On June 5438+February, 2006, Nanjing Transportation Planning Institute completed Xuzhou Urban Rail Network Planning (Interim Report), which was demonstrated by experts organized by the Municipal Planning Bureau.
On June 19, 2007, the Provincial Construction Department organized experts to demonstrate Xuzhou Urban Rail Network Planning.
In June, 2009, the Municipal Planning Bureau entrusted the Fourth Institute of China Railway to compile Xuzhou Urban Rapid Rail Transit Construction Plan (20 12-2020) and related topics.
20 1 0 65438+1On October 20th, the main construction of reserved passage project of Xuzhou rail transit1line was completed. 165438+ 10. In October, according to the new urban master plan, our city entrusted Nanjing Transportation Planning Institute to prepare the urban rail network plan of Xuzhou.
20 1 1 On March 26th, the municipal government approved the network planning approved by the Provincial Housing and Construction Department. 1June/July, the municipal development and reform commission reported to the provincial development and reform commission the "request for instructions on transferring Xuzhou urban rapid rail transit construction planning" (20 12-20 18). 165438+1On October 28th, the provincial development and reform commission reported to the National Development and Reform Commission the Request of Jiangsu Development and Reform Commission on Reporting Xuzhou Urban Rapid Rail Transit Construction Plan (20 12-20 18).
On March 8, 20 12, the Environmental Impact Assessment Department of the Ministry of Environmental Protection hosted a review meeting of the Environmental Impact Report on Urban Rail Transit Construction and Network Planning in Xuzhou, which was issued and passed on June 22. On April 15- 16, entrusted by the National Development and Reform Commission, China Consulting Company held an evaluation meeting of Xuzhou Urban Rapid Rail Transit Construction Plan (20 12-20 18) in this city, and issued an evaluation report on September 10. On July 30th, Xuzhou Urban Rail Transit Co., Ltd. was formally incorporated with an initial registered capital of 500 million yuan. Scope: rail transit project planning; Rail transit construction; Sales and leasing of rail transit equipment; Property management of rail transit stations; Development of advertising resources along rail transit. 65438+February 1 1 The Municipal Development and Reform Commission issued the Reply on the Proposal of Xuzhou Urban Rapid Rail Transit Line 1 Underground Municipal Engineering Project (Xu Fa Gai Administrative Licensing Service Examination Zi [20 12]No. 168).
20 1 310/6 "Feasibility Study Report on Underground Municipal Engineering of Xuzhou Urban Rapid Rail Transit1Line 1" was presided over by the Municipal Development and Reform Commission, and the meeting reviewed the feasibility report of underground municipal engineering. Chairman Li, General Manager and Deputy General Manager Zhang Changwei, Chief Engineer Han Ye and Assistant General Manager Yang attended the meeting. On October 25th, 65438/KLOC-0, the detailed survey report of Xuzhou Urban Rapid Rail Transit Line 1 Phase I underground municipal engineering passed the expert review.
20 13 On February 22nd, with the approval of the State Council, the planning of rail transit construction in this city was officially approved by the National Development and Reform Commission (No.2013), which indicated that the state agreed to implement rail transit projects in this city.
On August 20 13 1 3, the feasibility study report of the first phase of Xuzhou rail transit1line was approved by the provincial development and reform commission. The project line starts from Xingshanzi Station near Xiao Xu Highway in the west and ends at Xuzhou East Station of Beijing-Shanghai high-speed railway in the east, with a total length of 20.869 kilometers and 18 stations. The first phase line is 2 1.967km long, with 8 stations/kloc-0. 20 15 The first phase of 1 Line started in full swing, starting from Luwo Village Station in the west and ending in high-speed railway station, xuzhou east in the east.
2065438+June 2005, Xuzhou rail transit was listed as the first batch of national ppp pilot demonstration projects by the Ministry of Finance.
2065438+On July 24th, 2005, Xuzhou Rail Transit Company held a shield machine procurement conference in Chongqing. The contract amount of this project is about1600 million yuan, and the engineering quantity of shield machine is about 4756 meters.
On July 30th, 2065438+05, Shi Xiang, Deputy Secretary of Suzhou Municipal Committee and Mayor, said that the municipal government would actively connect with Xuzhou Municipal Government and plan the extension line from Xuzhou subway to Xiaoxian County.
On August 24th, 20 15, the two-way tunnel from Zhenxing Road Station to 1 Road Station in the first phase test section of Xuzhou Metro 1 Line was connected! The section is1265m long, including two one-way tunnels, passing through Cuipingshan Office and Jinlong Lake Dangkou Park respectively. .
In February 15, 15, 10, the shield machine purchased by Xuzhou will be fully underground, which will drive the construction of subway 1 line, subway line 2 and subway line 3. Let Xuzhou enter the subway era as soon as possible.
On the evening of February 2, 20 15 18: 50, the roof of No.3 warehouse of Zhenxing Road Station was successfully poured, marking the completion of the main structure of Zhenxing Road Station, the first stop of urban rail transit 1 line.
2065438+February 6, 2006, the first investment of the National ppp Fund was invested in Xuzhou City, Jiangsu Province, and it was clear that 400 million yuan was invested in the project in the form of equity, with a term of 10 year. The first phase of Xuzhou Rail Transit Line 2 has a total investment of 654.38+06.979 billion yuan and a total length of 23.9 kilometers. This project is listed as the first batch of PPP pilot projects in our province.
On February 6, 2065438, the environmental impact assessment of the first phase of Xuzhou Metro Line 3 was fully publicized. Line 3 is scheduled to start in June 20 16 and be completed in June 2020, with a construction period of 49 months.
2065438+On February 22nd, 2006, the whole line of Xuzhou Metro Line 2 was officially started, with the first phase of *** 12 station, which will be completed and put into operation in 2020.