Preparation of detailed urban regulatory planning: preliminary investigation is under way.
Urban design of key areas: the design of the new administrative area has been completed, and the planning review meeting of the new area will be organized on May 7.
Areas on both sides of the West Ring Road: Scheme design is under way.
War zone: the planning and design scheme has been determined, and some projects have started. Among them, the second street bend project began to be demolished, and initial contact was made with Wal-Mart's headquarters in China at the end of April. Other projects are being prepared in advance.
Special planning: the selection of the organization has been completed and the work plan is being submitted for approval;
Town planning: A special work conference will be held in the near future to deploy the city's town planning and construction work.
(2) Road construction projects
Chang 'an Road Construction Project: Drainage construction began on April 28th.
North extension project of Jingkai Road: At present, the site survey has been completed and the construction drawing design is under way.
Petrochemical Road West Extension Project: The site survey has been completed and the construction drawing design is under way.
Kunlun Road Construction Project: The construction drawing design has been completed and the project budget is under way.
Dongfeng road greening and lighting: the greening part is under way and is expected to be completed in late May; The lighting part has completed the installation of light poles and cable laying.
(3) Renovation project after canal opening: Dewatering and dredging have been completed, and slotting is being prepared as cushion, and houses and trees within the renovation scope will be demolished and cut down.
(4) Construction of sewage pumping station
Preparations before installation are under way and are expected to be completed by the end of June.
(5) Street View Reconstruction Project
Reconstruction of Yuhua Road Street View: The first phase of the project has completed the laying of concrete cushion and asphalt pavement, and now the laying of stone and concrete bricks is underway, and the ground works have been completed by 50%.
Reconstruction of West Ring Road Street View: Planning and design are under way, and the selection of design institutions has been completed. Three design units have been selected, and the work plan has been submitted to be determined.
(6) Urban greening project
The urban greening project has completed the replanting of trees and some shrubs.
(7) Construction of convenience facilities
At present, the site selection of 20 public toilets and 18 garbage transfer station has been completed. Among them, the government square mobile public toilets have been completed and put into use; The public toilet on the west side of Yuhua Road Education and Sports Bureau entered the venue on May 4; Six public toilets, such as the 4th West entrance of Yuhua East Road, the warehouse of Yuhua West Road Seed Company, the west entrance of Xinhua Road Supply and Marketing Cooperative, the south gate of Dechun Swimming Pool of Huizhan North Road, the 1st Squadron of Traffic Police of Jianshe East Road, and the family area of Ma Rong Factory of Jingkai North Road, are comparing their renderings, and the next step is to start the construction drawing design.
(8) Landfill Project
At present, the preliminary design of the project is being revised and improved; The procedure of adding 45 mu of land for borrowing soil has been completed.
(9) Natural gas household project
At present, the courtyard pipe network of Qingfeng Garden Community is 60% completed, and the indoor hanging table is 10%. The courtyard pipe network of Guoan, Radio and Television, Sanitation and other three communities has been completed 80%; LAM Raymond residential courtyard pipe network completed 30%; The medium pressure pipeline in the east and west sections of Yuhua Road (Yanshan Road to Hong Kong Street in the east section and Zhanhui Road to National Road in the west section 106) is under construction; The construction of medium pressure pipeline of Zhong Kai Jiayuan Phase II gasification project was completed; Zhuang Lin gas design drawings are being optimized and adjusted.
(10) Cultural and Art Center Project
At present, the main project has been completed, and the top grid structure, foundation reinforcement and outdoor stepping construction are under way; The exterior decoration project has completed the pre-qualification of the team and will be invited for bidding soon; The construction drawing design of indoor installation project is in progress; The fire protection project was invited for bidding on May 5th.
(1 1) steel market construction
At present, the earthwork bidding and grave sweeping have been completed, and road reconstruction is under way.
II. Brief Introduction of Qu Kai Reconstruction Project
Jingkai Canal is a river running through the north and south of our city. It depends on the rivers in Nantong in the north, Xiaobaihe in the north and Baiyangdian, the pearl of North China in the north. The canal is now a confluence of rain and sewage, and the phenomenon of "dirty, chaotic, poor and smelly" is very serious, which has affected the life of citizens and the image of the city. In order to improve the urban environment and build an "oil city near Yunnan", the municipal party committee and the municipal government listed the renovation of the Beijing Canal as a "major event and practical matter" in 2009.
The reconstruction project of Jingkai Canal is 360 meters long and 39 meters wide from east to west, with an estimated investment of 20 million yuan. The transformation plan is to divide rain and sewage, build two underground sewage pipes at the bottom of the canal, discharge sewage into underground pipes, build a clear water open channel on the ground, lay rubble at the bottom and wall of the canal, set rubber retaining dams at both ends, and build green belts, parking lots, public toilets and leisure facilities on both sides of the canal. The project entered the site on March 24th. Now, the dewatering and dredging work has been completed, and the slotting cushion is being carried out to prepare for laying underground sewage pipes. The demolition and felling of houses and trees within the scope of renovation is expected to be completed before the end of June.
After the project is completed, the city will have another beautiful landscape.
3. CPPCC leaders and some members inspected key urban construction projects.
On April 24th, Chairman Hao Lv and his team of 28 people, accompanied by leaders of the Municipal Construction Bureau and relevant responsible persons, inspected key urban construction projects in our city.
First of all, Chen Zhenhuai, director of the Construction Bureau, briefly reported on the management of urban construction this year. Subsequently, the CPPCC delegation visited the Culture and Art Center, Yuhua Road Street View Reconstruction, Jingkai Canal Reconstruction, Yanling Park and New Steel Market successively, and listened to the reports of relevant departments. After the on-site inspection, a discussion meeting was held. Members fully affirmed the urban construction work and put forward opinions and suggestions.
Chairman Hao finally pointed out that key urban construction projects are an important force to promote the economic and social development of our city, and are of great significance to improving urban functions, urban environment and quality of life. Doing a good job in the design, construction and management of key urban construction projects is an important measure to implement Scientific Outlook on Development and improve the work style, and puts forward the following requirements for urban construction work: First, we should further intensify the demolition and construction work and complete the task of changing the city's appearance in three years to the letter; Second, it is necessary to further strengthen the implementation of the plan and earnestly safeguard the seriousness and authority of the plan; Third, we should further strengthen urban management, improve urban management mechanism and build a livable city; Fourth, further strengthen urban construction, improve urban functions and improve urban carrying capacity; Fifth, it is necessary to further increase the publicity of urban construction work and create a public opinion atmosphere in which people's cities are built and managed by the people.
Director Chen Zhenhuai thanked the leading members of CPPCC for their concern and support for urban construction, and said that they would seriously absorb the opinions and suggestions of CPPCC members to make Renqiu a better place. Vice Mayor Zhang Jinzeng attended the forum and made comments.
Four, the Construction Bureau carefully organized and listened to the "Sunshine Hotline" program of Hebei Radio Station.
From 7: 30 am to 8: 20 am on April 24th, the Construction Bureau organized middle-level and above cadres to listen carefully to the program "Sunshine Hotline" of Hebei People's Broadcasting Station with the theme of "cleaning up and standardizing charging behavior and optimizing Hebei's development environment", and then conducted in-depth discussions and self-examination and self-correction according to the main problems reflected by the masses in the program and the conversation spirit of the executive vice governor Fu Zhifang and other leaders, combined with the actual urban construction work in our city.
Through discussion, everyone agreed that it is timely and necessary to listen to the program and make self-examination and self-correction. According to the opinions and suggestions of the masses on urban construction, the Construction Bureau will further clean up and standardize the charging behavior, improve the working methods, reduce the burden on enterprises and the masses, and better serve the masses.
Five, the dynamic bidding of key urban construction projects
1, Dongfeng Road Greening Project released the tender information on April 2, 2009, and issued the tender documents on April 9, 2009. A total of 1 1 qualified units such as Cangzhou Shi Ying Company, Hongye Garden Company and Cuiyuan Garden Company have signed up for bidding. The bid evaluation began on April 1 1, and the bid evaluation experts determined that the candidate unit for winning the bid was Cangzhou Shi Ying Company.
2. The bidding information of Dongfeng Road Lighting Project was released on April 2, 2009, and the bidding documents were issued on April 9, 2009. Huayou Lighting City, Yangzhou Haifeng and other three qualified units signed up for bidding. The bid evaluation began on April 1 1, and the bid evaluation experts determined that the candidate unit for winning the bid was Cangzhou Shi Ying Company.
3. The tender information of the fire protection project of the Cultural and Art Center was released on September 6, 2008, and the tender documents were issued on April 27, 2009. Nine qualified units, including Shijiazhuang Jindun, Beijing Yatai and Hebei Longtai, signed up for bidding. The bid evaluation began on May 5th, and the bid evaluation experts determined that the candidate unit for winning the bid was Shijiazhuang Jindun Company.
4. The public toilet project bidding information was released on April 27th, 2009, and three qualified units, Lixin, Jianyi and Wu Wang, signed up for bidding. The bid evaluation began on April 29th, and the bid evaluation experts determined that the candidate winning bidder was Lixin Company.
Six, the Municipal Construction Bureau conscientiously implement the "Regulations on the regulation of vicious braking bad atmosphere"
Since the year of cadres' work style construction and study and practice in Scientific Outlook on Development, Renqiu Construction Bureau has actively carried out various activities in accordance with the requirements of the municipal party committee, municipal government and superiors, and conscientiously implemented the spirit of instructions from superiors. On May 4th, we organized a special meeting for middle-level and above cadres to seriously study and deploy the Provisions on Stopping Bad Practices. All directly affiliated departments are required to attach great importance to it, pay close attention to its implementation, earnestly strengthen the construction of work style, be strict in discipline, put an end to unhealthy practices such as inaction, arbitrary charges and fines, and violation of work discipline, and further increase publicity through the internet, bulletin boards and other forms to create a good atmosphere. At the same time, increase accountability, and seriously investigate the responsibility of relevant responsible persons for units or departments with bad atmosphere.