The project is located at No.54, Zhongshan Second Road, Songjiang District. This project is invested and constructed by Shanghai * * Real Estate Development Co., Ltd., designed by Shanghai * * Architectural Design Office and supervised by Shanghai Urban Construction Supervision Consulting Co., Ltd., and consists of 18-storey serviced apartment, 12-storey residential building (Building 4), 6-storey residential building (Building 0/5) and central green underground garage, with a total construction area of 525,000. Among them, the underground garage is a frame shear wall structure system. The shear wall thickness is the hotel apartment 18 floor, the standard height is 3.2m, the total height is 7 1.5m 4 # floor 12 floor, the height is 39.5m: 15# floor, and the height is 23.5m Pile foundation and raft are used in this project, and the piles are precast piles. The construction technology of mixing pile and soil nailing wall is adopted for foundation pit support. The exterior wall doors and windows of this project adopt plastic-sprayed aluminum alloy doors and windows, the residential doors are solid wood security doors, and the rest are hardwood plywood doors. The exterior wall is high-grade exterior paint, the exterior wall of the podium is dry-hung with granite slabs, and the roof is made of PVC waterproofing membrane.
2. Determine the safety management objectives of this project.
When formulating safety management objectives, the project department of this project must adhere to the policy of "safety first, prevention first" of the party and the state, and combine the safety policy of "people-oriented, focusing on the site, strengthening standards and civilized construction" of this enterprise, establish a safety production responsibility system and prevention system, strengthen safety production management, implement the safety production responsibility system, take effective preventive measures, prevent casualties and other safety accidents, and make safety production more standardized, scientific and standardized. Major casualty accidents are zero; Put an end to fire, traffic, pipelines, equipment, poisoning and other accidents; Owners, social stakeholders and employees have no major complaints; The safety inspection on the construction site has reached the standard above JGJ59-99; The safety guarantee system has passed the audit and certification of DGJ08-903-2003; Dust, sewage and noise meet the requirements of urban management; Ensure the standardized civilized construction site in Songjiang District; Ensure the standardized management of standard construction sites in Shanghai; Strive for a civilized construction site in Shanghai.
3. Prepare the basis of the safety plan
(1) The preparation of the safety assurance plan of this project is mainly based on the inspection standards of Shanghai standards DGJ08-903-2003 and JGJ59-99, and the supporting documents of relevant laws and regulations, localities and industries, and the safety production assurance system standards of the construction site are planned.
(2) The documents, standards and specifications cited during the project construction can be divided into three categories:
1. National industry and local management documents, including People's Republic of China (PRC) Construction Law, People's Republic of China (PRC) Safety Production Law, Fire Protection Law, Shanghai Fire Protection Regulations, the State Council Safety Technical Regulations for Construction and Installation Engineering, Regulations on Construction Safety Supervision and Management, Regulations on Construction Site Management, etc. Provisions on the Supervision and Management of the Use of Safety Protective Equipment and Mechanical Equipment on the Construction Site, Interim Provisions on the Safety Management of Civilized Construction of Construction Projects in Shanghai, Regulations on the Supervision of Labor Protection in Shanghai, Regulations on the Management of Construction Market in Shanghai, etc. And other local documents, refer to the relevant documents and notices issued by the safety supervision station of Shanghai Construction Committee over the years.
Two. The second part is safety technical standards. The document specifications include: special operators, safety technical assessment management rules, hand-held power tools, construction winches and safety nets; Construction machinery: temporary electricity consumption, safety inspection and grading standards, etc.
Three. The company's internal management documents include: mechanical equipment management regulations, safety reward and punishment measures, various safety management systems, safety production responsibility systems at all levels, and ISO9002 compliance sequence documents of China enterprises, etc.
4. According to the elements of 16 in the safety system, it is implemented in various functional departments or individuals.
(1) The project consists of project manager, deputy project manager and project engineer; The functional department's installers, technicians, safety officers, material engineers, machine controllers and general managers, according to the actual situation of the project construction.
(2) Each post function person has a clear post responsibility system, which must be seriously implemented in the actual construction process, with a clear scope of responsibility and all responsibilities to be signed. In actual operation, functional personnel can be added according to the situation, which is decided by the project department.
