Who generally completes the summary and compilation of the completion acceptance report? The construction unit or the construction unit?
Construction unit. The summary and compilation of the completion acceptance report should be written by the construction unit first, and then submitted to the construction unit. The final summary report is generally issued by the construction unit. The completion acceptance report refers to the written report formed after the completion of the project, which is organized by the special acceptance agency set up by the relevant departments for quality evaluation and acceptance. ?

Construction unit: enterprises and institutions that are composed of relevant professionals and have corresponding qualifications to carry out production activities.

Construction unit: the investor of the construction project, who owns the property right.

Extended data:

Contents of the completion acceptance report

1, building foundation

Briefly explain the approval or scheme of the project feasibility study report, the approval unit and approval number, the approved construction investment and project budget (including revised budget), the specified construction scale and production capacity, and the main contents of the construction project contract.

2. Project overview

(1) Preliminary work and implementation of the project;

(2) design, construction, general contracting, construction supervision, equipment suppliers, quality supervision institutions and other units;

(three) the commencement date and completion date of each single project;

(4) Workload completed and production capacity formed (explain in detail the reasons why the construction period is advanced or postponed, the reasons why the production capacity is inconsistent with the original plan, and the countermeasures taken to ensure the implementation of the original plan during construction).

3. Initial inspection and trial operation

Main conclusions of initial inspection time, initial inspection and trial operation (the initial inspection report and main test indicators of trial operation should be attached, and the trial operation time is generally 3-6 months).

4. Overview of final accounts

Budget estimate (revised budget estimate), budget implementation and preliminary final accounts, and investment analysis of communication construction projects.

5. Arrangement of engineering and technical files

Records of major events in engineering construction, completion data of individual projects, acceptance data of concealed projects, design documents and drawings, supervision documents, technical data of main equipment and correspondence documents in engineering construction, etc.