Sample of bricklayer's labor subcontract
For construction enterprises, labor subcontracting management accounts for a large proportion. What do you know about bricklayer's subcontracting? The following is a model bricklayer's labor subcontracting contract that I have compiled for you. Thanks for reading it.

Model text of bricklayer's subcontract 1

General contractor (hereinafter referred to as Party A):

Labor Subcontractor (hereinafter referred to as Party B):

In accordance with the Contract Law of People's Republic of China (PRC), Construction Law of People's Republic of China (PRC) and other relevant laws and regulations, in order to clarify the rights, obligations and responsibilities of both parties during the construction period, in line with the principles of equality, voluntariness and mutual benefit, and in combination with the specific conditions of this project, both parties agree to sign this contract through consultation for common compliance.

Article 1 General situation of the project

1. 1 Project name: Hongri Jincheng 1#, 20#, 2 1#, 22# and civil air defense basement project.

1.2 project address: Lianshui County, Jiangsu Province

Article 2 Scope of project contracting

Scope of contract: Hongri Jincheng 1#, 20#, 2 1# and civil air defense basement projects: all bricklaying projects indicated in the construction drawings and other engineering materials, including: main structure concrete, other structural concrete, brick masonry projects, and all other projects except steel formwork for foundation engineering excavated by manpower, including manual excavation of pit bottom, trimming of slope and parts that cannot be excavated by machinery. Lime soil and gravel cushion; Brick side form; Artificial cooperation, backfill soil compaction leveling (rainy day underground foundation pit cleaning, sewage cleaning, earthwork collapse cleaning, etc. No need to log in separately). ; Indoor and outdoor decoration (all civil decoration works except paint putty, coiled material waterproof coating, doors and windows, metal railings and wood decoration). Carpenters chisel, bricklayers repair and paint concrete wheels.

Article 3 Contract Method and Payment

3. 1 package cleaning: limited selection, package quality, package safety, package construction period and civilized construction.

3.2 Contract Unit Price and Contract Amount

Masonry works: 1# building 1 15 yuan /m2 (excluding brick and external wall insulation board construction). Bricks shall be calculated separately according to the market price, and leveling in the insulation wallboard shall be included in the unit price; 20#, 2 1# and civil air defense basement 1 18 yuan/m2 (excluding external wall insulation board pasting), including external wall tile pasting (if the tiles are not deducted according to the current market price), and leveling inside the insulation wallboard is included in the unit price; Including waterproof protective layer of basement exterior wall, calculated according to the construction area (the construction area is implemented according to GB/T50353-2005).

3.3 the project content included in the contract unit price

(1) All bricklayer's projects indicated in the construction drawing and other engineering materials: main structure concrete, other structure concrete, brick masonry engineering and all other engineering projects except steel formwork in foundation engineering (manual cooperation with mechanical excavation, including manual excavation of pit bottom, trimming of slope, manual excavation of parts that cannot be dug by machinery, manual excavation, transportation and filling of brick side formwork; Lime soil and gravel cushion; Brick side form; Backfill soil shall be manually cooperated, compacted and leveled. ); Decoration works: indoor and outdoor earthwork leveling, cushion, floor, marble veneer on stair surface, skirting veneer, sporadic open ditch on outdoor platform steps; Column beam must be plastered; Indoor and outdoor wall plastering, ceiling insulation board plastering, other plastering, external wall bottom plastering, door and window hole plastering, decorative components; Roof leveling, slope finding, thermal insulation and rigid protective layer; All indoor and outdoor decoration works except painting, waterproofing, doors and windows, railing wood production and other jobs. Including the construction and demolition of all temporary facilities.

(2) Material unloading, horizontal transportation and vertical transportation. Mortar and part of concrete are mixed on site.

(3) Cement warehouse and mixing table: installation and removal; Mixer: loading and unloading vehicles, installation, maintenance and disassembly; Derrick and so on. Coordination and maintenance of installation and disassembly of loading and unloading vehicles.

(4) Coordination of construction survey and setting-out.

(5) The site working face shall be clean, civilized, protected, inspected and accepted.

(6) The work content and all necessary auxiliary work of each construction project specified in the construction specification.

(7) Cooperation and coordination with other types of work.

(8) Completion cleaning; Coordination of acceptance and delivery stages; Warranty after completion and delivery, etc.

(9) Drainage of foundation pit in the whole construction process; During the whole construction process, the drainage of the indoor and surrounding sites of the building is under construction.

