Summary of site construction management (1) At the end of the year, xx project department has been stationed in the site for more than a year, and I have gone through another year's work with the growth of the project department. Looking back on 20xx, it was a tense year and a full year. This year, I completed the transformation from a newly graduated student to a road and bridge worker. Through one year's study and practice, my professional skills and construction management have been greatly improved.
After a year of construction practice, I have my own understanding of construction management, and combined with the actual situation, I make the following summary of construction management:
1, according to the requirements of the construction production plan, decompose the quantities completed each month, and issue production tasks to the team at the beginning of the month. Organize the leaders of each shift of the construction team to hold a meeting, analyze the problems that may be encountered in the production this month (considering factors such as labor, materials and machinery), and take effective measures as soon as possible to ensure the smooth completion of the construction task.
2, adhere to the weekly production meeting. Summarize the work done this week and analyze the problems. Arrange the work tasks for next week. Make necessary optimization of the construction plan to ensure the completion of monthly production tasks.
3. Strengthen the construction quality control. Establish a construction file for each beam, and record all the data in the process of prefabrication and erection of the modified beam and slab. See the attached table for the format.
4. Standardize the construction procedures. First of all, organize the construction team and the heads of each team to hold a meeting to clarify the correct construction procedures and inspection procedures of each working procedure, emphasize the key points of quality control of each working procedure, and formulate corresponding punishment regulations accordingly. At the same time, the safety technical disclosure shall be made to the workers involved in the first-line construction, so as to eliminate the problem of irregular construction from the root.
5. Strengthen the analysis of the team's business activities and regularly count the expenses incurred by the team during this period, including labor, materials and other expenses. The statistics of labor force will be based on the actual attendance of the construction team in daily construction and the monthly supervision of wage payment to obtain data; Material analysis will establish a material account, record the planned quantity and quantity of various materials in construction, and analyze the material cost in combination with the completed quantities. Other expenses will be obtained by reviewing the loan from the construction team. We will strictly examine the lending of funds. Before borrowing money, the person in charge of the construction team should submit the fund use plan, as well as the bills and vouchers of the expenses incurred from the last loan to this loan. Through the statistics of the above three aspects, the total cost of the construction team is calculated, and its cost is calculated and its profit and loss are analyzed in combination with the amount of work completed.
6. Establish a reward and punishment system and improve management. In the case of clear rules and regulations and punishment provisions, the violators will be criticized and educated according to the seriousness of the case, and the relevant personnel will be fined. Under the premise of actively cooperating with the project construction and ensuring the quality, the situation of exceeding the production task should be reported to the project leader for reward.
7. Pay special attention to safety and civilized construction. Safety is no small matter. In daily construction management, constantly strengthen the safety awareness of workers and cultivate safety habits. For the parts with potential safety hazards, a written notice shall be issued in time for rectification within a time limit. Safety work should be people's responsibility, avoiding the phenomenon of buck passing.
8. Summarize your work in stages. Summarize the gains and losses of the work for a period of time, and put forward the key points and objectives of the next work.
The most important thing in management is execution. It is necessary to improve the quality of the project through management, standardize the construction procedures and speed up the construction progress. Looking back on the work in 20xx years, it is found that there is a great deficiency in the implementation of management, which leads to the arbitrariness of the construction team in the prefabrication yard and many cases of unauthorized construction without notice or inspection. In the future work, we will focus on the implementation of management, clarify the management system and standardize the construction procedures. Strict requirements to prevent such urban incidents from happening again. Really "warm service, synchronous guidance and strict management" and truly perform their duties.
Summary of site construction management (2) In a blink of an eye, the ordinary but not too busy year is over. Time flies unconsciously, and the calendar of xx years will be turned over without interest. With the pace of the times, reviewing the stormy course experienced in the past year and the shortcomings in my work, I made the following work summary:
First, pragmatic work, self-pressure, serious work, gains and losses.
The first half of xx is worth celebrating. The first residential project I started to participate in has been completed. We pay attention to quality and progress in order to finish it within the specified time. At the same time, I learned some construction procedures, including some detailed structures of drawings, some detailed practices stipulated by the company, and the arrangement of technical data. Including dealing with people, have greatly improved and accumulated some experience for themselves.
After the main body construction is completed, it mainly participates in the setting-out of masonry, the planting of Rachel bars and the final acceptance of masonry. In the later stage, it is mainly to cooperate with Party A's personnel and supervision to do household acceptance and copy the elevation of outdoor sewage pipes. General work maintains an atmosphere. As a novice, there are many mistakes and rework, but I will learn lessons, look at the drawings carefully and consider the problems comprehensively. We will never let the same problem happen again.
In the second half of the year, new projects started. Located in Weihai High-tech Zone, there are three small high-rise buildings, three multi-storey buildings and a big garage. Due to the shortage of technicians, I am quite busy. Although I am busy, I am very happy and confident in myself. Because this is my first project from foundation laying to final capping, I am looking forward to it.
Second, the work should have a sense of responsibility and arrange the work reasonably.
