(1) The field operators (above derricksen), mud logging workers, professional and technical personnel, production management personnel, field service personnel and related technical personnel engaged in drilling production must hold valid drilling well control training certificates. Leading cadres and technicians who have not obtained the certificate of drilling well control training have no right to direct production.
(2) The drilling well control operation certificate is valid for two years. Before the expiration of the validity period, the certificate must be replaced and the evidence must be obtained again. The original certificate is invalid.
(3) The relevant departments of the oilfield company have the right to stop the construction work of the construction team and construction personnel with false certificates and unlicensed operations, and investigate the responsibilities of the relevant departments.
Sixtieth three-level training system:
(1) The technicians of the drilling company or drilling team are responsible for organizing regular well control technical post training for employees of the unit and practicing the well control emergency plan of the unit.
(2) The drilling company is responsible for the pre-job well control knowledge training for workers in general positions of the drilling team.
(3) Well Control Training Center of Liaohe Oilfield is responsible for obtaining evidence and replacing certificates for corresponding certified personnel.
Article 61 Classification of training objects
(1) On-site operators: driller, driller, assistant driller, derrick man, drilling technician, driver, drilling fluid foreman, shift attendant, back-up and lead tong men and mud logging workers of the drilling team.
(2) Professional technicians: drilling engineers, designers, engineering managers, underbalanced drilling technicians, etc.
(3) Production management personnel: leaders at all levels in charge of drilling work, drilling supervisors, chief and deputy captains of drilling teams, instructors, safety officers, safety supervisors, etc.
(4) On-site service personnel: technicians and equipment maintenance personnel in the well control workshop.
(5) Relevant technical personnel: relevant technical personnel of professional service teams such as geological design, geological supervision, logging supervision and logging, cementing, mud logging, drilling fluid, coring, salvage, directional well and midway test.
Article 62 the well control technology training content
(a) well control technology:
1. Detection and prediction of formation pressure.
2. Causes of overflow and blowout and timely discovery of overflow.
3. Principle and parameter calculation of shut-in procedures and common well killing methods.
4. Well killing construction and handling of complex well control problems.
5. Knowledge of 5.H2S protection and underbalanced drilling.
(2) Well control device:
1. Structure and working principle.
2. Installation and debugging requirements.
3. Maintenance and troubleshooting.
(3) Detailed rules, well control technical regulations and relevant standards of China Petroleum and Natural Gas Group Company and Liaohe Oilfield.
(4) The characteristics, key points, problems and typical well control cases of Liaohe Oilfield.
Sixty-third well control training should be based on different training objects and the characteristics of well control work in Liaohe Oilfield, focusing on pertinence and classification:
(1) The key contents of on-site operator training include measures and methods for timely finding overflow and timely shut-in; Correctly implement shut-in operation procedures; Installation, use, maintenance and maintenance of well control equipment.
(two) the key contents of professional and technical personnel training include the method of correctly judging overflow; Correct shut-in procedures; Prepare well killing design and procedures, and implement well killing operation; Correctly judge the faults of well control devices and eliminate general faults; Correctly handle blowout and blowout out of control.
(3) The training of production management personnel focuses on the overall supervision and management of well control work, secondary and tertiary well control technologies under complex conditions, well control design principles, etc.
(4) The training of field service personnel mainly includes the structure and working principle of well control device, installation, debugging, maintenance, fault judgment and elimination of well control device, etc.
(5) The key contents of relevant technical personnel training include the concepts of various pressures in the wellbore and their relationships; The main causes of overflow, instructions and coordination requirements in dangerous situations, etc.
(VI) The contents of the certificate replacement training should be selected according to the industry standards and the revision of well control regulations of CNPC, combined with the well control rules of Liaohe Oilfield.
Article 64 The well control training center must meet the requirements of teachers, teaching equipment, teaching materials, teaching AIDS, school conditions and other provisions in the Management Measures for Well Control Training of China Petroleum and Natural Gas Group Company, and obtain the well control training qualification of the Group Company.
Article 65 The training hours and assessment methods for obtaining certificates and changing certificates shall meet the requirements of Management Measures for Well Control Training of China Petroleum and Natural Gas Group Company and Management Rules for Assessment of Well Control Safety Technology for Oil and Natural Gas Drilling. After the theoretical examination and practical operation assessment are all qualified, the well control training institution will issue the certificate of drilling well control training of the Group Company. Well control management department and engineering technical service enterprise of Liaohe Oilfield Company are responsible for supervision, inspection and management.