5. Analysis of the key safety protection parts of this project has the following aspects:
(1) The main building of this project is complex and difficult to construct.
(2) Due to the urgent construction schedule, there are many nighttime constructions in the schedule.
(3) The structure of this project is complex and the appearance is diverse, so it is difficult to set up scaffolding.
(4) Identify the dangerous points and hazards in the construction site in advance, and formulate targeted preventive measures, such as the danger of tower cranes in the erection area, temporary electricity consumption in the erection area and the construction site, protection of adjacent holes, elevator shaft, channel protection and other key parts control means.
6. The construction site mechanical equipment resources configuration are:
This project is set as the home page to join the real estate collection E-net project department safety planning-| website home page | information | regulations | architecture college | real estate college | real estate information | property management information |-article title, author, keywords of each column, building management, building construction, building safety construction papers, building certification, building training, building examination, registered architect, cost engineer and supervision engineer. & gt School of Architecture >> Building Safety > > Update of Safety Planning of Text Project Department: 20 13/6/26 Reading: Column 5: Summary of Safety Planning of Construction Safety Project Department: This project department must adhere to the policy of "safety first, prevention first" of the party and the state, and combine with the enterprise's "people-oriented, site-based and strengthening standards".
There are two 63T M tower cranes, two SCD200/200 passenger elevators, 1 derrick, two cutting machines, two mortar machines, five mud pumps, 12 vibrator, 1 circular saw, 1 planer and two bending machines put into use from the real estate e-net. Mainly for small and medium-sized mechanical operation training. The installation must meet the requirements and be listed after acceptance before it can be put into use.
7. Scaffolding
In this project, the podium of serviced apartment (18 floor, 7 1.5m high) is equipped with floor-standing scaffolding, and scaffolding is installed on the standard floor above the podium (see scaffolding construction organization design for details); 4# building (12 floor, 39.5m high) sets up double-row fastener scaffolding (see scaffolding construction organization design for details); Landing scaffolding is set up in 15# building (6 floors, 23.5m high) (see scaffolding construction organization design for details).
8. The preparation of special construction organization design are:
(1) temporary electricity construction organization design;
(2) organization design of foundation pit support construction;
(3) Scaffolding construction organization design;
(4) Receiving platform (cantilever steel platform, floor type);
(5) template engineering construction organization design;
(6) Construction organization design of large-scale machinery (disassembly) (including tower crane, passenger elevator and derrick);
(7) hoisting construction organization design;
(8) Construction organization design for preventing falling from high places;
(9) Road pipeline protection scheme.
The single construction organization design (scheme) shall be compiled by the technical personnel of the project department, and can only be implemented after being reviewed by the safety technology department of the Ministry and reported to the head office for approval.
9. Procurement and lease of project safety materials
The quality of materials, equipment and protective equipment required for safety facilities on the construction site directly affects the personal safety of construction workers and involves the quality of building products. It is an effective preventive measure for the project department to control the procurement.
(1) The material engineer shall, according to the actual needs of the project, prepare the procurement plan for materials such as equipment, facilities, safety protection and safety supplies used in the construction site, and the project manager shall examine and approve the specified requirements of the purchased materials before issuing or signing the contract to ensure the correctness and effectiveness of the information. The project buyer shall timely purchase materials according to the needs, and the safety supplies must be qualified and the procedures are complete. Strengthen on-site inspection to prevent inferior and forged products from entering the site and strictly control them.
(2) The implementation of procurement funds shall be carried out by the project department from 0. 1% of the total project cost in accordance with regulations, and shall be reported to the higher authorities for approval.
(3) Material suppliers (including leased materials) must be selected from the list of qualified suppliers issued by China enterprises in 2004.
10. Identification, evaluation and control of dangerous and unfavorable environmental factors
Identify the hazards and important environmental factors existing in the construction process, and formulate targets and management plans accordingly to effectively control accidents and pollution.
(1) The project manager shall organize all management personnel of the project department (including relevant personnel of subcontractors and experienced workers) to identify hazards and environmental factors in various fields.
(2) The safety officer is responsible for summarizing the hazards, controlling and locating the key parts, and arranging the important environmental factors.