1, new workers must carry out safety education, be familiar with the safety technical operation procedures of this type of work, and pass the examination.
Post operation, and should improve the three-level safety education card at the same time;
2, daily safety education must be carried out before the construction work, and should have a detailed safety record;
3, subcontractors must be aimed at engineering division (disciplines) parts in written form to the team and individual publicity.
All technical disclosure and safety technical disclosure must be signed;
4, subcontractors project manager, full-time security officer, electrician, living area management personnel must attend every Monday organized by our company,
At 9 o'clock on Thursday morning, two major safety inspections were carried out on the construction site and living quarters;
5. Our company will issue a safety rectification notice to subcontractors according to the potential safety hazards found in the on-site safety and civilized construction inspection.
The subcontractor must complete the rectification within the rectification period and reply to our company in writing;
6, special operations personnel must go through special operations safety training and education, and hold the operation certificate. When special operations personnel enter the site, the work permit shall be copied to the security department of our company;
7. When welding and cutting operations are carried out at the construction site, the Approval Form for Hot Work must be issued and strictly implemented. The validity period of the Approval Form for Hot Work is: first-class hot work permit 1 day, second-class hot work permit for 3 days and third-class hot work permit for 5 days. When hot work is carried out on site, you must carry the hot work permit and the special type of work operation certificate with you;
8. All units must equip their employees with corresponding qualified labor protection articles according to the requirements of specifications, and check and update them regularly. Product-related information of labor protection articles must be submitted to our company;
9. All kinds of materials and machinery on the construction site must apply to our company for release, and materials and machinery that have not been released shall not enter the site;
10, each unit must designate a special person to be responsible for the storage of materials and finished and semi-finished materials in this area.
Second, the safety protection civilization construction
1, security protection
(1) All construction personnel must wear safety helmets and fasten safety helmet belts when entering the construction site;
(2) For aerial work exceeding 2m (including 2m), you must fasten your seat belt, which must be hung high and used low;
(3) The use and operation platform of the miter ladder must be made of solid materials, the span of each step of the miter ladder shall not exceed 30mm, the middle part of the miter ladder must be tightened with a pull rope, and the upper part of the operation platform must be protected;
(4) Without our approval, it is forbidden to dismantle all kinds of safety protection facilities;
(5) Stairs, elevator shafts, electromechanical reserved holes, etc. There must be protective measures that meet the requirements, and the protection should be tight and firm;
(6) Every limb around floors, stairs, platforms or balconies and roofs must have protective measures that meet the requirements, and the protection should be strict and firm.
2, civilized construction
(1) The construction responsibility area of subcontractors shall be kept clean and tidy, and the site garbage shall be cleared as it is done, and whoever does it shall clean up the site after work;
(2) The raw materials, components, machines and equipment on site shall be neatly stacked in the designated area, and the roads shall be kept clear. Construction waste should be piled up and transported out in time, and it is forbidden to throw it at will, so that there is no accumulation of garbage, waste water and scattered objects on the working surface;
(4) River sand, cement and other dust-prone materials must be covered, and dust-proof measures should be taken, and ground residues should be cleaned up in time;
(5) The construction site materials and construction machines and tools shall be placed in the designated place as required and neatly stacked;
(6) When dealing with high-rise materials and cleaning up garbage, powdery granular garbage materials should be bagged and transported by elevator, and supervised by special personnel;
(7) The site stacking position shall not affect the construction, and it is forbidden to overload and pile materials on the ground. Construction waste must be cleaned up in time and transported to the garbage pool;
(9) It is strictly forbidden for the construction personnel and site management personnel of each unit to urinate at will at the construction site, and it is strictly forbidden to smoke in the no-smoking area at the construction site; It is forbidden to work after drinking and fatigue; It is forbidden to wear high heels, slippers, shirtless and shorts to enter the construction site;
(10) Fighting between all kinds of construction workers is strictly prohibited. Once found, it will be dealt with seriously, and the serious cases will be handled by the local police station.
Third, temporary electricity consumption
The setting, installation, use and maintenance of electrical equipment, distribution box and power supply line must strictly comply with the requirements of JGJ-46-2005 specification of the Ministry of Construction. Subcontractors must be equipped with full-time electricians, who must hold relevant certificates, and other personnel are not allowed to engage in electrical installation and maintenance.
1, distribution box and switch box
(1) The configuration of distribution boxes and switch boxes at all levels that each unit enters the site must be accepted by the general contractor's security department before use;
(2) Each distribution box and switch box shall be marked with the name, purpose, number and loop leader, and equipped with brackets and locks;
(3) Distribution boxes at all levels should be provided with overload short-circuit protection and leakage protection to ensure "three-level distribution and two-level protection";
(4) The main distribution box and switch box are provided with leakage protection switches, and the terminal switch box is protected by "one box, one machine, one brake and one leakage". The rated operating current and operating time of the leakage switch set in the switch box shall not exceed 30mA and 0. 1 s;
(5) The electric box shall be installed firmly, and the installation height shall not be lower than 600 mm on the ground. Outdoor installation should be equipped with rain protection device;