Is Huaqiao University Xiamen Campus not fully built? When will all the equipment be ready?
The first phase of the project was completed several years ago, and the second phase is still in progress.

Generally, it is dormitory, library, teaching building, experimental building, canteen, etc. Everything is basically ready.

Phase II projects under construction:

1, Xidamen, Xidamen Square: Pre-acceptance has been organized and is being rectified.

2. Civil engineering experimental building and earthquake prevention and disaster reduction center: about 85% of concrete pouring of foundation pile caps and ground beams has been completed. 70% of foundation earthwork backfilling of earthquake prevention and disaster reduction center is completed.

3. Zijingyuan 1# and 2# buildings in the student dormitory: the construction unit has entered the site, and the construction operation cannot be carried out because the nail house blocked the construction and demolition at the construction site.

4. Experimental Building of Architectural Discipline: Enter the stage of construction bidding.

5. Music and Dance Academy Building: Design and construction drawing.

6. The second-phase student canteen: enter the construction bidding stage.

7. China Training Center Complex: The feasibility study is basically completed.

8. Swimming pool: construction drawing design stage.

9. Lianyuan Stadium 1#, 2# Building: Scheme design stage.

10, Dragon Boat Training Hall: Make scheme adjustment.

Logistics Support Base of Overseas Chinese Museum Student Activity Center 1 1: Conduct feasibility study.

The main problem that hinders the construction period is the problem of relocated households = =, you know.