Second, when the floor is delivered, it must be unpacked and checked to confirm that the delivered floor is the model you ordered. It's best to take all the floors apart and check the quality problems. Carefully compare the color difference. Although the floor will inevitably have some chromatic aberration, if the chromatic aberration is too unacceptable, you can reject it and contact the seller as soon as possible to solve it. Don't wait for the floor to be paved before you find the color difference, which will cause losses at this time. Moreover, the general floor seller will let the owner sign for it when sending it to the floor. Once signed, it means that the quality of the floor is recognized.
Third, because the home has been basically completed when the floor is laid, workers should remind them when they arrive at the scene to avoid hitting the finished product. Before drilling the installation holes of skirting board and door batten and sawing the lower end of door cover, workers should clearly tell them where they can't drill and cut, so as not to damage the original water pipes and conduits. This is very critical. Many owners I know have encountered nail skirting boards pricking water pipes.
Fourth, before construction, we should re-check the laid direction and method determined in advance with the workers. In addition, it is necessary to open several more packages of floors, check the color and texture changes of the floors together with the workers, and determine whether to lay them randomly or in different shades before laying them. You can lay some floors with ugly colors under large furniture such as cloakrooms and beds. When my family was laying the floor, we also chose some floors with horizontal texture to lay in the aisle. After paving, it looks very chic and distinctive.
Five, the distance between the door and the floor (including the thickness of the door batten) should be kept above 4 mm after laying to prevent the back door from sinking and affecting the opening and closing.
Six, sawing the floor is best in the balcony, bathroom or corridor operation.
Seven, the expansion joint between the floor and the wall to ensure that 8- 10 mm, otherwise the floor will lose free expansion space, easy to arch. Generally, if the floor thickness is greater than 8 mm, you can also cut a piece of 8- 10 mm thick wood as a wedge and press it on the expansion joint near the wall as a measure. When installing the skirting board, the wooden wedge placed in the expansion joint must be taken out, otherwise the expansion joint will be left in vain. The installed skirting board shall completely cover the expansion joint. In order to install the baseboard firmly, it is best to fix it with nails. After the installation is completed, please ask the oiler to repair the nail holes and seams. The yin and yang angle of the baseboard should be 45 degrees diagonally, which will look much better.
Eight, the moistureproof layer of the ground and the geothermal floor are laid with plastic sheets, and the interfaces must be overlapped and glued with tape.
Nine, the floor length or width is greater than 8 meters, the interface between the room and the hall or door must be installed layering.
Ten, the wooden floor installation must be kept dry, after all, the wooden floor is afraid of moisture. In order to avoid future problems, these preventive measures must be taken.