Performance Commitment Letter 1 20xx On July * *, a production scheduling meeting was held in the project management department of * * contract section. * * Project Manager * *, Chief Engineer * *, Resident Engineer * * and Management Office * * of the Contract Section attended the meeting. According to the spirit of Fujii Expressway contractors' meeting and project management work meeting organized by the project office on July 10, 20xx, and the working goal of "working hard 100, vigorously promoting standardization construction", combined with the characteristics of tight time, heavy task, high standard and great difficulty of this project, the project manager * * represents the * * contract.
I. Pulling and hardening of vertical and horizontal construction access roads (steel trestles a2, a7 and a8) have been completed. The percentage of the total mileage of * * kilometers is * *, and the requisition of spoil ground has been completed (or it is planned to be completed on * * of 20xx). The whole contract section can be completed before 20xx * * to ensure concrete transport vehicles.
2. Construction of concrete mixing station, steel bar processing plant, small-scale cover slab prefabrication yard and beam slab prefabrication yard (attached with the plan of each temporary building)
The concrete mixing stations 1 and 1 are located at the pile number of * *, covering an area of * * square meters, the hardened area of * * square meters, the silo area of * * square meters, and the partition wall of * * meters high, which can store * * cubic materials. The mixer is of * * type, with an output of * * cubic meters per hour and * * sets.
The webmaster is * * *; No.2 concrete mixing station is located in pile * *, covering an area of * * square meters, with a hardening area of * * square meters, a silo area of * * square meters and a partition wall of * * meters high, which can store * * cubic materials. The mixer is a * * model, producing * * cubic meters per hour, * * concrete truck and * * concrete pump truck, which are mainly used for
2. The CNC steel processing machine arrived at the site on xx, xx, 20xx. 1 steel bar processing plant is located at the pile number of * *, with an area of * * square meters and a hardened area of * * square meters, mainly providing steel bar processing for * * structures. On * * month * day of 20xx,No. 1 steel processing plant team * was completed and put into use. The second steel processing plant is located in pile * *, with an area of * * square meters and a hardened area of * * square meters. Mainly for * * structure to provide steel processing. Completed and put into use before 20xx * *, the second steel processing plant has a team of * * * people, including * * skilled workers and * * factory director.
3. The small-scale cover plate prefabrication yard is located at the pile number of * *, covering an area of * * square meters and the hardened area of * * square meters. It was built and put into use 20xx years ago. There are * * people in the small cover panel team, and the person in charge is * * *. All small cover panels were produced in * * month of 20xx. 4. 1 Bridge Precast Yard is located at the pile number of * *, covering an area of * * square meters, with a hardened area of * * square meters, including * * T-beam base and * * sets of T-beam formwork, and the bridge produces * * T-beams, with an average annual output of * * T-beams of 20xx. The average daily production of * * plates and beams was completed before * * day of * * year, and the first plate and beam was produced on * * day of * * month, 1 Liang Chang * * team.
The field length is * *; The second bridge prefabrication yard is located at * * pile number, covering an area of * * square meters, with a hardened area of * * square meters, including * * T-beam bases and * * sets of T-beam templates. * * * The bridge will produce * * T beams, and the average daily production of * * T beams will be completed before 20xx.
Three. Sign a contract for the supply of raw materials (the contract agreement is attached to the signed contract)
1. At present, there are * * steel manufacturers that have signed contracts, and there are * * companies that plan to sign contracts on * * of 20xx.
2. There are * * cement manufacturers that have signed contracts, and there are * * cement manufacturers that plan to sign contracts on * * in 20xx.
3. At present, * * manufacturers have signed the external additives, and * * manufacturers plan to sign the 20xx * *.
….
Four, subgrade earthwork construction arrangement
Subgrade 1 work area: the length of work area is * *, the site technical director is * *, and the site management personnel is * *, so it needs to complete * * million earthwork. The main supporting machinery includes * * excavators, * * loaders, * * bulldozers, * * road rollers, 65438+20xx graders and * * dump trucks.
Subgrade 2 work area: the work area is * *, and the on-site technical director is * *, which is used for on-site management.
* * Personnel, * * The main machines that need to complete * * 10,000 earthwork are: * * excavators, * * loaders, * * bulldozers, * * road rollers, 1 graders, * * dump trucks ... It is estimated that earthwork will be completed every month and every day for 20xx years.
….
Five, the bridge pile foundation and substructure construction arrangement
1 team, bridge pile foundation and substructure 1 team: team leader * *, site technical director * *, site management personnel * *. * * * There is a * * bridge with a * * pile foundation, * * * needs a * * drilling rig, and the existing * * drilling rig is planned to arrive at the * * drilling rig on * * month, * * * needs * * kilowatts of electricity, and the temporary electricity consumption has been completed (or connected) * * kilowatts, and the self-provided generator set is * *. * * * There are * * caps, * * piers, * * capping beams and * * caps on the bridge substructure. * * * has * * equipment: * * crane * * platform, formwork * * square meters, steel pipe support * * tons.
2. The second team of bridge pile foundation and substructure: the team leader is * *, the on-site technical director is * *, and the on-site management personnel is * *. * * * There is a * * bridge with a * * pile foundation, * * * needs a * * drilling rig, and the existing * * drilling rig is planned to arrive at the * * drilling rig on * * month, * * * needs * * kilowatts of electricity, and the temporary electricity consumption has been completed (or connected) * * kilowatts, and the self-provided generator set is * *. * * * There are * * caps, * * piers, * * capping beams and * * caps on the bridge substructure. * * * has * * equipment: * * crane * * platform, formwork * * square meters, steel pipe support * * tons.
Six, circular pipe culvert, cover channel construction layout
1, round pipe culvert: the team leader is * *, the technical director is * *, the site construction personnel is * *, * * needs to complete * * round pipe culvert, and the existing equipment is * *, which is planned to be completed every * * days1; The leader of the second group is * *, the technical director is * *, and the on-site construction personnel are * *, so it is necessary to complete * * circular pipe culvert, and the existing equipment is * *, and it is planned to complete 1 culvert every * * days.
2. Cover channel: the team leader is * *, the technical director is * *, and the site construction personnel are * *, so it is necessary for * * to complete the cover channel. The existing steel formwork is * * square meters and the steel pipe supports * * tons. It is planned to complete foundation 1 and wall 1 every * * days. The second team leader is * *, the technical director is * *, and the site builder is * *, so it is necessary for * * to complete * * to cover the passage. The existing steel formwork is * * square meters and the steel pipe supports * * tons. It is planned to complete foundation 1 and wall 1 every * * days.
….
VII. Commitments for unfinished construction tasks
If the above commitments are not completed on the time node, I voluntarily invite the legal representative of the unit to Fuji Project Office and Section A Project Management Office on **20xx to explain the reasons and make reasonable adjustments to the organizational structure and construction organization design of the project management department. If the site has not been greatly improved within 20 days after the arrival of the legal representative, and it has not been recognized by the supervision engineer, I will request the headquarters of * * Company to change the project manager and leave Fuji Expressway automatically on the grounds that I am not competent for the employee.
Commitment: (signature)
Reference:
In order to protect the legitimate rights and interests of migrant workers and not default on their wages, I solemnly promise as the legal representative or authorized representative of (company name):
The project undertaken by our unit will ensure that:
1. Abide by the national laws and regulations on engineering construction, consciously maintain and standardize the order of the construction market, abide by the law in good faith, hire and use migrant workers in accordance with the provisions of the labor law, and their wages will be paid directly to the migrant workers themselves. After receiving the project payment, pay the wages of migrant workers first. Handle industrial injury insurance for migrant workers when hiring and using them.
2. Contracted projects shall not be subcontracted, illegally subcontracted or linked, and the illegal employment mode of "contractor" shall be put an end to.
3. In case of arrears or illegal deduction of wages of migrant workers, which leads to emergencies or public events such as migrant workers' petitions, our unit is willing to accept the punishment of the owner and other punishment decisions made by the competent authorities in accordance with relevant regulations.
Commitment unit: (official seal)
Legal representative or authorized agent (signature):
Date: Year Month Day
Zhangqiu Municipal Government Procurement Center Performance Commitment Letter 3:
If we win the bid for street lamp equipment (not ZQDL-20xx-008), our unit promises to fulfill all the responsibilities and obligations before signing the contract according to the requirements of the bid-winning notice after receiving the notice of winning.
If we breach the contract, we are willing to pay you 30% of the amount involved in the breach of contract as liquidated damages within 5 days; We are willing to obey the opinions on handling the facts of breach of contract and promise to bear all the consequences and responsibilities caused by our breach of contract.
Hereby promise!
Bidder ((official seal): Yangzhou Xinghui Lighting Co., Ltd.