Here, the knowledge learned in the first half of the year has been consolidated and deepened. Better understanding: learn more while you are young. In my spare time, I will spend some time reading brochures and atlases. The only drawback is that the work is not planned. As the saying goes, there are gains and losses. After summing up my work for one year, I realized the importance of the work plan. Reasonable arrangement of work can greatly improve work efficiency and make the work go smoothly. The statistics of data should proceed from reality, take the calculated amount as a reference, and report the data after many discussions and confirmation to ensure the accuracy of the data. Have a sense of responsibility, carry forward the management spirit of "three diligence", read more books, ask more questions and check more. Only in this way can we better find the problems in the project and take timely measures to solve them.
In the future construction process, we should not blindly carry out the construction according to the drawings, but also take into account the actual situation at the scene and report to the leaders in time if there are any problems. Only in this way can construction problems and rework be reduced. Finally, no matter what you do, you must have a correct and positive attitude. Attitude is everything.
Third, learn from the failure of xx years, make yourself achieve better results in xx years, and reduce rework and maintenance to improve yourself. I make the following suggestions:
In the spring of 1 and xx, Rachel reinforcement will be planted and masonry plastering will be carried out. At this time, we must be cautious and optimistic about the survival of the drawings, and we must not rework, forget, or leave the tail behind.
2, the main body construction, must be serious, serious, starting from the overall situation, control the floor elevation.
3, floor elevation control, pay-off, finally to line comparison.
4, completes the technical disclosure.
5, can't be young and energetic, and do a good job in interpersonal relationships.
Summary of on-site construction management (3) As a technician in the management department, I worked around xxx project from the beginning, and after two years of tempering, I embarked on an all-round growth highway. The main work during this period is: xxx project completion data (project entity data, quality assurance data, special construction plan preparation).
I am persistent, sincere, step by step, watering this hard-won job with painstaking efforts, interpreting my love and obsession with construction projects with actions, taking every task seriously and enriching every day. In the past two years, I have gained too many professional technical papers, the successful application of national patents, and the relevant procedures from the beginning to the completion of the project. At this point, I deeply realized that I have been talking about engineering in my life and architecture for the rest of my life. Since then, I have started a new journey of life around work.
At this point, when summing up the project management work, I thank the company for giving me this stage and the fertile soil for nutrition. The following is a summary of my project management work in the past two years, reporting and reflecting to colleagues and leaders.
First, integrate into the management department
Society is a comprehensive classroom to hone life. Leaving the simple and transparent school life, I set foot on my job and put on my work clothes. I feel responsible. In the face of this work that can't be sloppy at all, and my theoretical but empty work experience, I always remind myself: "Be a man in advance, be a man first." In my daily work, smiling and politeness are the ways I get along with Chinese stars I meet anywhere. I respect everyone on the construction site. Construction engineering is a comprehensive specialty, involving a wide range. If you want to grow up in an all-round way, you must consult many old engineers. Smiling and polite, I quickly integrated into the project management department, respected leaders and colleagues in my life, and actively helped everyone deal with some computer software and hardware problems at work. It was recognized by everyone in a short time.
No matter how difficult the problems encountered in the next project are, I will get careful guidance from my seniors, and the pace of growth will be accelerated by nitrogen. Enthusiastic treatment of every uncle and aunt in the operation team is also the key to my rapid improvement of engineering practice experience. I have always thought that there is no difference in academic qualifications in communicating on the project site. For the workers who have worked hard in the construction site for many years, they are very aware of all the details that should be paid attention to in the project. Their careful communication with you has made me understand many urgent problems in the project, which has provided valuable value for me to get inspiration and first-hand information in the process of patent research. The reason to be a man in advance is very simple, and everyone understands it. The real trick is: willing to serve your enthusiasm, your careful thinking, and your young execution.
Two. Overview of professional work
1, project completion data
The preparation for a concrete pouring (pouring sequence, inspection lot of six projects, steel bar concealment) has gone through too many ups and downs from ignorance at first to familiarity now, from a message to 3 hours and 20 minutes now. The local attributes of the data form, descriptions of the information of unit project, sub-unit project, sub-division project, sub-division project and concrete design, the pouring position and mixture ratio in the form, the determination of inspection lot time of each sub-project, the relevant contents in the inspection lot form should be filled in comprehensively and accurately according to the actual situation of the project, the information records of qualified and standardized use of steel bars in the inspection form of engineering concealed information, and the explanatory diagram of hidden drawings of steel bars.
2, safety technical disclosure.
Excellence begins with "standardization". With the leap-forward development of the company, we have a set of standard working system, which has spent a lot of efforts of old engineers. Learning this standard process well and implementing this file format well will make our work professional, efficient and standardized. With the progress of engineering construction, safety technical disclosure and technical disclosure of sub-projects and sub-projects must be carried out in advance. Technicians, as compilers and professors of safety technical disclosure and technical disclosure, should not only meet the requirements of relevant specifications of each division and sub-project, but also provide detailed and targeted solutions to practical problems on the project site, and the forms used for disclosure should meet the requirements of local acceptance data specifications. In addition, attention should be paid to communication methods when making disclosure to workers on site, and explanations must be made in a language that workers can understand and an acceptable attitude, so that they can truly accept their own technical measures after disclosure and can be well applied to engineering construction.
4, bidding quantity calculation, technical standard preparation
As technicians, we need to clearly understand: "The accuracy of engineering quantity is the basis of winning the bid, the special technical scheme and the allocation of human resources are the project cost, and we are the decision makers of project profits."
It is our honor to receive the invitation to bid, and it is our professional quality as technicians to accurately calculate the engineering quantity. In order to fully understand the meaning of a drawing, we must carefully calculate the quantities in the structural construction drawing and construction drawing. Cooperate with ministry of materials and equipment and Equipment Department to bring local
If the market price is well investigated, we will have a good grasp of the initiative of the project cost, so we will not bid blindly. In this fierce bidding market competition, know yourself and know yourself. After the engineering quantity calculation of a project is completed, the engineering details of the project will be fully understood, and when preparing the technical tender, what technical scheme to implement and what technical measures to choose for the related partial projects will be targeted. We will be handy and fully prepared in the aspects of turnover materials, manual stationing, mechanical configuration and schedule planning. Combined with the requirements of the tender documents, the requirements are reflected in the technical tender. After the formation of the technical standard framework, we collectively solicited opinions, revised the binding, and treasured a heavy fruit.
After bidding for a project in a down-to-earth manner, the grand outline of the project will remain in our minds forever, and the concrete implementation after winning the bid will give us a refreshing sense of knowledge and intimacy.
Give full play to your innovative thinking and contribute to the rapid development of engineering economy.
Strive to serve the engineering construction with innovative methods. When you arrive at the construction site, you should form the work habit of carrying problems with you, often find problems, and be good at solving problems with new ideas after finding them. In the shantytown renovation project, I found four topics worthy of study, advocating to improve the efficiency of engineering construction by manufacturing new devices. After the research and demonstration of the experimental conclusion, I have completed the preliminary patent application for the bolt hole plugging device of shear wall, and submitted it to the branch for approval. The other targets are trying to explore solutions and are ready to apply for patents one after another. Among them, a steel bar flattening device won the "national patent". The related topics of building plastering fixture have been well studied. The technical paper was successfully published.
Third, deeply understand corporate culture and actively invest in corporate culture construction.
During my work, I pay attention to the corporate culture of the company from all directions and angles, and often learn and understand it through the internet and internal magazines. Take the initiative to record the feelings of the construction site in words, give full play to their own advantages in words, draft relevant external documents of the project department, and report the deeds of the project department to the company in time in the form of a newsletter. During this period, more than 30 articles were collected by branches, and some were selected by xxx Group Company. Won the title of "excellent correspondent" of the branch in 20xx.
Fourth, the problems that should be paid attention to in the process of project management
1, construction of management team
The most important thing for a management department is the employees in this team. Whether our employees are United or not is a key issue. This key issue mainly depends on the correct leadership and example of the leadership of the management department. We need to focus on making every employee feel a sense of belonging and home, and then create benefits for the management department from the heart.
2, key, special division, special treatment of subdivisional work
Special attention and treatment should be given to the construction of special divisions and sub-projects (such as fire corridors), and delay is refused. When the solution is not perfect, the technicians can't handle it, and the technical director can't handle it. Report to the technical director of the project, one by one, and solve it in time without delay. This process needs special treatment, saving time, striving to be completed as soon as possible and not delaying the construction period.
3, material supply quality and quantity control
At present, there are many kinds of materials on the market, so shop around. Choosing high quality and low price materials is the first choice, which will bring benefits to our "future cost" and reduce the cost invisibly. The quantity should be strictly controlled, and the material loss in the project is normal, but it must not be used to make ingredients at will. Technicians should accurately calculate the quantity, material engineers should purchase as planned, and everyone Qi Xin should work together to strive for greater interests in this greatest interest.
4. Scientific control of machinery use
The builder needs100t crane today. Can we suggest that 60 tons is enough? If enough, try to use low-power machinery to avoid losses. Rent tower cranes, trucks, excavators, loaders, etc. Should be implemented after scientific discussion, so as to gather the strengths of all people and save profits.
5, labor subcontracting control
The control center of labor subcontracting should try to ensure that it is under the control of the management department. We should not choose the labor subcontracting that cannot be controlled. Choose carefully when choosing labor subcontracting.
6, reasonable arrangement process type of work
The construction period tells us that the process should not be chaotic, and the standard process should be scientifically broken when special needs arise. The delay of this roofing construction (too many rainy days in rainy season in 20xx), coupled with the external wall insulation construction arranged in the later period of 20xx, occupied the roofing, resulting in serious delay of roofing construction, which should be avoided scientifically in future projects. The scientific evasion and flexible application of engineering construction sequence will be an important guarantee for our construction profit, which needs careful consideration.