According to Article 4 1 of the Bidding Law,
Article 41 The bid of the winning bidder shall meet one of the following conditions:
(a) to meet the comprehensive evaluation criteria specified in the tender documents to the maximum extent;
(two) to meet the substantive requirements of the tender documents, and the evaluated bid price is the lowest; Only the bid price is lower than the cost.
As can be seen from this clause, the main bid evaluation methods are as follows
(1) comprehensive bid evaluation method;
(2) The lowest bid evaluation method.
I. Comprehensive bid evaluation method: (commonly known as "scoring method")
Features: All terms of the tenderer's qualification, technology, business and service are converted into a certain score, with a total score of 100. When evaluating bids, all indicators of bidders shall be reviewed and checked for compliance, and scores shall be given. Finally, the bidder with the highest score will be selected as the winning bidder.
When evaluating bids, the judges score independently and do not discuss with each other; Finally, summarize the scores.