Process of rural individuals applying for charging piles
Users who apply for the installation of rural personal charging piles shall submit the installation application to the local power supply department by telegraph with the registration form, identity certificate (ID card or organization code certificate), photos of the on-site environment of the parking space and parking space certification materials.

The power supply department shall, together with the applicant and the construction subject, go to the site to investigate the feasibility of electricity consumption and construction, and determine the construction scheme. The power supply department shall, within 7 working days, issue a reply to the electricity consumption plan and affix its seal on the registration form.

Precautions for installing charging piles are as follows:

1. The new electricity meter is used to measure the electricity consumption of charging facilities, and the electricity consumption is measured separately from the household electricity consumption. The two are independent. The household electricity consumption is charged according to the ladder electricity price, and the charging facilities electricity consumption is charged according to the fixed electricity price.

2. In the process of applying for the installation of household charging piles, communication with the property owner is very important, because the installation of charging piles involves line erection, circuit direction, meter installation, cost calculation and so on.

3. The installation and erection of household charging piles, what worries consumers most is the fire safety during use. Because most old communities do not have the location of charging piles, the corresponding supporting facilities are not perfect, and it is necessary to communicate with property owners.

4. In addition, the investigation of State Grid Power Supply Station is also very important. Unreasonable line erection will affect not only individuals, but the whole community.

To sum up, after the construction of the charging pile is completed, the charging pile company will go to the power company for filing, and the power company will go to the site for acceptance. After the acceptance, the power supply company will complete the work of installing meters and connecting electricity, and then it can be charged naturally.

Legal basis:

Article 29 of the Law of People's Republic of China (PRC) on Work Safety.

When adopting new technologies, new processes, new materials or new equipment, production and business units must understand and master their safety technical characteristics, take effective safety protection measures, and conduct special safety education and training for employees.

Article 36

The design, manufacture, installation, use, testing, maintenance, modification and scrapping of safety equipment shall conform to national standards or industry standards. Production and business units must carry out regular maintenance and inspection of safety equipment to ensure normal operation. Maintenance, maintenance and testing shall be recorded and signed by relevant personnel. Production and business units shall not shut down or destroy the monitoring, alarm, protection and life-saving equipment and facilities directly related to safety production, and shall not tamper with, conceal or destroy their relevant data and materials. Where production and business units in catering and other industries use fuel gas, they shall install combustible gas alarm devices and ensure their normal use.