Time passed before we knew it, and we realized that the hard work was over. Looking back on our work during this period, we have gained a lot. Let's sit down and write a work summary! So how do you sum up your works and write new tricks? The following is a summary of my carefully organized engineering work (5 general remarks), which is for reference only and I hope it will help you.
Summary of engineering work 1 Time flies, and I came to the No.9 Hydropower Bureau Co., Ltd. for nearly two years, during which I served the sandstone system of Taishan Nuclear Power Station and Guanyinyan sandstone system successively. Mainly responsible for electrical technical work.
During my stay in the gravel system of Taishan Nuclear Power Station, I was engaged in site excavation and civil engineering, and was assigned to the engineering department to work in civil engineering with leading colleagues of the engineering department. During Jian 'an period, he entered the electrician class of Gold Team and began to arrange construction electricity with the electrician master. During the installation of electrical equipment in Jian 'an period, with only five electricians, we worked overtime and finally completed the electrical installation project within the specified time. Because of Taishan's experience, I gave technical guidance in Guanyinyan sandstone system and completed the installation independently. After the installation, I had the honor to participate in the debugging of electrical equipment and the compilation of electrical completion data. The operation and maintenance of the power distribution system in the workshop for nearly one year ensured the stable operation of our sand and gravel system power, provided a foundation for the project to continuously provide qualified sand and gravel aggregates, and was well received by the owners.
Combined with my two years' work experience, I have the following new understandings in my work.
First of all, we should strengthen our familiarity with drawing specifications and standards and study on construction methods.
Engineering drawings are the basic basis of engineering construction and the common language of engineering builders. It is an essential quality for engineering builders. Codes and standards are also the basis of engineering construction requirements, and also the basic requirements of the country or industry for engineering construction. Familiarity with drawings and specifications is the prerequisite for engineers and technicians to carry out their work. Secondly, I should be familiar with engineering construction technology. Through the long-term re-engineering construction in the front line and the observation of the construction unit, I have a deep understanding of the engineering construction technology, and gradually began to study and discuss the engineering construction technology. I think it is of great significance to strengthen the research and improvement of construction technology and adopt advanced and reasonable construction technology to maximize enterprise value.
Secondly, we should strengthen the management of engineering materials.
Any construction project is a process of processing engineering materials. It should be one of the main tasks of engineers and technicians to find out the flow direction of incoming materials. As engineers and technicians, we should first budget the materials and equipment according to the engineering drawings, and then purchase the engineering site by the purchasing department, and then install and manufacture according to the drawings and specifications. Make it a qualified project for customers. Carrying out relevant statistics and management work around engineering materials is of great significance for engineering quantity statistics, engineering tracking and material control, and also provides conditions for enterprises to control costs and create profits.
Three, should strengthen communication with the owner, supervision, general contracting and related aspects.
The project site cannot be smooth sailing, and many factors such as material shortage and complete design department are not conducive to the smooth progress of the project. It is of positive significance for the smooth progress of the project to coordinate all parties in time and strengthen exchanges. Colleagues are also of great significance for creating a harmonious working environment and building a harmonious society.
In short, the school has learned a lot, gained a lot and paid a lot in this year in the gravel branch of the No.9 Hydropower Bureau. In the future, I will continue to demand myself to be an excellent technician. I will continue to guard against arrogance and rashness, work hard, closely unite with others in the big family of the company, and create the greatest surplus value for the company.
Summary of engineering work 2 Since I joined the work, I have taken the tasks assigned by the leaders seriously and worked hard to do a good job. Under the care and guidance of leaders at all levels, I successfully completed the supervision work of the office building renovation project of the Port Authority, got a clearer understanding of the problems that are easy to occur in the renovation project and the points that should be paid attention to in the construction, got a deeper understanding of the acceptance criteria of the renovation project, and greatly improved my professional knowledge. In my daily work, the revision and checking of engineering drawings also make me operate AutoCAD, a drawing software, more smoothly, and at the same time have a preliminary understanding of the application procedures of land use planning.
