Emergency investigation and drill scheme of geological disasters in Shandong Provincial Department of Land and Resources
Shandong Provincial Department of Land and Resources

(2065438+29 July 2003)

In the flood season, geological disasters in our province have entered a period of high incidence. In order to improve the emergency response capability of geological disasters, the ministries and agencies decided that the competent departments of land and resources at the provincial, city and county levels should jointly carry out actual combat drills for emergency investigation of geological disasters, and it is planned to invite relevant personnel from the Provincial Meteorological Bureau to participate. The following exercise plan is specially formulated.

I. Purpose of this work

Exercise the geological disaster emergency investigation team, test emergency equipment and capabilities, improve technical response capabilities, and improve the level of geological disaster emergency response.

Second, exercise tasks

The main task is to simulate the emergency investigation of a single geological disaster, test the emergency response ability and emergency investigation ability of relevant departments and personnel to sudden geological disasters through drills, and test the technical support degree of the construction of geological disaster emergency technical platform and related emergency equipment in our province.

The specific tasks are:

(1) Emergency pull of geological disaster investigation department, emergency mapping department and meteorological information service department.

(2) Implement the emergency investigation on the geological disaster of the north abutment landslide (collapse) of Wohushan Reservoir in Zhonggong Town, Licheng District, Jinan City.

(3) Try out the system and equipment for the construction of early emergency technical platform for geological disasters.

(4) Video and audio remote consultation and command to simulate geological disasters.

(5) Prepare the technical report on emergency investigation of geological disasters, suggestions on emergency measures and the first draft of information release.

Three. Location, time and background of the exercise

Exercise location: North abutment of Wohushan Reservoir, Zhonggong Town, Licheng District, Jinan City.

Exercise time: 2065438+July 29th, 2003 13: 00- 18: 00.

Background of the drill: A group of surveyors in the disaster point group at the north abutment of Wohushan Reservoir discovered the danger of landslide. According to the preliminary investigation, there are 3 threatened families, 12 people, threatening the safety of the residents in the north abutment of Wohushan Reservoir and the downstream of the reservoir. Group monitoring and prevention personnel immediately report the disaster situation to the land and resources departments at all levels step by step, and directly report it to the emergency duty personnel of the Department of Land and Resources. The personnel on duty think that the danger is urgent and significant, and quickly prepare an emergency work plan and report it to the Emergency Management Office of the Department of Land and Resources in time. After receiving the report, the Provincial Department of Land and Resources launched the first-class geological disaster technical response, and immediately requested the Jinan Municipal Bureau of Land and Resources to carry out preliminary investigation and take emergency measures in advance.

Four. Participating unit

Shandong Provincial Department of Land and Resources, Shandong Meteorological Bureau, Jinan Municipal Bureau of Land and Resources, Shandong Meteorological Observatory, Shandong Meteorological Information Service Center, Shandong Institute of Land Surveying and Mapping, Shandong Geological Environment Monitoring Station (Shandong Geological Disaster Emergency Technical Guidance Center).

Five, geological disaster emergency investigation system and equipment

1 set of three-dimensional geological environment information system; Meteorological early warning and forecasting system for geological disasters 1 set; 1 set of 3D laser scanner and supporting measuring equipment; GP S dynamic monitoring system 1 set; Satellite communication vehicle 1 vehicle, 4 other vehicles; 1 set of individual equipment for geological hazard investigation, 2 sets of individual equipment for automatic geological hazard monitoring and hand-held GP S3 department; Aerial drone1; 4 intercom devices; 2 satellite phones; Some weather forecasting system equipment; Video monitoring system for geological disasters; Mobile weather station.

Sixth, the content of the exercise.

(1) drill the emergency technical response procedure for geological disasters.

(2) Jointly carry out meteorological early warning and forecast of single-point geological disasters with meteorological departments.

(3) Conduct real-time consultation and command on emergency investigation of disaster points through video consultation system.

(4) Technical methods and contents of emergency investigation and monitoring of single geological disaster.

(5) Try out the technical methods and procedures for emergency investigation of single-point geological disasters by using satellite communication system, individual equipment, 3d scanner system and UAV aerial photography system.

(6) The preparation process and method of emergency investigation report, emergency response plan and information release.

(7) Video monitoring of geological disasters and real-time transmission of individual soldiers.

Seven, exercise organization and personnel

1. Emergency investigation headquarters

Commander: Ning Tinghe

Deputy Commanders: Dong Tongyu, Wang Guangxin, Li Guoxiang and Zhang Zhiguang.

Member: Field Coordinator Fu Ying; Lin Hai and Yan Jingsheng (team leader of rear experts); Shen Yude and Han Jingmin, emergency response during on-site investigation; Gao Shankun, the person in charge.

Responsibilities: Responsible for organizing, coordinating, guiding and commenting on the technical work of the drill, participating in discussing the basic situation of the disaster situation, handling emergencies during the investigation and reporting to the provincial government and the Ministry of Land and Resources.

Specific division of labor: Ning Tinghe is responsible for issuing instructions and commenting on the end of the exercise; Dong Tongyu is the chief commander in charge of aerial photography; Wang Guangxin is responsible for presiding over the exercise; Zhang Zhiguang is responsible for coordinating meteorological information; Li Guoxiang observation and guidance; Fu Ying is responsible for the overall coordination of the drill site; Lin Hai is responsible for the technical guidance of the drill; Yan Jingsheng is responsible for organizing and consulting the exercise; Shen Yude's observation and guidance; Han Jingmin is responsible for directing emergency response during on-site investigation; Responsible for quick reporting of disasters and dangers during his term of office; Gao Shankun is responsible for the compilation of drill information.

2. Rear Advisory Expert Group

Team leader: Yan Jingsheng

Deputy team leaders: Chang,,,.

Member: Shouji came to Zhang Shijie from his roots.

Responsibilities: responsible for consultation, disaster and danger judgment, summary of investigation results and discussion of basic situation of disaster.

3. Relationship Coordination Group

Team leader: Wang

Members:, Yue Qingjie, Shu, Zhang Mingting, Cui Jinghe

Responsibilities: Be responsible for the coordination of local relations, participate in negotiations, and place six warning signs at the intersections at both ends of the landslide section and at two landslide points respectively.

4. Disaster and Danger Investigation Team

Team leader: Hu, in charge of on-site technology.

Deputy Team Leaders: Yang, Yang Zongbo, Bian

(1) Fang Qinghai (team leader) and Zhang Jingkang of geological and topographic survey team.

(2) Disaster investigation team Zhang Yongwei (team leader) and Liang Hao.

(3) Danger investigation team Wang Qingbing (team leader), Meng.

(4) Emergency Monitoring Team Dong Qiang (Team Leader), Yang Peijie, Wang Ning, Lin Zhao and Li Yongchao.

Responsibilities: Responsible for carrying single soldier, 3D laser scanner, hand-held GP and other equipment to investigate geological disasters.

Specific division of labor: Hu is responsible for on-site technology and carries walkie-talkies.

Yang, Yang Zongbo and Bian are responsible for meteorological personnel and equipment on site. Fang Qinghai is responsible for geological and topographic survey. With the cooperation of Zhang Jingkang, he carries a camera and holds GP and topographic map to accurately draw geological maps and geological profiles.

Zhang Yongwei carries walkie-talkies, satellite phones, automatic monitoring 1 set, and is responsible for disaster investigation; Liang Hao carries a camera, holds a GPS, and fills out a disaster investigation form; Wang Qingbing carries satellite communication equipment and is responsible for dangerous situation investigation; And Meng carry hand-held GPS, and fill out the Survey Form of Danger at Disaster Points.

Dong Qiang is responsible for emergency monitoring and carrying walkie-talkies; Dong Qiang and Yang Peijie undertake static GPS monitoring and carry 1 set of automatic monitoring soldiers; Wang Ning and Lin Zhao Li Yongchao are in charge of 3D laser scanning.

5. Image aerial photography team

Team leader: Yang Yanping

Deputy leader: Mao

Members: Zhang Weiguo, Zhang Heng, Wu Xuechao, He Yougang, Zhang Guangqing, Yang Jian, Gao Min.

Responsibilities: Responsible for aerial photography and image processing.

6. Technical Network Support Group

Team leader: Jia Wei

Deputy Team Leaders: Zheng Tingming, Ren Cuiai, Han.

Members: Zhang Ye, Sha Lingbao, Zheng Xiurong, Hu, Wang, Zou Lianqing, Cao Chunshan and Liu Yang.

