities, rights and obligations contained in the contract.

4. During the performance of the contract, no matter whether the contractor adopts any suggestions, schemes and requirements put forward by the person in charge, the contractor shall not ask for any additional expenses. Unless the cost change caused by the person in charge's request to change the scale and standard can be adjusted by both parties through consultation, the contract cost will not be adjusted in all other cases.

5. Unless otherwise stipulated in the contract, the contract price is applicable to any implementation method of any project specified or included in the contract documents, and the contractor shall not require any additional expenses due to different or changed construction methods.

6. Any construction scheme and technical measures adopted by the contractor shall be approved and recognized by the person in charge. If the contractor's construction plan and technical measures are not approved by the person in charge, the contractor shall be responsible for the expenses and consequences arising therefrom.

Fourth, payment

The project settlement shall be calculated according to the construction progress of Party B, and 35% shall be paid after the completion of the first floor, 35% after the completion of the second floor, 25% after the completion of the project, and 5% shall be used as the quality guarantee. The liability period for quality defects is two years.

5. Delay compensation

1. If the project is delayed due to the contractor's reasons, the contractor must pay the delay compensation to the person in charge, and the person in charge can deduct the compensation from any amount that should be paid or will be paid to the contractor, but it is not excluded to recover the amount by other means. The payment of the compensation fee does not relieve the contractor of his responsibility to complete the project or other responsibilities stipulated in the contract.

2. The compensation for delay in this contract shall be calculated at 5% of the contract price every day and paid by the contractor to the person in charge.

Intransitive verb tax

1. The contract price includes all taxes and fees payable by the contractor during the project implementation.

2. Before signing the contract, the contractor shall fully understand and understand the relevant government regulations on taxes and fees. Once the contract is signed, it will not be adjusted during the execution of the contract.

VII. Term of the Contract

1. The contractor's mobilization time for this contract is tentatively set as year month day, and the whole project will be completed before year month.

2. The contract period stipulated in this clause refers to the time when the engineering entity in the contract passes the completion acceptance.

3. In order to realize the construction period, the contractor must take all measures to ensure that it can be realized on time without delay. If the person in charge thinks that the progress of the whole project or part of the project is too slow to meet the requirements of ensuring the key construction period, the person in charge may instruct the contractor to speed up the progress or modify the original construction plan. The contractor shall not make any compensation to the person in charge for this.

4, the contractor must be in accordance with the requirements of the head, before the start of the implementation of construction organization design, the progress plan of each division subdivisional work submitted to the head for approval. The approved implementation of the construction organization design and schedule will become a part of this contract.

5. The person in charge reserves the right to temporarily stop the engineering work, and the contractor shall not refuse.

Eight. Warranty service period after project handover

1. According to the minimum warranty period of housing construction projects stipulated in the upcoming Regulations on Quality Warranty of Construction Projects, this contract stipulates that the warranty period of this project is 30 years under normal use conditions. The warranty period of roofing waterproof works, toilets, rooms and external walls with waterproof requirements is 5 years; The warranty period is calculated from the date of project completion acceptance.

2, matters not covered, should be implemented in accordance with the provisions of the "housing construction quality warranty measures".

Nine. Procurement, supply and storage of materials and equipment

1. The person in charge is responsible for the procurement and supply of all materials and equipment in this contract, and the contractor is obliged to provide assistance, guidance and treatment for the procurement of materials and equipment.

2. The contractor shall not only give the material and equipment supply plan purchased by the person in charge in the construction organization design, but also give the material and equipment purchase notice in advance in the construction process.

3. The contractor shall be responsible for keeping the materials and equipment delivered to the site. The person in charge shall not be responsible for the loss or damage of the contractor's construction tools, equipment and temporary facilities at any time.

X. Safe and civilized construction

1, safe and civilized construction must meet the requirements of relevant management regulations in Wuhan.

2, the contractor shall strictly abide by the national "production safety law" and the relevant safety regulations of Wuhan, and take full responsibility for all safety accidents.

3. If the responsible person is claimed by others for the safety and civilized construction of the contractor, the responsible person reserves the right to claim compensation from the contractor.

XI。 quality

1. Engineering quality standards: national quality inspection and evaluation standards and relevant provisions of the terms of this contract.

2. No matter whether the person in charge has carried out and passed various inspections, the contractor cannot be exempted from the responsibility for the quality of the project contracted by him, unless the quality problem is caused by the person in charge, the contractor shall promptly notify the person in charge of such quality problems.

3. Whether the engineering materials are supplied by the responsible person or not cannot exempt the contractor from the responsibility for the overall quality of the project. The contractor shall inspect all kinds of materials, equipment and equipment according to the specifications, and refuse unqualified materials, equipment and equipment to be used in the project.

Twelve. Technical terms of this contract

Thirteen. any other business

1. The written agreement or text of both parties on engineering negotiation and change shall be regarded as an integral part of this contract.

2. The contractor hereby agrees with the person in charge to ensure that the construction, completion and defect repair of this project are fully contracted as stipulated in the contract, and shall undertake the project quality warranty responsibility within the quality warranty period.

3. Considering that the contractor will carry out the construction, completion and defect repair of this project, and assume the responsibility of engineering quality warranty during the quality warranty period, the person in charge hereby reaches an agreement to ensure payment to the contractor in the way and time stipulated in the contract.

Fourteen Entry into force of contract

This contract shall come into effect as of the date of signing, and each party shall hold one original.

Date of Contract Signing: Date of Contract Signing:

Party A: (signature, handprint)

Party B: (signature, handprint) Address: Address:

Tel: Tel: