How to write the contents of engineering visa well
Question 1: How to write the content of the visa project quantity? 10. You asked the budget staff how to write the contents of the project visa form. Answer: 1, topic: project visa form; 2. Project name: XX project; 3. Visa content: The foundation was originally designed to be dug below the natural ground1.2m.. During the construction, it was found that there was a silt layer between the original 5-7 shafts. After research with the design department, this part is deepened by 0.3m, and the others remain unchanged. Construction unit: Party A represents XX Company: XX Supervisor: XX 20 1 1 year 1 February1day.

Question 2: How to write the contents of the project visa for budget personnel? How to write the contents of the project visa for budget personnel?

Answer: 1, visa form for prestigious schools;

2. Project name: XX project;

3. Visa content: The foundation was originally designed to be dug below the natural ground1.2m.. During the construction, it was found that there was a silt layer between the original 5-7 shafts. After research with the design department, this part is deepened by 0.3m, and the others remain unchanged.

Construction unit: XX company, Party A's representative: XX supervision: XX.

20 1 1 12 1.

Question 3: What is the general template format of the project visa form? First, the common format template:

Second, the project visa form introduction:

The concept of engineering visa is explained and defined as "according to the contract, the signature certificate of representatives of both parties in the construction process involving events other than the contract price" in the Operation Guide of Engineering Cost Consulting issued by China Construction Engineering Cost Management Association in 2002. The relationship between the form of engineering visa and the contract price of construction contract and its function. In the model text of the construction project contract, the contract price refers to "the sum agreed by the employer and the contractor in the agreement, which is used by the employer to pay the contractor to complete all the projects within the scope of the contract and assume the warranty responsibility according to the contract". The contract price is the "agreement" between the employer and the contractor in the agreement, which is used to "pay" the money for completing the contracted project and undertaking the warranty responsibility. Engineering visa is a certificate signed by the employer and the contractor's entrusted agent on the liability events beyond the contract price according to the contract agreement, which involves the money beyond the contract price and is the concrete implementation and embodiment of the authorized behavior of the legal representative.

Question 4: The concept of how to write a project visa for a construction visa in construction is explained and defined as: "According to the contract, the responsible events involved in the construction process other than the contract price are generally signed and confirmed by the representatives of both contracting parties" in the Operation Guide for Engineering Cost Consulting issued by China Construction Engineering Cost Management Association in 2002.

The relationship between engineering visa and construction contract price and its function. In the model text of the construction project contract, the contract price refers to "the sum agreed by the employer and the contractor in the agreement, which is used by the employer to pay the contractor to complete all the projects within the scope of the contract and assume the warranty responsibility according to the contract". The contract price is the "agreement" between the employer and the contractor in the agreement, which is used to "pay" the money for completing the contracted project and undertaking the warranty responsibility. Engineering visa is a certificate signed by the employer and the contractor's entrusted agent on the liability events beyond the contract price according to the contract agreement, which involves the money beyond the contract price and is the concrete implementation and embodiment of the authorized behavior of the legal representative. The above two items, one is the behavior of a legal person and the other is the behavior of an agent entrusted by the legal representative. The former is clearly the contract price, and the latter involves money other than the contract price (that is, the adjustment item of the contract price), which is different. The principal-agent behavior here is to clarify the entrusted matters and authority through the contract. His behavior cannot cover the contract between legal persons, and his behavior is bound by the contract.

Due to these characteristics of engineering visa behavior, by signing and authenticating on the principal-agent platform, money-related events within various behavior limits in the construction process can be effectively solved, which promotes the efficient coordination and rapid settlement of various controversial construction behaviors.

Question 5: How to write the construction site visa template?

(V- 1) Division Project Name Right Bank Wharf, Concrete Surface of No.3 Dam Square and Granite Plate Installation

Drawing number, signature certificate number

Content:

1 year On May 22nd, 2000, the original design of granite paving on the right bank pier and abutment steps was 3cm thick mortar, but the actual paving thickness exceeded the design. See calculation of extra plain concrete.

2. On May 22nd, the granite on the front eaves of the wharf on the right bank was not originally designed, and then granite plates were added as instructed by the supervisor and the owner. Because the pier front eaves are 9cm lower than the original design, reinforced concrete is needed.

Calculation of engineering quantity:

1. Quantity of plain concrete: 31* 4 * 0.035 = 4.34m3.

2. Quantity of reinforced concrete:15 * 0.27 * 0.09 = 0.37m3.

Number of granite slabs: (0.1+0.37+0.25+0.45) *16 =18.72m2.

3. Quantity of reinforced concrete: 4.7 * 4.5 *10 * 0.08 =16.92m3.

Signature of representatives of the construction unit, supervision unit, owner unit and on-site representative:

Question 6: How to write the engineering quantity visa form? For the engineering construction beyond the drawings, you must apply for a quantity visa. How to fill in the visa form:

1, visa reasons and basis

Step 2: Location

3. The engineering quantity (it is best to sign the engineering quantity according to the requirements of the quota subtitle, so that the quota can be applied when settlement is convenient. If rework does not involve the corresponding quota subtitle, you can directly sign the fee or apply a similar quota).

Question 7: How to write a visa quantity statement? Visa form:

Reason: It is the instruction of Party A or the instruction of the supervisor.

Result: Content pays for this.

Application: Express your intention to apply for a visa:

The following list:

Visa form

Signature) number xx

To xxx supervision unit:

(reason) x year x month x day. Received written instructions from the supervision engineer. Requirements. . . . After receiving the instructions. We'll do it right away . . .

(Implementation) This instruction was completed on * * * on * X * of X year. . . . It's consumed . . . Total cost. . .

Please grant an audit visa.

This gift

Question 8: How to write a visa for engineering quantity? Understand these, you will have the direction, the basic project cost problem, but what you can't see is the design change, so you must have the documents approved by the supervisor and Party A and Party B.

The form has a fixed pattern and it will be easy to read. In fact, it is cautious and the nature of responsibility is well divided.

Question 9: How to write the project visa, mainly in the form of sending it to you by email address.

Question 10: How to write the on-site visa form, and how to make it?

For the work beyond the construction contract or related to the construction scope of the construction drawing, the document (or drawings) proposed by a project participant (which may be Party A, Party B, design and supervision consultant or relevant management department) and countersigned by all project participants is called the project site visa.