Specific division of labor: Jia Wei is responsible for the technical support of the rear experts' consultation, the meteorological early warning and forecast of geological disasters, and the report on the basic situation of disasters (in case of emergency); Zhang Shengtao is responsible for the connection and debugging between the provincial offices and the emergency hall of the main station; Zou Lianqing is responsible for the application of three-dimensional geological environment information system, the switching of audio and video system in emergency hall and the connection and debugging of emergency hall; Ren Cuiai is responsible for sorting out expert opinions; Sha Lingbao stays on duty for forecasting and is responsible for meteorological data transmission; Hu is responsible for map search and modification; Zheng Tingming is responsible for the smooth flow of network communication and the handling of emergencies; Wang, Zhang Ye and Liu Yang are responsible for the connection debugging and switching of satellite communication vehicles; Cao Chunshan is in charge of driving the satellite communication vehicle.

7. Logistics Services Section

Team leader: song heping

Deputy leader: Han

Members: Chen,,, Zhu Guo.

Specific division of labor: song heping is responsible for logistics services and emergency response; Han and Chen are responsible for emergency vehicle preparation and dispatching and driver arrangement; Li Qinghai, Lin Ming, Li Dayong and Zhu Guo are ambulance drivers.

8. Communications Group

Team leader: Wu Wenfeng

Members: Yang Xuezuo, Zhao.

Eight, exercise procedures

This drill is divided into four stages:

(1) Emergency investigation start-up stage (13: 00— 14: 00): The team surveyors report the disaster situation, and the provincial offices start the first-level technical response, prepare the emergency investigation plan, and set up an emergency investigation team to prepare for departure.

(2) Emergency investigation stage (14: 00— 16: 25): Each team arrived at the designated place and started the investigation in groups.

(3) Emergency consultation stage (16: 25 ——16: 50): Experts from both sides conduct emergency consultation to form an emergency investigation report, emergency measures suggestions and the first draft of information release.

(4) Emergency end stage (16: 50 ——17:18): The drill is announced and the commander will make comments.

Emergency drill flow chart

Nine. Expected result

(1) Emergency Investigation Report on Geological Disasters at the North Abutment of Wohushan Reservoir in Zhonggong Town, Licheng District, Jinan City

(2) Emergency treatment measures and suggestions for the landslide (collapse) at the north abutment of Wohushan Reservoir in Zhonggong Town, Licheng District, Jinan City.

(3) The first draft of information on landslide (collapse) at the north abutment of Wohushan Reservoir in Zhonggong Town, Licheng District, Jinan City was released.

Ten, emergency investigation drill preparation

1. programming; arrange

The main contents of the plan include the drill purpose, drill task, drill place, time and background, participating units, geological disaster emergency investigation system equipment, drill content, drill organization and personnel, drill procedures, expected results, emergency investigation drill preparation, etc.

Attachments include emergency drill script, emergency investigation plan, start-up report of emergency technical response to geological disasters, release information of geological disasters and dangerous situations, outline of drill summary report and other drill-related contents.

2. Information preparation

Land Surveying and Mapping Institute provides topographic map of disaster point 1: 1 10,000. Jinan Station is responsible for compiling1:50,000 geological map of disaster point, emergency investigation report and blank form of disaster point questionnaire. The monitoring and early warning room is ready to release information and blank forms of emergency measures and suggestions at any time. Blank form for emergency technical response start-up report prepared by emergency treatment room.

3. Equipment system preparation

Shandong Meteorological Bureau is preparing to relocate the weather station. Land Surveying and Mapping Institute prepares aerial drones. Jinan Municipal Bureau of Land and Resources prepares 4 warning signs. The monitoring and early warning room shall prepare satellite communication vehicles, 1 set of satellite communication soldiers, 2 sets of automatic monitoring soldiers, 1 set of satellite phones and 4 sets of walkie-talkies; The monitoring room is responsible for preparing three-dimensional geographic information system, geological disaster meteorological early warning and forecasting system, geological disaster video monitoring system, emergency hall, three-dimensional laser scanner, static GPS and handheld GPS 1. The emergency room is equipped with 1 camera, 1 handheld GPS, 1 satellite phone. The office prepares emergency vehicles.

Selected geological disaster emergency drills 20 13

Selected geological disaster emergency drills 20 13

Selected geological disaster emergency drills 20 13

Selected geological disaster emergency drills 20 13

Selected geological disaster emergency drills 20 13

Selected geological disaster emergency drills 20 13

Selected geological disaster emergency drills 20 13

Selected geological disaster emergency drills 20 13