(10) Wall construction hole plugging; Remove the casing mortar from the hole of the through-wall screw to plug the hole (excluding the removal of the cork or rubber of the underground external wall water stop screw).

(1 1) Fabrication and installation of precast concrete blocks with water and electricity conduits and other precast concrete blocks.

(12) hardening of construction roads and sites, etc.

3.4 The contract price includes expenses.

(1) The contract price has included all the engineering contents in Clause 3.3, as well as all expenses such as management fees and profit policy adjustment factors. Within the scope of contracting, there will be no more work, work estimation, etc. , no longer sign a single labor cost within 3000 yuan within the scope of the contract, sporadic changes, shutdown and other expenses. Except as stipulated in Item (4) of this clause, the contract price shall not be adjusted. The contract price already includes the incentive fee of high quality and good price. The contract price includes the cost of tools, machines and protective equipment provided by Party B and the cost of tools at hand of workers. Including: mixer, vibrator, vibrator, three-stage electric box, wire, sun lamp lighting, trolley and its accessories, maintenance; Cutting machine, electric drill, electric hammer, cutting edge drill, maintenance; Safety helmet seat belt; Shovel, ash bucket, thread pendant, cotton thread, pencil, broom, spirit level, horizontal pipe, water pipe, gloves, etc. When it is higher than 0.00, other required pumps except the ground suppression pump, and other tools available to workers, etc.

(3) The contract price has included the salaries of the following personnel: operators, maintenance personnel and bell men of mortar mixers, concrete mixers and winches.

(4) During the construction process, for the design change projects with a single labor cost of more than 3,000 yuan, the projects entrusted by Party A to Party B that are beyond the contracted scope of Party B shall be settled according to the actual situation, and the pricing shall be negotiated by both parties on the spot or fixed according to the current budget. Both parties shall handle the on-site visa formalities in time, and Party B shall submit the visa form to Party A's budget officer for price review in the current month. If the visa is not processed in time and submitted to Party A's budget officer in the current month, or the visa matters do not conform to the provisions of this contract, the settlement will not be made.

3.5 Payment of project funds: during the construction, the living expenses shall be paid monthly according to the standard of 800 yuan/person; After the project is completed, Party B shall pay off the project payment (excluding the quality warranty payment and other deductions stipulated in the contract) at the end of the year (before the Spring Festival). 90% of the actual workload shall be paid in advance before the Spring Festival.

Article 4 Term of Contract

4. 1 The total duration and phased duration shall meet the requirements of Party A and the Owner.

4.2 If the phased construction period and total construction period are delayed due to Party B's reasons, Party A will punish Party B according to the monthly progress 1 1,000 yuan/day. The fine is deducted from the monthly living expenses.

Article 5 Quality grades

5. 1 Engineering quality grade: high-quality structure in Huai 'an.

5.2 Consciously accept the inspection of Party A's management personnel during the construction, and rework at any time according to the requirements of Party A's personnel.

5.3 If the project quality fails to reach the agreed level, the incentive fee for reaching the agreed quality level has been included in the contract unit price after deducting the construction area of 2 yuan /m2. All are subject to the certificate.

Article 6 Safe and civilized construction

6. 1 Ensure the civilized construction site of the city and strive for the civilized construction site of the province. Those who fail to reach the civilized construction site will be punished according to 5% of the total settlement price.

6.2 During the construction period, Party B shall ensure safe production and no accidents. Strict safety management, put an end to illegal command and illegal operation.

Article 7 Work and Responsibility of Party A

7. 1 Responsible for providing construction drawings, technical disclosure, quality disclosure, safe and civilized construction disclosure, site construction technology and quality management.

7.2 Be responsible for providing mechanical equipment, turnover materials and engineering materials needed for the project, and providing temporary facilities such as accommodation for Party B's construction personnel (6 people must live in each room, and all kinds of electrical appliances are not allowed in the accommodation area. Once the electrical appliances are found to be confiscated, a fine of 1 000 yuan will be imposed, which will be deducted from the living expenses of the team in that month).

7.3 Connect the construction water and electricity pipelines to the edge of the construction building number to meet the construction needs.

7.4 Conduct safety and civilized construction, legal system and public security fire prevention education for Party B's personnel entering the site, and do a good job in safety production management.

7.5 Assess Party B's quality, time limit, safe and civilized construction, and limited material acquisition during the construction process, and urge Party B to rectify the unqualified contents within a time limit.

7.6 In case of limited purchase, Party B has the responsibility to compensate Party B for the overcharged materials according to the market price.

7.7 Floor water is only provided with suppression pump and connecting pipe to the floor, and secondary electric box to the floor.

Article 8 Work and Responsibility of Party B

8. 1 Organize and adjust the labor force and management personnel according to Party A's requirements, obey Party A's management and coordinate with Party A well.

8.2 Ensure that the site construction personnel must be at least 18 to 45 years old, healthy, suitable for construction and production, and technically able to operate independently.

8.3 Ensure that all types of workers (including special types of workers) provided hold relevant certificates, and the number of employees can meet the requirements of construction progress, engineering quality and safe and civilized construction. Party B shall bear the cost of on-the-job training and certification for its own personnel of various types of work and special types of work. Party B shall bear the entry and exit expenses of its personnel.

8.4 Strengthen the education and management of legal system, public security, fire control, environmental sanitation, engineering quality and safe and civilized construction of our construction personnel. Ensure that our personnel abide by relevant national and local laws and regulations, strictly abide by the rules and regulations of Party A's unit, and obey management. For those who violate the regulations, Party B must accept the punishment unconditionally.

8.5 Ensure the normal construction during statutory holidays and busy farming periods. If the construction progress is affected, Party A will punish it.

8.6 If the main person in charge of our site leaves the site for more than 1 day, he must ask for leave from the project leader of Party A, and can leave and return on time only after approval. Before leaving the job, a temporary person in charge should be appointed to exercise his duties on his behalf to ensure the normal production.

8.7 Ensure that the construction is organized according to provincial civilized construction site standards. Self-production and self-cleaning, Nissan Nissin, cleaning up the site after construction and transporting construction waste to the place designated by Party A. ..

8.8 Actively cooperate closely with other types of work to ensure the smooth construction of the whole project, and shall not stop work without authorization, otherwise Party A will be severely punished.

8.9 Put an end to fire accidents and fighting accidents. After Party B enters the site, it is absolutely not allowed to gather people to make trouble for any reason, which will affect the construction production and Party A's reputation. If there is any contradiction, it should be settled through friendly negotiation with Party A in time. Otherwise, Party A has the right to punish Party B. ..

8. 10 strict safety measures must be taken in accordance with relevant regulations, and illegal command and operation are strictly prohibited. If a safety accident is caused by Party B's illegal command and operation, and other accidents happen to Party B's personnel, Party B shall handle it by itself and bear all the responsibilities by itself.

8. 1 1 It is forbidden for construction workers to urinate in the construction area. If Party A finds this phenomenon, it will be punished by defecation 100 yuan and urinating in 20 yuan. It is strictly forbidden to throw construction waste directly down from the sky, otherwise, once found, Party B will be deducted 1 0,000 yuan each time.

Article 9 Engineering Inspection and Quality Acceptance

9. 1 Party B shall carry out the construction in accordance with relevant national and local building construction codes and standards, as well as the requirements of construction drawings and documents and the instructions issued by Party A's representative according to the contract.

9.2 Party B shall accept the inspection and acceptance of the owner, supervisor, Party A's representative or designated personnel at any time and provide convenience for them. Party B shall modify and rework according to the instructions of the owner, supervisor, Party A's representative or designated personnel, bear all expenses caused by its own reasons, and compensate Party A for losses when necessary. After receiving the rectification instructions from the owner, supervisor and Party A, Party B shall rectify in time. If it is not implemented in time, Party A has the right to stop the parties from continuing to operate or impose penalties.

9.3 The economic expenses caused by Party A shall be borne by Party A. ..

9.4 Party B shall bear all kinds of fines and losses of Party A in terms of quality, safety, civilized construction, site appearance and team management caused by its own construction.

Article 10 Quota acquisition

10. 1 The acquisition of engineering materials and turnover materials is limited, and the project payment is deducted according to the market price for materials exceeding the limit. The system of picking and signing for all kinds of materials shall be implemented, and Party B shall designate a special person as a material clerk to be responsible for picking and managing materials.

10.2 Party A has the right to punish Party B's personnel for wasting materials.

10.3 Party B shall be responsible for the maintenance of the mixers, cranes and other machinery it operates.

Article 11 Quality warranty money

1 1。 1 The quality warranty payment is 5% of the settlement amount, and the quality warranty period is one year. After the project is completed and accepted, the report shall prevail, and the warranty money shall be returned to Party B after the warranty period expires.

1 1.2 Before and after the acceptance of the main structure, Party B shall be responsible for eliminating structural problems in time. After completion, during the warranty period, people should be sent to repair it immediately after receiving the warranty notice. If Party B fails to pick up the structural problem immediately after receiving the warranty notice and send someone to repair it, Party A will arrange another person to handle it, and the expenses will be borne by Party B. ..

Article 12

12.65438+ if party b fails to perform the contractual obligations seriously and violates the rules and regulations on project quality, project progress, safety and civilization, material and equipment management, logistics support, fire fighting, tertiary contract education and comprehensive management, party a has the right to impose a fine of 65,438+000-65,438+0,000 yuan/time on party b according to the seriousness of the case.

12.2 The probation period is two months after Party B enters the site for construction. During the probation period, if Party B is found to be unable to meet the requirements of this project in terms of project quality, project progress, safety and civilization, staffing and team management, etc. Party A has the right to terminate the contract and ask Party B to leave unconditionally at its own expense. Party A will settle the project with qualified completion quality and pay off the settlement money. Party B shall not make trouble when he leaves.

12.3 If Party B fails to fully perform the contract, stops the construction in the middle or quits by itself, Party A shall settle the account according to 70% of the qualified workload actually completed.

12.4 in case of safety and quality accidents caused by party b, party a has the right to terminate this contract and claim losses from party b. ..

12.5 When signing this contract, Party B shall submit a performance bond of 20,000 yuan to Party A as performance guarantee. If the person in charge of Party B is not resident at the construction site or Party B subcontracts the project, it will be regarded as a serious breach of contract by Party B, and Party A has the right to deduct the performance bond from Party B and will not return it.

12.6 the deposit will be refunded after the entity ends.

Article 13 Others

13. 1 The project has passed the completion acceptance and the warranty period expires. After the project payment is settled, this contract will automatically become invalid.

13.2 Matters not covered in this contract shall be supplemented separately.

Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _

Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Model essay on bricklayer's labor subcontracting II

Employer: (hereinafter referred to as Party A) Contractor: (hereinafter referred to as Party B)

1. Party A will contract the bricklayer and machine maintenance works of this project. The building of the general contractor of our company shall be completed by Party B.. Due to the change of the actual situation of the project, in order to ensure the smooth progress of the project, Party A and Party B signed this contract through consultation, and the terms of the contract are as follows.

Two. Project name: Project contract scope:

1) All tower cranes (warehouses, offices, etc. ) In this project, it is not maintained for the time being, and other labors are calculated according to the actual man-days.

2) All masonry, concrete pouring, vibrating, leveling, foundation excavation, foundation cleaning, foundation tamping, foundation moistureproof layer, flue installation, roof secondary crushed stone concrete, flue plastering, eaves gutter, heat preservation, all leveling layers, outdoor steps, drainage slope, ditch cover plate and other projects within the scope of this project.

3) The materials required by Party B in the construction process will be unloaded by itself, and Party A does not need to work separately.

Third, the construction area calculation

Implementation of the "Heilongjiang province construction project budget quota" construction area calculation rules. The foundation is calculated according to the external wall size, the main body is calculated according to the external wall size (excluding benzene board), and the balcony is calculated according to half the area. The construction area is calculated according to the actual situation of the project:

1), fire eaves do not calculate the construction area;

2) commercial service entrance steps (including cantilever slab) do not calculate the construction area;

3) The seven-story attic terrace does not calculate the construction area.

Four, the contract project price:

Through negotiation between Party A and Party B, the contract price of Liwa is calculated according to the floor, basement floor, equipment floor and attic floor (all above are subject to the construction area of each floor), and the contract price is 47 yuan per square meter. The above prices are all guaranteed at one time, and there is no difference. Party A has no obligation to bear the increased project contracting costs due to Party B's thoughtlessness.

Verb (abbreviation for verb) Settlement and payment methods:

According to the progress of the project image, advance labor costs: foundation (? 0.00) After the settlement is completed, the entity will settle it once (borrowing living expenses halfway) and settle it in three times. The first settlement shall be based on 70% of the actual amount of work completed by Party B, and the second settlement shall be paid to 25% after the completion of the main division, and 5% of the quality deposit shall be reserved after Party A's acceptance. The warranty period is one year, and once there is no quality problem, it will be paid in full.