1. Application Form for Construction Project Planning Permit of Lhasa Construction Project and written application of the construction unit (original);
2, planning compliance review opinions (except private decoration);
3, elevation expert review opinions (10000 square meters -50000 square meters);
4. Review opinions of the Latin Planning Commission (over 50,000 square meters);
5, the relevant documents of land use (including state-owned land use right transfer contract or decision, construction land planning permit, red line map and land use right certificate);
6, the development and reform department approval or approval documents;
7, the environmental impact assessment documents of the environmental protection department;
8. Risk assessment documents of the complaint reporting department;
9. The general plan or construction detailed planning completed by a design unit with planning and design qualification (along the main and secondary roads or important sections of the city, three different styles of elevation renderings are required). After the examination and approval of the general plan or the detailed construction plan, it shall also submit the construction drawing (blueprint) documents such as the general plan of the construction project, the plan, elevation and profile of the single building, the foundation plan, the plan, elevation and profile of the basement folded into A4 format;
10, qualification certification materials of construction engineering design preparation unit;
1 1, other special projects and other materials specified in the planning and design conditions;
12. If it is lost and reissued, provide newspaper materials;
13, other materials stipulated by laws, regulations and rules.
Extended data
Processing basis:
Article 40 of the Law of People's Republic of China (PRC) on Urban and Rural Planning, where buildings, structures, roads, pipelines and other projects are built in urban and town planning areas, the construction unit or individual shall apply to the competent department of urban and rural planning of the people's government of a city or county or the people's government of a province, autonomous region or municipality directly under the Central Government for a construction project planning permit.
To apply for a planning permit for a construction project, the relevant certification documents for land use, the design scheme of the construction project and other materials shall be submitted. A detailed construction plan shall also be submitted for a construction project that requires the construction unit to prepare a detailed construction plan. To meet the requirements of regulatory detailed planning and planning, the municipal and county people's governments determined by the people's governments of provinces, autonomous regions and municipalities directly under the Central Government or the competent department of urban and rural planning of the town people's government shall issue the construction project planning permit.
The competent department of urban and rural planning of the people's government of a city or county or the people's government of a town determined by the people's government of a province, autonomous region or municipality directly under the Central Government shall publish the general plan of the approved detailed planning and design scheme of the construction project according to law.
Article 41 For the construction of township enterprises, rural public facilities and public welfare undertakings in township and village planning areas, the construction unit or individual shall apply to the township and town people's government, which shall report to the competent department of urban and rural planning of the people's government of the city or county to issue a rural construction planning permit.