Current location - Education and Training Encyclopedia - Graduation thesis - Thick slurry epoxy coal tar asphalt topcoat v. Construction reference
Thick slurry epoxy coal tar asphalt topcoat v. Construction reference
1, the surface of the coated object must be dry and clean, without scale, rust and oil stain.

2. When the base temperature is lower than 3℃ or the air humidity is higher than 85%, it is not suitable for construction.

3. After the component A must be fully stirred, pour the component B into the component A according to the matching requirements, fully mix and stir, let stand for 30 minutes, add an appropriate amount of supporting diluent, and adjust it to the construction viscosity.

4. The service life is 4h(25℃).

5. Air spraying, brush coating or roll coating (continuous stirring is required during coating to prevent precipitation).

6, repainting interval:

Minimum interval h4824 12 of substrate temperature℃ 5-15-2025-30.