During my work in an engineering company, my professional level has also been greatly improved. Not only participated in the budget preparation of the preliminary design scheme of Pier 5 and Pier 6, but also was mainly responsible for the preparation and filling of the engineering data of the port-facing highway project in Huanghua Port Comprehensive Port Area. During the budget preparation of the preliminary design scheme of Pier 5 and Pier 6, I learned to use the 20 1* coastal hydraulic budget system to carry out hydraulic budget, and got a deeper understanding of the budget process. The compilation process of engineering data of the port-facing highway project in Huanghua Port Comprehensive Port Area has also effectively promoted the improvement of my professional knowledge. This is a comprehensive process: it is necessary to personally go to the site to understand the actual construction situation, so that the information filled in is consistent with the actual situation, and it is inseparable from the guidance of professional and technical personnel of this project department. At the same time, we need to consult professional books in time, use our brains to sort out our work ideas and make our work orderly. Through such efforts, my work ability has been greatly improved and my work achievements have been recognized. This is largely due to the care and guidance of the leaders and the enthusiastic help of the company's professional and technical personnel. I would like to express my deep gratitude here!
In the future work, I will work harder, constantly enrich myself in my work, improve myself, speak with my performance, and repay the care and guidance of leaders at all levels with excellent work results!
Engineering Work Summary 3 Since I came to work in xxxxxxx Company in 20xx 10, I have been close to xx, and participated in xx project and xx project successively. Through the practical work training of these two projects, thanks to the care and training of leaders, as well as the enthusiastic help and inculcation of colleagues, my work has been rapidly improved. Although it is only less than xx, I have learned a lot of knowledge and gained a lot of rare experience through practice. Thank the company leaders for their trust in me and the support of my colleagues. Through the joint efforts of the team, I have explored some work experience. Here is a summary of my personal work during this period. Please give guidance and correction from leaders:
I. Main responsibilities
1, responsible for the improvement and utilization of xx technology.
2. Be responsible for the on-site installation supervision of xx project.
3. Be responsible for further research in the field of xx.
4, responsible for the promotion and application of xx technology.
Second, work experience
1, knowing how to do a good job is the premise of an excellent job, which requires us to have a solid professional foundation. Although my professional knowledge is somewhat different from xx's, through xx's tireless teaching and my colleagues' unreserved experience, I have also supplemented my professional knowledge with specific problems I have encountered, and my ability has been greatly improved. I will continue to work hard in the future to fully meet my work needs as soon as possible.
2. The success or failure of a project depends on teamwork. A project needs the close cooperation of many departments. Only by overcoming all the immediate difficulties and forming a joint force can the whole team have strong combat effectiveness and win one victory after another in the fierce market competition!
In the process of participating in two completed projects, due to lack of experience, many problems were encountered, but through the close cooperation of various departments and the help of colleagues, the projects were successfully completed. And learned valuable experience in dealing with engineering problems, so as to effectively prevent these problems in the next project progress and complete the project with good quality and quantity.
3. Be diligent at work, have a serious attitude, communicate actively, and avoid information lag.
No matter in technical research or engineering construction, it is necessary to coordinate and communicate with the corresponding departments. Only by maintaining timely information exchange with relevant departments can we complete the task better and more efficiently.
4, technology, management, both hands must be grasped, both hands must be embarrassed!
In order to finish the work better, we should first try to enrich our knowledge and improve our technical level, and then we can put forward reasonable suggestions in team work, make more confident and decisive decisions in project management, and share the worries for the leaders.
5. For the contract energy management mode, I personally think that the contract period should not be too long. There are too many uncontrollable factors, the replacement of leading bodies, the revision of laws and policies, the depreciation of RMB and so on. This may become an obstacle to the recovery of funds. If our share increases or even accounts for all in the initial stage and decreases year by year in the later stage, the cost recovery period can be shortened and the contract period can be shortened accordingly. Our investment risk can be greatly reduced, and Party A can acquire the ownership of the equipment in a short time. (If you don't understand maturity, please correct me.)
Third, shortcomings
1, professional knowledge is not solid enough, and many technical problems are slow to respond, so we need to strengthen our study.
2. Due to the lack of construction experience, some aspects of project management cannot be controlled in advance, and unexpected problems cannot be solved quickly and effectively.
3. The understanding of xx process is not thorough, so it is difficult to put forward high-quality suggestions in the research of new xx scheme.
Four. Future plans
1. Strengthen the study of professional knowledge, accumulate work experience, closely integrate theory with practice, thoroughly digest and absorb professional theories in practice, and lay a solid theoretical foundation for project management.
2. We have passed the national examination for mechanical and electrical construction engineer, and strive to obtain the first-class construction engineer next year.
