"2" Water and Mud Technology
Science and leasing
1 overview
Case analysis of a transformer differential protection misoperation
Nicolas
(Hefei Cement Research and Design Institute 23005 1)
Chile Lafarge grinding 200,000 tons cement production line is the first in our hospital.
The relationship between success and failure of an EP project in the United States.
Whether our hospital can explore the American market is the implementation of our hospital's American development war.
Slightly critical. This project is from the initial design to the selection of equipment.
The most advanced technology in China. To this end, the work of our hospital
Cheng's technicians are working hard, but the electrical aspects of the site
There are still some technical problems. Our engineers and technicians are very
Pay attention to the problems, without any slack, and the technicians in Chile.
With the strong cooperation and efforts of our engineers and technicians, we require electricity.
The problem was finally solved satisfactorily and was well received by the owners.
Here, I only take the Transformers micro that appeared in Lafarge, Chile.
The misoperation of mechanical differential protection is listed and the technical analysis is made.
For your reference.
2 electrical fault phenomenon
The power supply for the 200,000-ton cement grinding production line in Lafarge, Chile is
Adopt 23/6.6 kV-23/0.4 kV bidirectional power supply mode, two main
See table 1 and table 2 for the technical parameters of the transformer.
Table 1 1# main transformer
Transformer model s11-Ⅳ b-3150/23.
On-load voltage regulation 23 2x2.5
Transformer connection mode Dynl 1
The transformer capacity is 3 150t.
The voltage ratio is 23/6.6 kV.
Table 2 2# Main Transformer
Transformer model Sl 1 MB 2000/23
On-load voltage regulation 23 2x2.5
Transformer connection mode Dynl 1
Transformer capacity is 2000 kilometers.
The voltage ratio is 23/0.4kv.
The main protection of main transformer is microcomputer differential protection (model:
R circle 1543), R 43 microcomputer comprehensive insurance is near ABB company.
A new type of comprehensive insurance is new to the world and has a very powerful function.
The self-programming of running software and programs provides convenience for users.
After half a year of installation, it was put into trial operation on June 20, 2008.
The two main transformers are running normally under no-load condition. But when two main transformers are in the band
After load production, the high voltage sides of two main transformers tripped one after another.
Like, ABB microcomputer comprehensive protection shows microcomputer differential protection action, obviously this
Samples will seriously affect the production of the whole factory, and this problem must be solved as soon as possible.
Solve.
3 Fault inspection steps and technical analysis
(1) First, check whether the phase sequences of the high and low voltage sides of the current transformer are the same.
Therefore, if the phase sequence of power supply is positive sequence, as long as the selection is reasonable.
The differential current flow through that variable ratio and the microcomputer phase compensation is very small, but
The situation of negative sequence is different, and the secondary side of current transformer on high voltage side loses power.
The output current is in phase with the secondary output current of the low-voltage side current transformer.
The bit difference is 60. , so it will cause differential protection misoperation, but
Carefully check whether the phase sequence of the power supply is correct on site.
(2) Comprehensively check the transformation ratio at both ends of the current transformer.
Ensure that the protection values match, recheck and calculate the protection settings.
A 35—
2008.N93
Cement slurry technology
Science and logic OFC
Value, did not find any problems.
(3) Check whether the secondary side of the current transformer is damaged, because
When the transformer has a certain load, if the secondary circuit of the current transformer is disconnected
Line, is likely to cause differential protection starting element, differential element action,
Thus lead to misoperation of differential protection. The inspection result was not found.
Describe the problem.
(4) Then, all technicians began to suspect that the transformer was inside.
Whether there is a fault or not, it has been tested by two main transformers and the factory.
Value verification, the detected data is almost the same as that of the transformer when it leaves the factory.
(5) According to ABB's technical data of microcomputer integrated protection (RKI'543),
Check ABB (RY43) microcomputer integrated protection terminal (transformer)
Whether the current terminals of current transformers on both sides are connected to comprehensive protection.