Authorized person/agent (signature or seal):
Tel: 05 14-4xxx999
Chuan Zhen: 0514-42xxxxx9
Commitment date: April 20, 2006
Performance Commitment Letter 4: Name of the Tenderee
As the applicant of the project name supervision bidding, our company solemnly promises that there will be no fraud, serious breach of contract and major engineering quality problems in the past three years. If the tenderer or the bidding administrative supervision institution with jurisdiction discovers and verifies that our company has extracted false information on the above matters, regardless of whether the tenderer or the bidding administrative supervision institution with jurisdiction has legal punishment basis, our company will unconditionally give up the bidding qualification and bid-winning qualification of this project; If our company has received the bid-winning notice, our company unconditionally recognizes that the bid-winning notice of this project received by our company is an invalid document, which is not legally binding on the bidder, and any consequences and losses caused thereby shall be borne by our company. This commitment has corresponding independence. Whether there are other explanations to the contrary or not, this commitment is an effective part of our bidding documents, an expression of our company's true meaning, and always has priority legal binding force on any behavior of our company related to this project.
Commitment: (Seal)
Legal representative: (seal or signature)
20xx year month day
Letter of Commitment for Performance Article 5 Party A: (hereinafter referred to as Party A)
Party B: (hereinafter referred to as Party B)
In order to promote the legal construction of projects, strengthen project management and enhance the advantages of enterprise groups. Through friendly negotiation between Party A and Party B, based on the principles of mutual assistance, mutual benefit and common development, Party A will set up a project department, and the partners must make the following commitments:
1. In the contract price, Party B confirms that the following factors and expenses have been comprehensively considered and included in the total contract price:
(1) Party B confirms all temporary land occupied by the project (temporary access roads, prefabricated factories, living quarters, etc.). ) included in the total contract price, the total cost of the contract; Party B is responsible for the coordination of temporary land occupation, lease, cultivated land and greening.
(2) The contractor's equipment insurance and employee personal accident insurance shall be insured by Party B, and the insurance premium shall be borne and paid by Party B, which has been included in the total contract price;
(3) The taxes and fees that Party B needs to pay during the implementation of this contract project (except the taxes and fees for materials supplied by the project department and the taxes and fees withheld by the owner) have been included in the total contract price;
(4) Due to the tight construction period of this project, the cost of various quality assurance measures taken by Party B to ensure the project quality in winter, rainy season and night has been included in the total contract price;
(5) The spoil ground shall be determined by Party A through coordination and bear the expenses. When signing the contract, Party B has fully considered the transportation distance and other factors, and the relevant expenses have been included in the total contract price;
(6) The construction access road, temporary water use and temporary electricity use (except for the installation of construction electricity facilities required by Party A) during the construction period have been included in the total contract price;
(7)
(8) The expenses related to the main line crossing rivers and roads have been included in the total contract price; During the execution of this contract, Party B has fully considered the influence of labor, materials (except materials supplied by the project department) and equipment price increase on the project cost, and has included it in the total contract price;
(9) All risks of construction project and third party liability insurance in the project shall be insured by Party A, and Party B shall fully accept it.
2. Party B shall pay a performance bond of 1% of the contract project cost to Party A before entering the site for construction. The deposit will be refunded in three times two months after Party B puts in the personnel and mechanical equipment needed for construction according to Party A's requirements, and it is not allowed to leave without Party A's consent. In this case, Party A has the right to deduct the performance bond paid by Party B. ..
3. After Party B enters the site, the representatives of both parties will set up a quantity verification team to carefully check all the quantities in the bill of quantities of this bid according to the approved construction drawing design documents and the actual situation of the project. After the bill of quantities is verified and revised, it shall be signed by the representatives of both parties, and the revised bill of quantities shall replace the original bill of quantities. Party B totally agrees.
In order to protect the common interests of both parties, Party A thinks that there are many unreasonable quotations in Party B's contract price, and decides to adjust the unit price of contract quantities based on the bill of quantities of both parties' contract prices, and replace the original bill of quantities with the adjusted bill of quantities.
Express complete agreement.
4. If there is a list unit price for new and changed projects, it shall be executed according to the unit price of contract signing; If there is no list unit price, Party A will charge a management fee of 65438+ 02% of the total project price. The newly added and changed engineering projects have passed the acceptance of Party A, the supervisor and the owner, and the change data have been submitted completely according to the owner's requirements, and the settlement will be made after measurement approval.
5. Party B shall settle debts such as local materials, machinery fees and wages of migrant workers. Otherwise, after verification, Party A has the right to deduct the unsettled part from the project payment for payment.
6. If there is a construction project arranged by the owner in the contract list signed by both parties, the project (such as expansion joint and waterproof layer, etc.). ) must be excluded from the original contract according to Party A's arrangement.
7. Party B shall implement the relevant project management measures formulated by Party A (such as quality management measures, safety management measures, project acceptance measures, labor competition plans, etc.). ).
8. This commitment letter has the same legal effect as the target responsibility letter, and will take effect immediately after being signed by both parties.
9. This undertaking is made in triplicate. Party A holds two copies and Party B holds one copy.
Party A: (Seal) Party B:
Representative: representative:
Date: Year Month Day
Performance Commitment Letter 6: Name of the Tenderee
As the applicant of the project name supervision bidding, our company solemnly promises that there will be no fraud, serious breach of contract and major engineering quality problems in the past three years. If the tenderer or the bidding administrative supervision institution with jurisdiction discovers and verifies that our company has extracted false information on the above matters, regardless of whether the tenderer or the bidding administrative supervision institution with jurisdiction has legal punishment basis, our company will unconditionally give up the bidding qualification and bid-winning qualification of this project; If our company has received the bid-winning notice, our company unconditionally recognizes that the bid-winning notice of this project received by our company is an invalid document, which is not legally binding on the bidder, and any consequences and losses caused thereby shall be borne by our company. This commitment has corresponding independence. Whether there are other explanations to the contrary or not, this commitment is an effective part of our bidding documents, an expression of our company's true meaning, and always has priority legal binding force on any behavior of our company related to this project.
Commitment: (Seal)
Legal representative: (seal or signature)
20xx year month day
Article 7 The book bond of performance commitment shall be used as the performance bond for the construction project (tender number: 20xx-GC-G-026) of the land consolidation project (Phase II) of four towns in Pingyu County signed by Henan Taihui Construction Engineering Co., Ltd. (name of bidder). 10% of the bid amount in the performance guarantee amount.
1, the contractor guarantees to submit the performance bond to the employer at the same time as receiving the letter of acceptance. The amount of the performance bond is ten percent (10%) of the contract price. The balance of the performance bond will be returned to the contractor within thirty (30) days after the project is completed, accepted by the relevant departments and signed a written conformity report, without interest.
2. The performance bond shall be transferred in cash.
3. If there is a contract dispute at this time and it cannot be resolved, the validity of the performance bond shall be extended until the above dispute is finally resolved and the settlement is completed.
4. Without the consent of the Employer, the project manager and technical director shall not be replaced. If the replacement is not approved, the penalty will be deducted from the performance bond. If the project manager is replaced, the penalty of 10000 yuan will be deducted. If the technical person in charge is replaced, a penalty of 5,000 yuan will be deducted.
Name of bidder (contractor): (official seal of the company)
Bank account number:
Bank address:
Bank phone number:
Legal representative or authorized representative: year (signature)
Performance Commitment 8: Name of the Tenderee
As an applicant for project supervision bidding, our company solemnly promises that at this stage, our company is not in a state of being ordered to suspend business, disqualified from bidding, taken over, frozen or bankrupt. If the tenderer or the bidding administrative supervision institution with jurisdiction discovers and verifies that our company has extracted false information on the above matters, regardless of whether the tenderer or the bidding administrative supervision institution with jurisdiction has legal punishment basis, our company will unconditionally give up the bidding qualification and bid-winning qualification of this project; If our company has received the bid-winning notice, our company unconditionally recognizes that the bid-winning notice of this project received by our company is an invalid document, which is not legally binding on the bidder, and any consequences and losses caused thereby shall be borne by our company. This commitment has corresponding independence. Whether there are other explanations to the contrary or not, this commitment is an effective part of our bidding documents, an expression of our company's true meaning, and always has priority legal binding force on any behavior of our company related to this project.
Commitment: (Seal)
Legal representative: (seal or signature)
20xx year month day
Performance Commitment Article 9 Performance Commitment
To: No.2 Work Area of Zhang Tang Railway Project Manager Department of China Railway 14th Bureau Group Co., Ltd.
We voluntarily reached an agreement with your company (hereinafter referred to as "Party A") on the construction labor cooperation of the second work area project of Zhang Tang Railway Project Management Department of China Railway 14th Bureau Group Co., Ltd., and made the following commitments.
1, ensure that the project undertaken is not subcontracted or subcontracted, otherwise it will be regarded as our breach of contract, and the performance bond paid by us can be confiscated as a fine.
2. Ensure to obey the leadership, scheduling and coordination of Party A, and handle the cooperative relationship with adjacent construction units. If the construction scheme, construction period, etc. are changed. Or our reasons, we will obey Party A's adjustment of our tasks.
We promise that there is no need to pay the advance payment for this project. In the process of project payment, if the owner fails to allocate funds to Party A on schedule, the funds allocated to us by Party A can be postponed by the same amount. The appropriation is based on the monthly work inspection, and we provide the monthly work inspection and valuation data in time, and agree that the work inspection and valuation is the payment for qualified and excellent projects, which shall be calculated according to the number of projects approved by Party A and shall not exceed the construction drawing.
4. For each day of delay in the construction period, the liquidated damages shall be 0.1‰ of the contract price; If it is more than 5 days, the construction period will be punished at 0.5‰ of the contract price for each day of delay; If it is over 10 days, Party A has the right to terminate the contract and settle the completed workload at 5% lower than the contract price.
5. During the execution of the contract, if we can't guarantee the quality, safety and progress, Party A has the right to terminate the contract unilaterally without bearing any economic and legal responsibilities; We promise to leave the construction site within the time specified by Party A and compensate the losses caused to Party A from this.
6. I am willing to sign the contract in the form of comprehensive unit price contract agreed by both parties, and promise not to adjust the price during the execution of the contract.
7, our project director and technical director, according to the agreed time in mechanical equipment. If the project director and technical director delay entering the site, they will be punished for delaying the entry of major equipment and personnel, that is, each person will be fined 500 yuan every day, mechanical equipment will be delayed entering the site, and each machine will be fined 500 yuan every day. The amount of the fine is deducted from the performance bond of the contract. The fine is only a means, and it does not exempt our personnel and mechanical equipment from the responsibility of continuing to enter the site.
8. Our project leader guarantees that he will be at the construction site for a long time, and his vacation must be submitted to the site leader of Party A for approval. If you don't show up at the scene without reason, you will be fined 500 yuan every day, which will be deducted from the performance bond of personnel.
9. We promise to do the following in terms of engineering quality:
(1), the engineering quality conforms to the construction specifications, regulations, quality standards and engineering construction standards issued by the Ministry of Railways, and it shall be inspected by the construction unit and supervision engineer, and the visa formalities for concealed works shall be handled well.
2, must meet the technical requirements specified in the design.
(3) The quality standard of this project is the current excellent engineering standard of the Ministry of Railways, and the quality target is the high-quality project of the Ministry of Railways, striving for the national excellence award.
(4), engineering quality warranty and maintenance methods, according to the provisions of the state and the Ministry of Railways industry.
5], completed according to the ministerial acceptance standard acceptance, a unit project qualified rate reached 100%, meet the requirements of building engineering excellence planning.
[6], such as quality can not meet the acceptance criteria, all the losses caused by this shall be borne by our unit.
10, we promise to bear all economic and legal responsibilities for the safety accidents caused by our reasons and properly handle the aftermath; Party A will never be affected by improper handling of the aftermath of the accident. Otherwise, we will bear the economic losses and related legal responsibilities caused by improper handling.
165438+
(1), we compiled a team and brought it into the unified management of Party A; According to the requirements of Party A, the dressing personnel and mechanical equipment shall be uniformly identified. Personnel shall receive education and training organized by Party A before taking up their posts, and take up their posts with certificates after passing the examination.
(2) All laborers sign labor contracts with our company, register them, prepare monthly payroll and submit it to Party A for review; And ensure that under the supervision of Party A, the wages of migrant workers are paid in time according to the requirements of the local labor department and Party A's regulations on the management of migrant workers' wages; In case of default of service fee, we promise that Party A has the right to terminate the service contract, deduct the performance bond and other payables paid by us as the payment of service fee, and bear all economic losses and legal responsibilities caused thereby.
(3) We promise that all risks of ground materials and auxiliary materials purchased by ourselves will be borne by us, and Party A will not be affected by disputes caused by materials purchased by us after the project is completed. Any economic and legal responsibilities arising from the ground materials and other small materials and machines purchased by us will be borne by us.
12. We agree that all main materials and special materials (including but not limited to concrete, cement, sand, crushed stone, steel bar, concrete admixture, flaky, steel strand, anchorage and corrugated pipe) shall be purchased by Party A through bidding, and the suppliers of self-purchased materials shall be approved by Party A, and Party A has the right to designate suppliers when necessary.
13. During the construction, our consumption of materials provided by Party A shall not exceed the material quota.
If it is exceeded, we promise that Party A will deduct the excess material consumption from Party B's current settlement price by × 1 10% of the market price.
14. We are willing to unconditionally obey Party A's construction environmental protection and soil and water conservation measures; Occupational health and safety protection measures; Labor organization plan; Civilized construction, cultural relics protection and a series of measures conducive to the project.
15. If we can't achieve the phased construction period or meet the quality standards as required by Party A, Party A has the right to adjust the scope and quantity of our project and replace the construction labor operation team. We promise to leave the construction site on time, and all our temporary equipment or mechanical equipment will be provided to Party A free of charge until the project is completed and returned without paying any fees.
16. We understand that the owner's fund allocation is not in place, which will affect the land acquisition and demolition, delay the provision of design change documents, and promise not to affect the progress and quality of the project.
17. We promise that the comprehensive unit price will not be adjusted once the contract is signed. If there is any loss, we will bear it ourselves, and only need to keep a copy of the work content of the construction project in the construction labor contract; For the losses caused by the third party, we promise to consider compensation only after the construction unit approves the compensation expenses of Party A, and it will not exceed the approved expenses of the construction unit. If the construction unit refuses to approve, no compensation is needed; If the change cost increases during the construction, we promise to consider compensation only after the construction unit approves the change cost of Party A, and it will not exceed the cost approved by the construction unit. If the construction unit refuses to approve the change fee, there is no need to compensate.
18. We guarantee that during the construction process, our personnel will not make trouble, make trouble, or contain the project department, mixing station, vehicles and personnel of Party A in Party A's work area. Otherwise, Party A has the right to terminate the contract immediately, or even submit the construction contract to the court where Party A's legal entity is located for prosecution. At the same time, we will bear all economic and legal responsibilities and guarantee to leave the site within 24 hours.
19. During the performance of the contract, we promise not to abuse, insult personality, personal attack or other illegal and criminal acts against Party A's staff at any time and any place. In case of conflict due to our reasons, Party A will refuse to contact all our work and confiscate the performance bond paid by it. If the circumstances are serious, the public security and judicial organs where Party A's legal person institution is located shall make a judgment.
20. This letter of commitment is one of the main contents of the Project Construction Labor Cooperation Contract.
Commitment:
Xx, xx, 2000
Performance Commitment 10 Fire fighting project consists of fire alarm system, automatic sprinkler system and fire hydrant system. With the aim of "reasonable price, quality assurance, excellent service and reputation first", relying on the strict internal management of the company, we will carry out technical checks in accordance with relevant specifications, carefully organize construction plans and personnel, and ensure the project quality to be completed on schedule. And on this basis, make the following service commitments:
1. The price of equipment and materials provided by this project and the rate of installation and commissioning are calculated according to the most favorable charging standard based on the 20xx quota.
2. In the process of engineering construction, if there is any contradiction or inconsistency between the engineering drawings and the relevant fire protection codes, timely point out and put forward reasonable suggestions to Party A and the design department, and then carry out the construction after approval, so as to make the engineering materials and labor force get the most reasonable configuration.
Three. In the process of fire control audit and declaration of this project, if there are any specific problems that are difficult to solve, our company will assist Party A to handle them reasonably and properly, so as to meet the requirements of the code, solve the specific problems, and obtain the unanimous opinion of all parties.
Four, after the completion of the project, our company is responsible for fire detection declaration (declaration form and other information will be filled in by you with the assistance of our company) and submitted to the relevant fire supervision department for acceptance.
Five, after the project completion acceptance and delivery, our company is responsible for the free repair and maintenance of fire control facilities within two years to ensure the normal operation of the equipment. After receiving the fault notice, send someone to eliminate it within 24 hours and patrol once every quarter.
Six, after the completion of the project, Party A is responsible for the operation of fire control facilities, and compulsory training for management personnel, imparting professional knowledge, so that they can operate correctly and eliminate common obstacles.
Seven, to assist the operation and management personnel to formulate the maintenance and maintenance system of fire control facilities.