3. Strengthen project management, and strengthen the ability of target control and management coordination.
Generally speaking, all the tasks assigned by the leaders have been successfully completed. In the work of xx, I have made continuous progress, my professional knowledge has been improved and deepened, and my work ability, including organizational cooperation ability, management ability and adaptability, has been greatly improved. More importantly, I have gained valuable work experience. Looking forward to the second half of 20xx, the projects being planned are xx, xx, xx, xx, xx and xx. There will be more new challenges in my work, and I will try my best to work more actively. In the future work, I will meet new challenges with a hundred times enthusiasm, make continuous progress and maturity in my study, and make contributions to the development of the company!
Summary of engineering work 4 I came to the company from 20xx, participated in the construction of four projects, and got a deep understanding on the whole. The company has always demanded higher product quality, and it has also been recognized by peers and the market. Through the project management in recent years, I have also learned a lot. Here's what I think.
First, the importance of project management
The real estate control policy will remain unchanged in 20xx, and the future real estate market will gradually shift from the era of profiteering to the era of meager profit. Due to the high profit in the early stage, many large-scale investment projects of real estate companies regardless of cost will be eliminated by the market. Developers should pay more attention to the refinement of cost control, standardization of management, quality, reputation and reputation, and find the balance point of cost, quality and effect on the premise of correct positioning.
In the whole project development process, project decision-making, project promotion and sales, fund raising and operation are all very important, and the important role of project management in project development can not be ignored:
1, compact and reasonable development cycle, shortening capital turnover time. For example, Vanke has developed a mature development process through research and summary to ensure that all projects are carried out in accordance with the company's established processes. On the whole, the construction period of Vanke project is very compact, which speeds up the capital turnover and reduces the management cost to a certain extent;
2. Reduce costs and improve quality through high-quality management; For example, in order to pursue product quality, Greentown spared no expense in material selection, and the corresponding project cost was higher. Under the premise of ensuring quality, whether we can seek lower cost to achieve the same effect is what we should focus on in project management;
3. Doing a good job in engineering quality can reduce rework losses, lower later maintenance costs and reduce customer complaints, which is of great help to the establishment of corporate reputation and brand;
4. Reasonable cost control can not only reduce the project capital investment, but also reduce the friction with the construction unit and avoid the lose-lose situation; As far as I know, there are several projects. After the construction unit found the loss (complicated reasons), it refused to do it. Because developers can't afford it, they subsidize the construction unit, and the final accounts are much higher than the bid price. How to control costs and double profits is the ultimate goal of cost control.
Second, the current difficulties in project management:
1, due to too many real estate projects, the number of migrant workers is seriously insufficient and the technical level is backward; Due to excessive demand and lack of training mechanism, the technical level and management level of project departments of many construction units are generally low;
2. In order to save costs, real estate companies use a lot of materials provided by Party A. Although the types of subcontractors of Party A pay 3% of the management cooperation fee and are included in the general contractor management, most general contractors not only do not manage, but insist that the subcontractors of Party A are the responsibility of Party A, and claims are extremely common. In this case, how to strengthen Party A's project management is particularly important.
Third, improve the project management level.
(1) Technical aspects:
1. Common quality defects: Up to now, we haven't seen any construction unit have a comprehensive pre-control plan for common quality defects, and many of them still rely on us to grasp the quality. However, the experience level of our managers is different from that of engineering, such as curtain wall construction. Some people have done it, some people have not touched it, but the company lacks uniform standards, and all managers basically grope for it themselves.
What we are talking about is pre-control, that is, we should consider the difficulties and key points of the work before the process construction, and have corresponding countermeasures: just like the problems that are easy to occur in curtain wall construction: the window top is flooded, which is inconsistent with the interior decoration size, the doors and windows, the glue joint is too wide, the deviation of aluminum plate blanking at the arc is large, the aluminum plate is not rigid enough, and it is easy to degum after cutting. Organize analysis and discussion before construction, determine the feasible implementation plan, and control the engineering quality to the maximum extent.
2. Schedule management: And according to the previous engineering experience, the construction period of each construction unit in the main stage will generally not differ too much, mainly in the decoration stage after capping, because in the decoration stage:
(1). There are many subcontractors: the processes of the general subcontractors are connected and influenced each other, and the problem of one unit may affect the whole project progress.
(2) Reasons of Party A: Some practices, materials, bidding, etc. of subcontractors due to ignorance of the project progress. It was not determined in time, which led to the delay of the construction period.
