Qingdao Bay Bridge, also known as Jiaozhou Bay Cross-sea Bridge, is a super-large cross-sea bridge designed, built and constructed by China. It is the starting point of G22 Qinglan Expressway, a national expressway network, a part of the online framework of "five verticals, four horizontals and one ring" in Shandong Province, and a "one bridge" in the cross-sea passage "one road, one bridge and one tunnel" on the east and west sides of Jiaozhou Bay planned by Qingdao. The bridge starts from Haier Road in the main city of Qingdao and goes to Huangdao via Hongdao. The total length of the bridge is 36.48 kilometers, and the investment is nearly 654.38+0 billion, which took four years to complete. The bridge was opened to traffic on June 30th, 20 1 1.

Brief introduction of bridge

Qingdao Bay Bridge starts from the entrance of Yangjiaqun, Heilongjiang Road, the main city of Qingdao in the east, crosses Jiaozhou Bay and reaches Hongshiya, Huangdao in the west. The total length of the route (Phase I) is 28.047km (Phase II12km). The length of offshore section is 25. 17 1 km, Qingdao side wiring is 749 m, Huangdao side wiring is 827 m, and Hongdao tie line is1.3km.. The estimated investment of the project is 9.04 billion yuan. Quanwan Bridge Project includes Cangkou, Hongdao and Daguhe Waterway Bridges, non-navigable bridges and road approach bridges at sea, connecting projects on both sides of Huangdao and Hongdao connecting lines, Licunhe Interchange, Hongdao Interchange, three main toll stations and management facilities in Qingdao, Hongdao and Huangdao.

20 1 0 65438+On February 22nd, the main bridge of Qingdao Bay Bridge was completed and officially opened to traffic on June 30th, 201year.

The total planned investment of Qingdao Bay Bridge Project is 9.082 billion yuan, and the project is implemented by franchising. According to the Company Law of People's Republic of China (PRC), the self-owned capital of this project is 36,543,800 million yuan, accounting for 35% of the capital, all of which are exclusively funded by Shandong Expressway Group Co., Ltd.

Qingdao Bay Bridge Project is invested and operated by Shandong Expressway, and tied with Jiaozhou Bay Expressway. This project is the largest transportation infrastructure project invested by a single state-owned enterprise in China at present, and it is the first super-large bridge cluster project in the frozen sea area in northern China. Together with the approach bridge and connecting line, the overall scale is the largest bridge in the world.

The operation period of Qingdao Bay Bridge Project is 25 years. At the end of the operation period, all the ownership and management rights of the project will be handed over to Qingdao Municipal Government. During the operation period of the project, it is estimated that the traffic volume of the Bay Bridge will be 30,849 vehicles/day in 2065, 438+00 vehicles/day, 4,565,438 vehicles/day in 2065, 438+036 vehicles/day in 2020 and 77,795 vehicles/day in 2029. The payback period of investment is 15 years (from the franchise year).

Architectural history

Total investment: 9.53 billion yuan.

Project duration: 1993 to 20 1 1 year.

During the period of 1993, the Qingdao municipal government organized an expert demonstration meeting for the first time on the sea crossing scheme, and reached the conclusion that "the south tunnel is north bridge, and the bridge is first followed by the tunnel".

On September 30, 2003, the enlarged meeting of the Standing Committee of the Municipal Party Committee listened to the report of the Municipal Transportation Commission on the elevated road in Huang Qing, and agreed to start the Huang Qing Elevated-Qingdao Bay Bridge (North Bridge) project of the auxiliary line of the national key highway Qingdao to Hongshiya according to the planned route plan;

From February 27th to 29th, 2004, Shandong Provincial Development and Reform Commission presided over the review meeting of "Pre-feasibility Study Report on Huang Qing Elevated Section of Qinghong Branch of National Key Highway".

/10 2004 On June 26th, 2004, according to the national requirements, Qingdao officially submitted the Qingdao Bay Bridge (North Bridge) project to the National Development and Reform Commission for approval.

On March 3, 2005, Qingdao Bay Bridge (North Bridge) project was successfully discussed at the office meeting of the director of the National Development and Reform Commission.

On March 7, 2005, the National Development and Reform Commission approved it with the document [2005] No.327.

On February 26th, 2006, 65438, the project officially started construction.

On February 2, 2007, the first bored pile was successfully poured.

On June 3, 2009, the first tower of Qingdao Bay Bridge, the main tower of Daguhe Waterway Bridge, was successfully capped.

On June 27th, 2009, Qingdao Planning Bureau publicized the planning scheme of urban wiring project of Bay Bridge.

By the end of June 2009, 565,438+065,438+003 bored piles, 65,438+065,438+003 caps, 65,438 piers and 4,365,438 precast box girders had been completed.

On June 5438+February 10, 2009, the main construction of Hongdao Interchange Bridge of Bay Bridge was completed. At this time, 67% of the superstructure and 98% of the substructure of the Bay Bridge have been completed.

65438+On February 27th, 2009, the groundbreaking ceremony of JIAOZHOU connecting line project of Qingdao Bay Bridge was held in new industrial district, JIAOZHOU Bay.

On March 20 13 10, the installation of steel box girder on Qingdao side of Daguhe waterway bridge was completed.

On June 28th, 20 1 1, the JIAOZHOU bay bridge of Shandong Expressway passed the handover acceptance of relevant departments.

2011On the morning of June 30th 10, Qingdao Jiaozhou Bay Bridge was officially opened to traffic.

On August 23rd, 20 13, the bus company of the bus group opened the "High-tech Express Line" passing through Jiaozhou Bay Bridge. From Hippo City to High-tech Zone, there are only 37 seats but no seats.