Correct), found that the transformer on both sides of the current transformer and comprehensive protection wiring are
The manufacturer mistakenly placed the current transformer on the high voltage side and the low voltage side of the transformer.
The current signal of the current transformer is reversely connected to the position of comprehensive protection, and
After the wiring adjustment is correct, the differential protection tripping phenomenon is still found.
Existence.
At this point, the problem at the scene seems confusing, but both China and Chile
Engineers and technicians are not discouraged. They looked at the drawings and looked up the information, and finally found it.
The chronic disease of the problem It turned out to be the same polarity terminal on the secondary side of the transformer.
Wrong wiring will lead to differential protection misoperation, because this wiring mode will
Lead out the secondary current direction of current transformers on both sides in the differential circuit.
Similarly, the current flowing through the microcomputer comprehensive protection is the sum of two-phase currents, which is a changing voltage.
Faults during no-load operation are generally not easy to reflect, only when
When the transformer has a certain load, the differential protection will act. Reconnect
The two transformers behind the line are running normally with load.
Figure 1
In this way, with the efforts of technicians from both sides, this situation will change together.
A 36 one
The misoperation of differential protection of voltage transformer finally came to the bottom, and the fault was rounded.
Full solution, but in the hearts of engineers and technicians for a long time lingering.
The distant fog gradually melted away and became the joy of the smooth completion of the project.
It is raining. Figure 1 shows the correct and wrong wiring of differential protection.
4 experience and suggestions
4. 1 Fault analysis and elimination
Through the analysis and elimination of differential protection misoperation fault
The whole process, elaborated some normal operation (system trouble-free and no
Influence) differential protection misoperation, but in addition to the above reasons.
There are also some factors that may lead to time difference dynamic protection of transformers in normal operation.
The main phenomena of misoperation protection in the secondary circuit of current transformer are: (1).
The terminal screw is loose, resulting in poor connection or short circuit of the secondary circuit.
Open the way. (2) The primary phase contact in the secondary circuit of the current transformer is poor,
The arc generated at the poor contact causes single-phase grounding or grounding between two phases.
Grounding (short circuit in secondary circuit of current transformer). (3) Current transformer
The outer insulation of the cable core of the secondary loop is damaged or damaged, and it is running.
Vibration causes short circuit to ground. (4) Secondary differential current transformer
The loop is grounded at multiple points, and the grounding point is not in one place, resulting in a grounding point.
The potential difference between them is too large, which leads to differential current and differential error.
Action (thunderstorm season).
4.2 Suggestions
In order to improve the reliability of differential protection, the following work should be done.
Operation: (1) Strictly check the polarity of current transformer; Intermediate frequency current mutual inductance
If the polarity of the device is wrong when wiring, it is used in the protection circuit.
This will cause misoperation of protection. If it is use in that measuring circuit of an instrument,
Will affect the accuracy of measurement. (2) Be careful of the secondary circuit of the current transformer.
Poor road contact and open circuit; Strengthening differential current transmission of differential circuit
Maintenance of line monitoring and protection devices. In transformers and protective equipment
After installation and debugging, carefully check the secondary circuit of current transformer.
Road, tighten the secondary circuit terminal screw and use the spring pad.
Reinforcement. (3) Strictly implement the specification requirements; All electrical connections
The secondary circuit of differential current transformer can only have one male * * * grounding point.
The location of the grounding point should be on the protection disk. (4) ensure differential electricity
The secondary cable cores of the current transformer are insulated from each other, and the cores are insulated from the ground; correct
It is necessary for the initial operation of the transformer and the operation of the high-voltage equipment after maintenance.
Measure the secondary cable core of current transformer with 1000V insulation resistance meter.
Insulation between conductor and ground to meet the requirements of electrical regulations; in addition
The cross section of the secondary cable of the externally selected current transformer shall be no less than 4 mm.