A good manager, like an old Chinese doctor, should not only have foresight, but also be able to see whether there is a problem at the scene in the early stage, what is the root of the problem and how to solve it, so as to avoid the rising cost of solving the problem after the "illness" worsens. Therefore, we should establish a model of the project progress, and deeply analyze the involvement time of each process, the order of each process and the relationship between the processes that cross and influence each other. Only by fully understanding the process of each stage of the project can we better guide the work, better serve the project, and ensure the smooth connection of various types of work and the smooth progress of the construction period.
3. Technical training: Because the skills and experience of managers are uneven, in order to pursue high-quality products, it is necessary to improve the technical level and management ability of managers.
Engineering technology is very professional, and enterprise training often lacks pertinence: first, many trainings are about design content, while design and construction are two different industries, lacking experienced lecturers; Second, a lot of training is the understanding of norms, which is relatively general and lacks pertinence to the problems that are easy to appear on the spot; Third, the training should conform to the actual progress of the site. For example, it is best to train the knowledge of piling or the technology of basement stage. If we say that the content of the later decoration stage has a big time gap, we can't deepen our impression and the training effect is poor. Vanke's management manual and construction technical instruction book are the most comprehensive among housing enterprises, but Vanke's engineering quality management can only be said to be average, which is not only related to the management ideas of the enterprise, but also because of the professionalism and complexity of engineering technology, the training has not prescribed the right medicine.
(2) management:
1. Positioning: We are responsible for a project of about 65,438+10,000 square meters with dozens of subcontractors. If we are only quality inspectors, it is impossible to run all the working faces, so how to locate the project management personnel of Party A is the key. A supervisor should be a manager while mastering technology. No matter how good the idea is, no matter how good the plan is, it is empty if it is not implemented.
2, methods: project management, methods are very important, because our management object is very special, and it is an external unit. First, the relationship between construction units is complex, and whether to obey management is one aspect; Secondly, many managers in the construction unit are smooth workers from the grassroots, and there are various ways to perfunctory you. To do a good job in project management, we should not only be skilled, but also learn to use the surrounding resources, so as to establish prestige and carry out the requirements.
The control of supervision is mentioned here, and some rewards for supervision are extracted from Vanke's contract, but most people think that Vanke's project quality management is not very good. Analyze the reasons:
1. Lack of guidance on supervision: the overall level of supervision is backward, and it cannot be expected that no matter how much money is spent, it can be completely managed. We should also strengthen process management: make clear what is required to be done at each stage and how to do it, so as to become our effective helper;
2. The main body of project implementation is the construction unit: we have 1 bid section, 1 civil engineering supervisor, two civil engineering supervisors and half a director. It is unrealistic to do this project well by just a few people. After all, the main body of project implementation is the construction unit, and the supervision of Party A can only play the role of supervision and spot check. The construction unit is the most manager. How to straighten out the relationship and give full play to the role of supervisors and managers of construction units?
3. Deep management: participate in the internal management of the cooperative unit.
As mentioned above, many general contracting units and supervision units are backward in internal management, and managers lack enthusiasm, but the project ultimately depends on the construction unit. It is difficult for a team with low overall level to do a good job in the project, which will eventually affect our quality objectives and schedule objectives. If you want to do a good job in the project, you should consider helping the general contractor and supervision to coordinate their internal relations and give full play to the role of each post.
For personnel management, I think it is important to know people and use good people, and it is not recommended to adjust personnel frequently. Because many times you can't choose the person you are in charge of, and even if you can change it and change it many times, it may not meet your expectations. Personnel adjustment will bring many new problems.
The knowledge of management is to consider how to make use of existing personnel and maximize work efficiency. I think we must first have a comprehensive and correct understanding of everyone, that is, "knowing people": everyone has advantages and disadvantages, it is easy to find a person's shortcomings, but it is unwise to deny a person easily.
It is "making good use of" to tap a person's advantages and make use of them, control his shortcomings and avoid harm. This is said from two aspects:
(1), reasonable division of labor: none of the Leshan Bid Section I am in charge of is a person with strong comprehensive skills in technology, management and external coordination. Everyone has obvious advantages and disadvantages, but a reasonable division of labor can give full play to everyone's specialties, so the work efficiency is high; If you put someone in an inappropriate position, it will not only have no effect, but will affect your work.
(2) How to mobilize enthusiasm: Everyone has different sources of motivation, either because of pressure, or because of interest incentives, or because of their own initiative. Many construction units and supervision units have low internal management level, no assessment, no incentive, and doing well is the same as doing badly; The following managers are sloppy and inefficient, so even if our supervisor of Party A runs hard, it is still very difficult to do the project well.