Important influence

After the completion of the Bay Bridge, the communication between Jinan and Qingdao in the province will be closer and more convenient. In the past, vehicles had to bypass the Jiaozhou Bay Expressway and go to Huangdao along the south line of Qing Ji Expressway. Since the northern starting point of Qing Ji South Line is connected with the Bay Bridge under construction, after the completion of the bridge, vehicles can go directly to Qingdao along Qing Ji South Line and Bay Bridge. The bridge will further promote the traffic links between Qingdao and the cities in the peninsula urban agglomeration, which is of great significance to give play to Qingdao's leading position in the economic development of Shandong Province, further accelerate the construction of the Shandong Peninsula urban agglomeration and promote the tourism development of Jiaodong Peninsula.

For Qingdao, the Bay Bridge is also an important transportation hub in the city's strategy of "protection and development around the bay". After the completion of the bridge, the traffic pressure of Qingdao Jiaozhou Bay Expressway will be greatly relieved, the east-west cross-sea traffic connection of Qingdao will be further improved, the urban skeleton of Qingdao will be expanded, the time and space distance between Qingdao and Hongdao and Huangdao will be shortened, the connection between the main urban area and the two wing sub-urban areas will be strengthened, and the great Qingdao urban framework embracing Jiaozhou Bay will be shaped, opening up a new space for the in-depth development of Qingdao.

The total length of the expressway around Jiaozhou Bay is about 70 kilometers. The construction of the bridge project will conveniently connect Qingdao, Hong and Huang islands, shortening the land distance from Qingdao to Huangdao by nearly 30 kilometers. If the speed is 80 kilometers per hour, taking the bridge will save 20 minutes compared with taking the expressway! The bridge has two lanes and six lanes, with a design speed of 80 kilometers per hour.

Regarding the wind-resistant and fog-proof design of the bridge, experts said that the wind-resistant performance is excellent and it was designed to resist the once-in-a-century gale. But the interference of sea fog is inevitable. To "connect" with the expressway, the whole line should be closed in heavy fog. According to meteorological statistics, the bridge is closed for about 20-30 days every year, and it is closed for about 80 days in strong wind, heavy rain and fog.

traffic

Between Qingdao and Huangdao, Jiaozhou Bay Cross-sea Tunnel and Jiaozhou Bay Bridge have been connected with the expressway around Jiaozhou Bay by ferry until they are completed and opened to traffic. Ferry is limited by transportation capacity and climatic conditions, and can only pass more than a thousand vans every day; The design standard of the expressway around Jiaozhou Bay is 25,000 standard cars/day, but the traffic volume has soared year by year after opening to traffic. At present, the peak traffic volume of standard sections has reached 460,000! The construction of this project will connect Qingdao, Hong Kong and Huangdao conveniently, which will not only shorten the land distance from Qingdao to Huangdao by 30 kilometers, but also ease the traffic pressure. At the same time, the bridge built on Hongdao can also take into account the traffic on Hongdao.

At the mouth of Licun River in the old city, the bridge connects Chongqing Road and National Highway 308 in the form of urban expressway, which directly introduces the traffic flow from the city to the outside of the city into the expressway, reducing the traffic flow collected and evacuated by multiple entrances and exits of Jiaozhou Bay Expressway in all directions in the city, effectively reducing the traffic congestion in the external communication part of the old city and improving the traffic situation in the city.

After the completion of Qingdao Bay Bridge, the business volume of Qianwan Port, Huangdao Oil Port and Xuejiadao Port can be effectively increased, so that the old port of Qingdao, the oil port and Qianwan Port can be integrated, the cooperation among the three ports can be strengthened, and the overall benefits of the ports can be better brought into play, especially the problem of land collection and transportation capacity of Qingdao Port.

industry

According to the industrial layout, the spatial scope of the east coast area centered on the old city is narrow, and there is almost no room for urban space to expand eastward. As the port moves westward, it is imperative for the economic center to move westward. The construction of Qingdao Bay Bridge organically links the three islands of "green-red-yellow" and greatly promotes the implementation of the urban development strategy of "three-point layout, first-line development and group development" in our city.

travel

In the website of Langyatai Scenic Area, the signboard "After the completion of the Bay Bridge, you can reach the urban area in 30 minutes" has already been hung. It is understood that there are not a few scenic spots like Langyatai waiting for the "benefits" brought by the Bay Bridge. After the project is completed, it will not only release the development space of tourism and tertiary industry in the east, but also connect the contiguous seaside resorts in the old city with the provincial tourist resorts in Xuejiadao, Huangdao District, which will greatly promote the development of Qingdao tourism and form an "encirclement circle" of Qingdao tourism.

Meet/suit the convenience of the local community

In the "Qingdao" online community, netizens have been discussing Qingdao Bay Bridge. One of the senior netizens commented, "Huangdao Development Zone and Qingdao are separated by Jiaozhou Bay, which can be described as' green and yellow'. Therefore, the construction of the cross-sea bridge has become a lingering complex in Qingdao for many years. It's time to wait for no one. "

The customs declaration place of export goods is in Huangdao over there, and most trading companies are in Qingdao city. When an enterprise declares taxes, it can only be paid by the customs broker. Obviously, this has brought inconvenience to their operation and financing. A private entrepreneur said, "I am looking forward to this bridge. I am already eager to see it."

For more exclusive information about the construction industry, please pay attention to the micro-signal of the construction network in real time.

For more information about bid writing and improving the winning rate, click on the bottom customer service for free consultation.