4. Management training: Generally, the training courses of large companies are aimed at the internal management of enterprises, just like the training I attended was about Haier's management model: managers face a group of high-quality people in the company, or managers have the power to kill employees, and the management objects and management models are completely different from our engineering site. The object of our management is foreign units, many of whom are smooth hands with low quality and grassroots background. How to do a good job in project management requires targeted training.
Fourth, establish the enterprise's own engineering standards.
Take civilized construction as an example: I passed by the Xidebao construction site in Greentown some time ago and didn't visit it. However, the scaffolding on the outer wall is really much better than ours, and the closure at the bottom of the scaffolding looks neat. We still have all kinds of things here, and the construction units have their own magical powers.
The first impression of a customer's visit or inspection by a government department is the civilized construction on site. The civilized construction of a project is not only a matter for the construction unit, but also often represents the image and management level of the developer. Therefore, I think we should have our own standards for these aspects that can show the corporate image.
Verb (abbreviation of verb) conclusion
The new year is coming, the government's policy of restricting the purchase of real estate shows no signs of relaxation, and the demand for housing products in the whole market is hot and cold, so it will be difficult to reproduce the era of profiteering in the real estate industry. In this situation, we consider doing a good job in brand maintenance, strengthening our own construction, improving our viability and enhancing our competitiveness. Under the wise decision of the company leaders, we will definitely step out of our own sky.
Summary of engineering work 5. I have been working in 20xx for more than a year. I always abide by the rules and regulations of my enterprise and project department, actively obey the work arrangement of the leaders, successfully complete all tasks, safeguard the collective honor, actively demand progress in thought, actively respond to the call of the enterprise, work conscientiously, work hard, seriously study relevant professional knowledge and skills, and constantly enrich and improve myself.
Looking back on the past 1 year, every day is busy and full. Only after work did I know that all the school textbooks were theoretical knowledge. The practical experience accumulated bit by bit in my present job is an inexhaustible wealth in my life. During the 1 year of work, I had both difficulties and gains. The result of serious work not only fulfilled my personal responsibility, but also strengthened myself.
I summarized the work in the past 1 year as follows:
First, ideologically
I have a strong sense of ownership, always pay attention to the development of the enterprise, firmly believe that the enterprise will continue to grow and develop, and be full of enthusiasm and expectation for the future of the enterprise; I won't relax because of this. I will be more strict with myself, consciously accept the supervision and help of my colleagues, and persistently overcome my shortcomings and make up for my shortcomings. I will start from doing my own job and daily work, starting from me, starting from now, starting from the little things around me, doing my best in my work, making unremitting efforts and making achievements. I will constantly improve my job skills, strive to master all kinds of professional knowledge, and do my job in a down-to-earth manner.
Second, in the work attitude.
No matter at work or in life, I always believe that no pains, no gains, so I have been working hard, studying hard and working hard; Treat every job correctly and seriously, work hard and attend on time; Sometimes there are too many jobs, too few people and heavy tasks. We can carry out every work in an orderly way, plan ahead and finish it successfully on time, and then constantly summarize the methods to streamline the workflow. These methods also played a great role in the future work; In 20xx, I was stationed in XXX project department. The whole project has a long front, arduous measurement task and hot weather, but I am not afraid of hardship and fatigue. I study professional knowledge seriously, combine theory with practice seriously, and carefully control monitoring and measurement for the project department. Carry forward the spirit of continuous work and hard struggle of our construction personnel.
Third, in terms of job responsibilities.
Strictly implement the company's relevant standards and national specifications, and carry out construction survey in strict accordance with the design specifications during the work. If you have any questions, find the top management of the project department and communicate with them. Because of this, I learned more professional knowledge at the construction site. It ensures that XXX has zero error in daily construction measurement, and has been affirmed by the third-party monitoring center of subway company in monitoring measurement. My achievements are inseparable from the encouragement of my leaders and the strong support of my colleagues. I hope to continue to complete the tasks assigned by the leaders with a rigorous working attitude in the next year's work. Pass the good measure to yourself, to the leader, to the company, and hand in a satisfactory answer sheet.
What the company gives us is to constantly improve and summarize ourselves, improve and enrich ourselves from different angles and platforms, raise awareness and enrich our lives. The company has given us a lot, and in return, we will contribute to the company's development and future.
;